Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

CAPM Certified Associate in Project Management (CAPM) Questions and Answers

Questions 4

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

Options:

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

Buy Now
Questions 5

A project team has missed a milestone.

Which response strategy should be implemented?

Options:

A.

Communications

B.

Stakeholder

C.

Contingent

D.

Risk

Buy Now
Questions 6

Match each tool or technique with its corresponding Project Cost Management process.

CAPM Question 6

Options:

Buy Now
Questions 7

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 8

During the execution phase of a multibillion-dollar project, the project manager encountered performance issues with some of the team members. In a performance review meeting, the project manager noticed that the team members do not follow SMART objectives.

What are SMART objectives?

Options:

A.

Specific, measurable, accurate, relevant, and time-bound.

B.

Specific, measurable, achievable, relevant, and time-bound.

C.

Specific, measurable, accurate, realistic, and time-bound.

D.

Specific, measurable, achievable, realistic, and time-bound.

Buy Now
Questions 9

What is the purpose of an adaptive standup meeting?

Options:

A.

To review what work has been completed, remove impediments, and calculate velocity

B.

To ask the team what work has been completed, calculate velocity, and determine what work will be completed

C.

To ask the team what work has been completed, ask what work will be completed, and report impediments

D.

To update the burndown chart, calculate velocity, and report impediments

Buy Now
Questions 10

Which type of risk diagram is useful for showing time ordering of events?

Options:

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

Buy Now
Questions 11

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Buy Now
Questions 12

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Buy Now
Questions 13

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

Options:

A.

Risks should be considered when selecting the content of each iteration.

B.

Risks should be tailored for each iteration.

C.

Risks should be identified, analyzed, and managed during each iteration.

D.

Risks should be documented prior to each iteration.

E.

Risks should be reviewed only once during each iteration.

Buy Now
Questions 14

What important leadership quality/qualities should project managers possess?

Options:

A.

Skills and behaviors related to specific domains of project management

B.

Skills and behaviors needed to guide a team and help an organization reach its goals

C.

Industry expertise that helps to better deliver business outcomes

D.

Industry and organizational expertise that enhances performance

Buy Now
Questions 15

A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?

Options:

A.

Create a product backlog with the information depicted in the WBS and prioritize the newly developed user stories into iterations.

B.

Accept this limitation and perform accordingly since the WBS can only be used in Scrum iterations.

C.

Consider reforming the structure of the company first as it is difficult for a company to transition from predictive to adaptive methods.

D.

Save the WBS in the historical data as the information can only be used for educational purposes and not as inputs for creating user stories.

Buy Now
Questions 16

Which of the following are outputs of define scope process in project scope management

Options:

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project Scope statement and project documents updates

D.

Scope baseline and project documents updates

Buy Now
Questions 17

A project manager should communicate to stakeholders about resolved project issues by updating the:

Options:

A.

project records

B.

project reports

C.

stakeholder notifications

D.

stakeholder register

Buy Now
Questions 18

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Buy Now
Questions 19

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 20

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

Options:

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Buy Now
Questions 21

When closing a project or phase, part of the process may require the use of which type of analysis?

Options:

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Buy Now
Questions 22

An organization ' s project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?

Options:

A.

Organizational systems access

B.

Organizational process assets

C.

Resources management plan

D.

Procurement management plan

Buy Now
Questions 23

A key benefit of the Manage Communications process is that it enables:

Options:

A.

The best use of communication methods.

B.

An efficient and effective communication flow.

C.

Project costs to be reduced.

D.

The best use of communication technology.

Buy Now
Questions 24

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

Options:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Buy Now
Questions 25

When sequencing activities, what does the common acronym FF stand for?

Options:

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

Buy Now
Questions 26

The organization ' s perceived balance between risk taking and risk avoidance is reflected in the risk:

Options:

A.

Responses

B.

Appetite

C.

Tolerance

D.

Attitude

Buy Now
Questions 27

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Buy Now
Questions 28

Which are the main objectives of Project Risk Management?

Options:

A.

Increase the probability of positive risks and decrease the probability of negative risks

B.

Avoid all kind of risks

C.

Increase the probability of positive risks and eliminate all negative risks

D.

Identify positive and negative risks

Buy Now
Questions 29

Which of the following is provided by the critical path method?

Options:

A.

Schedule float

B.

Earned value (EV)

C.

Total float

D.

Schedule value

Buy Now
Questions 30

Which of the following processes are part of the Project Integration Management Knowledge Area?

Options:

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

Buy Now
Questions 31

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

Options:

A.

Interrelationship digraphs

B.

Tree diagram

C.

Affinity diagram

D.

Network diagram

Buy Now
Questions 32

What type of meeting is held to discuss prioritized product backlog items?

Options:

A.

Status

B.

Daily standup

C.

Iteration planning

D.

Release planning

Buy Now
Questions 33

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

Options:

A.

Expert judgment

B.

Interpersonal skills

C.

Team agreements

D.

Communication skills

Buy Now
Questions 34

Which technique helps to determine the risks that have the most potential impact on a project?

Options:

A.

Cost risk simulation analysis

B.

Expected monetary value analysis

C.

Modeling and simulation

D.

Sensitivity analysis

Buy Now
Questions 35

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

Options:

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Buy Now
Questions 36

Where are key project deliverables documented?

Options:

A.

Project management plan

B.

Requirements traceability matrix

C.

User acceptance criteria

D.

Work breakdown structure (WBS)

Buy Now
Questions 37

Which of the following is used as an input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Buy Now
Questions 38

Which tool should a project manager use to calculate cost variance for a project?

Options:

A.

Contingency analysis

B.

Review lessons learned from similar projects

C.

Expert judgment

D.

Actual cost

Buy Now
Questions 39

The following chart contains information about the tasks in a project.

CAPM Question 39

Based on the chart, what is the schedule performance index (5PI) for Task 4?

Options:

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Buy Now
Questions 40

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

Options:

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

Buy Now
Questions 41

A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?

Options:

A.

Life cycle approaches

B.

Resource availability

C.

Project dimensions

D.

Technology support

Buy Now
Questions 42

A regression line is used to estimate:

Options:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Buy Now
Questions 43

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

Options:

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Buy Now
Questions 44

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Buy Now
Questions 45

Which of the following is an example of the simplest fixed-price contract?

Options:

A.

Purchase requisition

B.

Purchase order

C.

Verbal agreement

D.

Request for quote

Buy Now
Questions 46

What process is used to identify quality requirements and/or standards for a project and its deliverables ' ?

Options:

A.

Manage Quality

B.

Plan Quality Management

C.

Control Quality

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 47

What is one of the main purposes of the project chatter?

Options:

A.

Formal authorization of the existence of the project

B.

Formal acceptance of the project management plan

C.

Formal approval of the detailed project budget

D.

Formal definition of stakeholder roles and responsibilities

Buy Now
Questions 48

The project manager is creating the communications management plan Which group of inputs Is required to begin?

Options:

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

Buy Now
Questions 49

Which characteristics do effective project managers possess?

Options:

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Buy Now
Questions 50

Which kind of communication should the project manager use when creating reports for government bodies?

Options:

A.

Hierarchical

B.

External

C.

Formal

D.

Official

Buy Now
Questions 51

In which Project Management Process Group is the project charter developed?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Buy Now
Questions 52

What is the project manager ' s responsibility in Project Integration Management?

Options:

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

Buy Now
Questions 53

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

Options:

A.

The development team ran out of time and did not pull the social media story from the backlog.

B.

The development team completed all of the stories identified by the product owner as having the highest customer value.

C.

The sprint demo went smoothly and the team did not find any open issues.

D.

The social media story is a marketing priority and less important than other priorities.

Buy Now
Questions 54

The stakeholder register is an output of:

Options:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Buy Now
Questions 55

Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?

Options:

A.

Project Schedule Management

B.

Project Scope Management

C.

Project Resource Management

D.

Project Integration Management

Buy Now
Questions 56

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

Options:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Buy Now
Questions 57

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

Options:

A.

-8000

B.

-2000

C.

2000

D.

8000

Buy Now
Questions 58

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Options:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Buy Now
Questions 59

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three)

Options:

A.

Many expected simple scope change requests

B.

Few expected simple scope change requests

C.

Routine and repetitive activities

D.

Collocated project teams

E.

Use of established templates

Buy Now
Questions 60

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Questions 61

What tool or technique can improve a products final characteristics?

Options:

A.

Design for X (DfX)

B.

Problem solving

C.

Process analysis

D.

Risk report

Buy Now
Questions 62

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Buy Now
Questions 63

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Close Project or Phase

D.

Perform Integrated Change Control

Buy Now
Questions 64

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Options:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Buy Now
Questions 65

A tool and technique used in the Develop Project Charter process is:

Options:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

Buy Now
Questions 66

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Buy Now
Questions 67

Inputs to the Plan Risk Management process include the:

Options:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Buy Now
Questions 68

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

Options:

A.

triangular distribution

B.

tornado diagram

C.

beta distribution

D.

fishbone diagram

Buy Now
Questions 69

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Buy Now
Questions 70

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

Options:

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7

Buy Now
Questions 71

What is the primary purpose of Project Scope Management?

Options:

A.

Determining and managing stakeholder needs

B.

Contorting the status of the product scope and managing changes to its be seine

C.

Defining and controlling what is and is not included in the project

D.

Differentiating between the product scope and project scope

Buy Now
Questions 72

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

Options:

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Buy Now
Questions 73

What purpose does the hierarchical locus of stakeholder communications serve?

Options:

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Buy Now
Questions 74

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Buy Now
Questions 75

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 76

The Define Scope process is in which of the following Process Groups?

Options:

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Buy Now
Questions 77

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

Options:

A.

Bottom-up estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Parametric estimating

Buy Now
Questions 78

Which type of organizational structure is displayed in the diagram provided?

CAPM Question 78

Options:

A.

Balanced matrix

B.

Projectized

C.

Strong matrix

D.

Functional

Buy Now
Questions 79

Which tool or technique is used to manage change requests and the resulting decisions?

Options:

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

Buy Now
Questions 80

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

Options:

A.

Portfolios

B.

Standards

C.

Concepts

D.

Programs

Buy Now
Questions 81

What are the project management processes associated with project quantity management?

Options:

A.

Plan Quality Management, Manage Quality, and Control Quality

B.

Plan Quality Management, Manage Quality, and Cost of Quality

C.

Manage Quality, Customer Satisfaction, and Control Quality

D.

Customer Satisfaction, Control Quality, and Continuous Improvement

Buy Now
Questions 82

An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?

Options:

A.

Team velocity in past iterations

B.

Related epics of each story

C.

Product owner ' s priorities

D.

Detailed acceptance criteria

Buy Now
Questions 83

Recognition and rewards are tools and techniques of which process?

Options:

A.

Develop Team

B.

Manage Team

C.

Control Resources

D.

Plan Resource Management

Buy Now
Questions 84

Which quality control technique illustrates the 80/20 principle?

Options:

A.

Ishikawa diagram

B.

Control chart

C.

Run chart

D.

Pareto chart

Buy Now
Questions 85

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Buy Now
Questions 86

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Buy Now
Questions 87

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

Options:

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

Buy Now
Questions 88

A project ' s business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology?

Options:

A.

Must have, should have, could have, won ' t have (MoSCoW)

B.

Strengths, weaknesses, opportunities, threats (SWOT)

C.

Work breakdown structure (WBS)

D.

Responsible, accountable, consulted, informed (RACI)

Buy Now
Questions 89

Change request status updates are an output of which process?

Options:

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Buy Now
Questions 90

The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?

Options:

A.

Prompt lists and data analysis

B.

Reports and representations of uncertainty

C.

Data analysis and risk audits

D.

Interpersonal and team skills and project management Information system

Buy Now
Questions 91

What is purpose of using the building information model (BIM) in software tools in the construction field?

Options:

A.

Reduce significant amount of time and money

B.

Help manage risks in large projects

C.

Keep up with emerging trends

D.

Provide sellers with multiple sources for documents

Buy Now
Questions 92

Tailoring considerations for project scope management may include:

Options:

A.

requirements management, stability of requirements, development approach, and validation and control.

B.

WBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.

C.

business needs, product descriptions, project restrictions, and project management plan.

D.

issues defining and controlling what is included in the project, vended deliverables, and quality reports.

Buy Now
Questions 93

A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

Options:

A.

Provide the information to the product manager for approval.

B.

Provide the information to the project manager to seek approval or rejection.

C.

Reject the change as the project scope has already been defined.

D.

Accept the modification and update the requirements traceability matrix.

Buy Now
Questions 94

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

Options:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Buy Now
Questions 95

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

Options:

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

Buy Now
Questions 96

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Buy Now
Questions 97

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

Options:

A.

Initiating Process Group

B.

Planning Process Group

C.

Executing Process Group

D.

Monitoring and Controlling Process Group

Buy Now
Questions 98

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

Options:

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Buy Now
Questions 99

Requirements documentation will typically contain at least:

Options:

A.

Stakeholder requirements, staffing requirements, and transition requirements.

B.

Business requirements, the stakeholder register, and functional requirements.

C.

Stakeholder impact, budget requirements, and communications requirements.

D.

Business objectives, stakeholder impact, and functional requirements.

Buy Now
Questions 100

In an organization with a projectized organizational structure, who controls the project budget?

Options:

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Buy Now
Questions 101

During project execution, a team member has identified and then analyzed an opportunity that

will yield a net saving of 10% and reduce time in the schedule by 20%

Which strategy should the project manager adopt to accommodate this opportunity?

Options:

A.

Escalate to upper management to build awareness of the opportunity.

B.

Exploit the opportunity immediately, since the cost saving makes it worthwhile.

C.

Transfer the opportunity to a partner and start a partner contract.

D.

Create a trail of the opportunity before full adoption, because of the risk associated.

Buy Now
Questions 102

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

Options:

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

Buy Now
Questions 103

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

Options:

A.

50-75%

B.

25-50%

C.

75-100%

D.

0-25%

Buy Now
Questions 104

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Buy Now
Questions 105

The project manager has following information about duration for an activity:

* Most likely [tM] - 15 days

* Pessimistic [tP] - 20 days

* Optimistic [tO] - 10 days

What is the estimated duration of this activity, according to the triangular distribution technique?

Options:

A.

10 days

B.

15 days

C.

12.5 days

D.

5 days

Buy Now
Questions 106

Which element does a project charter contain?

Options:

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

Buy Now
Questions 107

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Buy Now
Questions 108

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Buy Now
Questions 109

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Buy Now
Questions 110

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?

Options:

A.

Move these user stories back to the product backlog for reprioritization.

B.

Remove these user stories as they are not important.

C.

Advance these user stories to the top of the next sprint backlog.

D.

Complete these user stories in the current sprint and extend the sprint length.

Buy Now
Questions 111

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Buy Now
Questions 112

A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?

Options:

A.

It will give the project manager Independence to make decisions without other departmental input.

B.

It Integrates organizational data and information to ensure that strategic objectives are fulfilled.

C.

The project management office can execute administrative tasks.

D.

The project management office can coordinate projects.

Buy Now
Questions 113

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

Options:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Buy Now
Questions 114

What behavior refers to leadership style?

Options:

A.

Do things right.

B.

Do the right things

C.

Ask how and when.

D.

Rely on control

Buy Now
Questions 115

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 116

A project manager is creating a project charter to provide a direct link between the project and the organization ' s strategic objectives. What must be considered when creating this document?

Options:

A.

High-level requirements and the project team

B.

Key stakeholder list and contingency reserve

C.

Detailed milestone schedule and project objectives

D.

Project purpose and high-level project description

Buy Now
Questions 117

Which of these is true of project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Buy Now
Questions 118

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

Options:

A.

Cost management plan.

B.

Work performance information.

C.

Quality management plan.

D.

Work breakdown structure.

Buy Now
Questions 119

What communications management process enables an effective information flow among project stakeholders ' ?

Options:

A.

Monitor Stakeholder Engagement

B.

Manage Communications

C.

Monitor Communications

D.

Manage Stakeholder Engagement

Buy Now
Questions 120

Which of the following is an output of Define Scope?

Options:

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Buy Now
Questions 121

The following is a network diagram for a project.

How many possible paths are identified for this project?

Options:

A.

3

B.

4

C.

6

D.

7

Buy Now
Questions 122

A project charter is an output of which Process Group?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Closing

Buy Now
Questions 123

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Buy Now
Questions 124

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

Options:

A.

Communication models.

B.

Stakeholder participation.

C.

Expert judgment

D.

Enterprise environmental factors.

Buy Now
Questions 125

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Buy Now
Questions 126

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

Options:

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Buy Now
Questions 127

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Buy Now
Questions 128

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Buy Now
Questions 129

A project team member identifies a possibility......the team member ' s idea?

A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.

How should the project manager evaluate the team member ' s idea?

Options:

A.

Treat the idea using risk management processes, to handle it in a controlled and managed way.

B.

Perform an experiment simulation to confirm idea results, to make sure the cost to implement is worthwhile.

C.

Do a feasibility analysis study to confirm if an investment to explore a solution will add value.

D.

Submit the idea as a change request to the change control board to ensure that all interests are met.

Buy Now
Questions 130

Tools and techniques used for Plan Communications include the communication:

Options:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

Buy Now
Questions 131

Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?

Options:

A.

Conduct Procurements B Plan Procurement Management

B.

Plan Risk Responses

C.

Plan Risk Management

Buy Now
Questions 132

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Buy Now
Questions 133

Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

Options:

A.

Video conferencing

B.

Audio conferencing

C.

Shared portal

D.

Email/chat

Buy Now
Questions 134

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Buy Now
Questions 135

What tool or technique will establish expected behaviors for project team members?

Options:

A.

Ground rules

B.

Decision mating

C.

Power/influence grid

D.

Stakeholder engagement assessment matrix

Buy Now
Questions 136

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Buy Now
Questions 137

During a project ' s execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?

Options:

A.

Legal requirements

B.

Politics and power structures

C.

Internal information needs

D.

Sensitivity and confidentiality of the information

Buy Now
Questions 138

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Options:

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Questions 139

What tool or technique is used in the Collect Requirements process?

Options:

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

Buy Now
Questions 140

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Options:

A.

List of identified risks, potential risk owners, list of potential risk response

B.

List of identified risks, list of causes, list of risk categories

C.

Short risk titles, list of potential risk owners, list of impacts on objectives

D.

List of activities affected, list of potential risk responses, list of causes

Buy Now
Questions 141

A business analyst is evaluating solutions against the expected results and logging defects along the way. The next task is to analyze the discrepancies prior to facilitating a go/no-go decision.

Which technique should be used as a starting point to uncover problem areas?

Options:

A.

Elicitation

B.

Opportunity analysis

C.

Cost-benefit analysis

D.

Feasibility analysis

Buy Now
Questions 142

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

Options:

A.

Organizational standard processes

B.

Marketplace conditions

C.

Historical information

D.

Templates

Buy Now
Questions 143

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Buy Now
Questions 144

A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)

Options:

A.

Project management plan

B.

Product roadmap

C.

Requirements traceability matrix

D.

Business goals and objectives

E.

Risk register

Buy Now
Questions 145

An input of the Create WBS process is:

Options:

A.

requirements documentation.

B.

scope baseline.

C.

project charter.

D.

validated deliverables.

Buy Now
Questions 146

Which of these is true project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects

B.

Project Integration Management and Expert Judgement are mutually exclusive

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero

Buy Now
Questions 147

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Options:

A.

1

B.

0.4

C.

0.5

D.

0.8

Buy Now
Questions 148

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

Options:

A.

Project

B.

Scope

C.

Contract

D.

Program

Buy Now
Questions 149

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Buy Now
Questions 150

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Options:

A.

Requirements documentation

B.

Requirements traceability matrix

C.

Project management plan updates

D.

Project documents updates

Buy Now
Questions 151

The diagram below is an example of a:

Options:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Buy Now
Questions 152

Which of the following are three inputs to the risk register?

Options:

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Buy Now
Questions 153

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

Options:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Buy Now
Questions 154

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

Options:

A.

Project level

B.

Organizational level

C.

Industry level

D.

Influential level

Buy Now
Questions 155

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

Options:

A.

Risk, resource, and communications management plans

B.

Scope, quality, and resource management plans

C.

Procurement, integration, and risk management plans

D.

Communications, schedule, and cost management plans

Buy Now
Questions 156

In which process might a project manager use risk reassessment as a tool and technique?

Options:

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Buy Now
Questions 157

Which defines the portion of work included in a contract for items being purchased or acquired?

Options:

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Buy Now
Questions 158

In the Plan Stakeholder Management process, expert judgment is used to:

Options:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Buy Now
Questions 159

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

Options:

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

Buy Now
Questions 160

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

Options:

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Buy Now
Questions 161

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Buy Now
Questions 162

Which of the following set of elements is part of an effective communications management plan?

Options:

A.

Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information

B.

Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology

C.

Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology

D.

Glossary of common terminology, constraints denved from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan

Buy Now
Questions 163

Success is measured by benefits realization for a:

Options:

A.

strategic plan

B.

project

C.

portfolio

D.

program

Buy Now
Questions 164

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

Buy Now
Questions 165

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

Options:

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Buy Now
Questions 166

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

Options:

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Buy Now
Questions 167

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Buy Now
Questions 168

Variance and trend analysis is a tool and technique used in which process?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

Buy Now
Questions 169

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?

Options:

A.

Three-point estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Data analysis

Buy Now
Questions 170

Stakeholder satisfaction should be managed as a key project:

Options:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Buy Now
Questions 171

Plan Schedule Management is a process in which Knowledge Area?

Options:

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Buy Now
Questions 172

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Options:

A.

Close Project or Phase

B.

Conduct Procurements

C.

Control Procurements

D.

Close Procurements

Buy Now
Questions 173

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?

Options:

A.

Adaptive

B.

Hybrid

C.

Extreme

D.

Traditional

Buy Now
Questions 174

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

Options:

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Buy Now
Questions 175

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:

A.

event.

B.

response,

C.

perception.

D.

impact.

Buy Now
Questions 176

The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?

Options:

A.

Organizational structure type, Key stakeholders, and protect funds

B.

Rules. policies and norms

C.

Project management software, resources availability and risk checklist

D.

Governance elements, team policies, and organizational goals

Buy Now
Questions 177

Which of the following can be used as an input for Define Scope?

Options:

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Buy Now
Questions 178

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Buy Now
Questions 179

Which process involves determining, documenting, and managing stakeholders ' needs and requirements to meet project objectives?

Options:

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Buy Now
Questions 180

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

Options:

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

Buy Now
Questions 181

The Verify Scope process is primarily concerned with:

Options:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Buy Now
Questions 182

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Buy Now
Questions 183

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Buy Now
Questions 184

Project managers plan a key role performing integration on the project what are the three different levels of integration?

Options:

A.

Process, cognitive

B.

Complexity, understand and change

C.

Interact, insight and leadership

D.

Communication, knowledge and value

Buy Now
Questions 185

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Options:

A.

Exploit

B.

Share

C.

Enhance

D.

Transfer

Buy Now
Questions 186

Once the make-or-buy analysis is completed, which document defines the project delivery method?

Options:

A.

Procurement statement of work (SOW)

B.

Procurement strategy

C.

Terms of reference

D.

Change request

Buy Now
Questions 187

While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap. Which three roles are involved in establishing the product roadmap? (Choose three)

Options:

A.

Project sponsor

B.

Portfolio manager

C.

End user

D.

Program manager

E.

Internal inspector

Buy Now
Questions 188

What is the main purpose of Project Quality Management?

Options:

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Buy Now
Questions 189

The three processes of Project Cost Management are:

Options:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Buy Now
Questions 190

Which of the following are processes associated with Project Cost Management?

Options:

A.

Develop Costs. Estimate Costs, Determine Budget. Control Costs

B.

Develop Budget, Determine Budget, Determine Risks, Control Costs

C.

Plan Cost Management, Estimate Costs. Determine Budget. Control Costs

D.

Plan Budget Management. Determine Budget, Create Cost Accounts. Control Costs

Buy Now
Questions 191

Perform Quality Control is accomplished by:

Options:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Buy Now
Questions 192

Testing falls into which of the following categories of cost of quality?

Options:

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Buy Now
Questions 193

Which activity involves ensuring that the composition of a projects configuration items is correct?

Options:

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Buy Now
Questions 194

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options:

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Buy Now
Questions 195

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Buy Now
Questions 196

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Options:

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Buy Now
Questions 197

How is the schedule variance calculated using the earned value technique?

Options:

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

Buy Now
Questions 198

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

Options:

A.

5

B.

2

C.

3

D.

4

Buy Now
Questions 199

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

Options:

A.

Extend an iteration review invite to the new stakeholder.

B.

Perform qualitative risk analysis.

C.

Engage with the new stakeholder.

D.

Allow team members to share project status reports.

Buy Now
Questions 200

Project Scope Management is primarily concerned with:

Options:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Buy Now
Questions 201

Which characteristic do projects and operational work share in common?

Options:

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Buy Now
Questions 202

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options:

A.

Engage customer earlier

B.

Conduct quality audits

C.

Validate Scope

D.

Validate quality requirements

Buy Now
Questions 203

Which of the following is a group decision-making technique?

Options:

A.

Brainstorming

B.

Focus groups

C.

Affinity diagram

D.

Plurality

Buy Now
Questions 204

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

Buy Now
Questions 205

Which tool uses an algorithm based on historical data to calculate cost?

Options:

A.

Three-point estimating

B.

Parametric estimating

C.

Analogous estimating

D.

Relative estimating

Buy Now
Questions 206

An input to the Plan Procurement Management process is:

Options:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Buy Now
Questions 207

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

Options:

A.

2

B.

3

C.

4

D.

6

Buy Now
Questions 208

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.

Bidder conference

Buy Now
Questions 209

Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?

Options:

A.

Interactive communications

B.

Pull communications

C.

Push communications

D.

Communication style assessment

Buy Now
Questions 210

An input to the Identify Stakeholders process is:

Options:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Buy Now
Questions 211

Which actions should a project manager follow to manage stakeholders?

Options:

A.

Identify the key stakeholders and keep them informed at all times.

B.

Identify the stakeholders, planning, managing and monitoring their engagement

C.

Meet and keep informed any person related to the project, at all times

D.

Identify the stakeholders and monitor their level of satisfaction

Buy Now
Questions 212

What benefit does the Manage Stakeholder Engagement process offer?

Options:

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Buy Now
Questions 213

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

Options:

A.

Result

B.

Product

C.

Service

D.

Improvement

Buy Now
Questions 214

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

Options:

A.

Power interest grid

B.

Stakeholder cube

C.

Salience model

D.

Directions of influence

Buy Now
Questions 215

The process of identifying the stakeholders ' information needs is completed during:

Options:

A.

Plan Communications.

B.

Manage Stakeholder Expectations.

C.

Stakeholder Analysis.

D.

Identify Stakeholders.

Buy Now
Questions 216

A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the timeline for development.

What should the project manager do next?

Options:

A.

Update the project management plan.

B.

Add the discovery to the assumptions.

C.

Evaluate the risk with the project team.

D.

Conduct an opportunity analysis with the team.

Buy Now
Questions 217

Match the method for categorizing stakeholders with its corresponding description

CAPM Question 217

Options:

Buy Now
Questions 218

What is the role of project management in terms of organizational strategy?

Options:

A.

Project management aligns initiatives, prioritizes work, and provides resources.

B.

Project management provides the strategic vision (or an organization lo achieve its goals.

C.

Project management enables the achievement of organizational goals and objectives.

D.

Project management harmonizes components and controls interdependencies to realize specific benefits.

Buy Now
Questions 219

How can working in iterations increase the quality of the product being built?

Options:

A.

Teams have to do less planning and focus more on quality.

B.

The project manager has more time to document goals in advance.

C.

Less testing is required since it is done at the end of the project.

D.

Requirements are frequently clarified by users of the product.

Buy Now
Questions 220

Which action should a project manager take to ensure that the project management plan is effective and current?

Options:

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Buy Now
Questions 221

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Buy Now
Questions 222

The primary purpose of the stakeholder register is to:

Options:

A.

Record stakeholder issues on the project

B.

Maintain lessons learned earlier in the project

C.

Maintain a list of all project stakeholders

D.

Document change requests and their status

Buy Now
Questions 223

A few project team members are having issues understanding the requirements as described. Which action should be taken to resolve this issue?

Options:

A.

Review the requirements traceability matrix and set up a meeting with the business analyst and key stakeholders.

B.

Review the requirements traceability matrix, the business analysis communications management plan, and set up a meeting with the business analyst and key stakeholders.

C.

Review the business analysis communications management plan and set up a meeting with the business analyst and key stakeholders.

D.

Review the project management plan and set up a meeting with the project manager and key stakeholders.

Buy Now
Questions 224

Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?

Options:

A.

Increased support and minimized resistance from stakeholders

B.

Increased performance of the project team

C.

Maintenance of stakeholder satisfaction because costs and scope are under control

D.

Updated project documents, as requested by stakeholders

Buy Now
Questions 225

High-level project risks are included in which document?

Options:

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

Buy Now
Questions 226

Due to organizational changes, a new product owner joins a project The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

What process should the project manager review with the product owner?

Options:

A.

Acquire Resources

B.

Plan Resource Management

C.

Estimate Activity Resources

D.

Control Resources

Buy Now
Questions 227

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

Options:

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

Buy Now
Questions 228

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

Options:

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Project management processes

D.

Project scope management plan

Buy Now
Questions 229

What is a tailoring consideration in Project Integration Management?

Options:

A.

Validation and control

B.

Benefits

C.

Technology support

D.

Physical location

Buy Now
Questions 230

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

Options:

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Buy Now
Questions 231

An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?

Options:

A.

Product and sprint backlog

B.

Key performance indicators (KPIs) and baseline

C.

Increments and bottlenecks

D.

Burndown and burnup charts

Buy Now
Questions 232

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Buy Now
Questions 233

Which Process Group includes the Manage Stakeholder Engagement process?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

Buy Now
Questions 234

An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed.

What project management approach should the organization use?

Options:

A.

Predictive

B.

Hybrid

C.

Iterative

D.

Adaptive

Buy Now
Questions 235

Which of the following Project Communication Management processes uses performance reports as an input?

Options:

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Buy Now
Questions 236

To which knowledge area does the Collect Requirements process belong?

Options:

A.

Quality Management

B.

Scope Management

C.

Cost Management

D.

Integration Management

Buy Now
Questions 237

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

Options:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Buy Now
Questions 238

What kind of skills should a project manager use when attempting to achieve consensus by balancing the conflicting and competing goals of project stakeholders?

Options:

A.

Interpersonal skills and the ability to manage people

B.

Strategic and business management skills

C.

Technical and business management skills

D.

Business analysis skills and expertise

Buy Now
Questions 239

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?

Options:

A.

Create Work Breakdown Structure (WBS)

B.

Create Scope Baseline

C.

Collect Requirements

D.

Define Scope

Buy Now
Questions 240

Managing procurement relationships and monitoring contract performance are part of which process?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements

Buy Now
Questions 241

Perform Quantitative Risk Analysis focuses on:

Options:

A.

compiling a list of known risks and preparing responses to them.

B.

assessing the probability of occurrence and Impact for every risk in the risk register.

C.

evaluating the contingency and management reserves required for the project.

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives.

Buy Now
Questions 242

A project team has completed the sprint review and the users are impressed by the demo. However, another functionality included in the sprint that was not discussed in the review is not ready for production deployment.

What should the project team do?

Options:

A.

Demo the incomplete feature at the sprint retrospective.

B.

Deploy the functionality that was presented to the users.

C.

Wait to complete all user stories that are in development.

D.

Continue with sprints until the product backlog is empty.

Buy Now
Questions 243

The individual or group that provides resources and support for a project and is accountable for success is the:

Options:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Buy Now
Questions 244

Which process numerically analyzes the effect of identified risks on overall project objectives?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 245

Which item is a cost of conformance?

Options:

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Buy Now
Questions 246

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

Options:

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

Buy Now
Questions 247

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Options:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Buy Now
Questions 248

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Options:

A.

-8

B.

425

C.

1.4

D.

8

Buy Now
Questions 249

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Buy Now
Questions 250

Which of the following is an input to Control Scope?

Options:

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Buy Now
Questions 251

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options:

A.

Follow organizational methodology and produce all required deliverables.

B.

Discuss the processes and deliverables needed to meet the project objectives with the team.

C.

Identify the processes and deliverables for only the current phase first.

D.

Integrate hybrid approach processes and deliverables to meet the short delivery timeline.

Buy Now
Questions 252

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

Options:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Buy Now
Questions 253

A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.

Which methodology did the project manager adopt?

Options:

A.

Incremental approach

B.

Predictive approach

C.

Hybrid approach

D.

Iterative approach

Buy Now
Questions 254

It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?

Options:

A.

Pareto chart

B.

Regression analysis

C.

Statistical sampling

D.

Automated testing tools

Buy Now
Questions 255

The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?

Options:

A.

Team values, team agreements, and conflict resolution process

B.

Conflict resolution process, communication guidelines, and meeting schedules

C.

Team roles and responsibilities, team management, and training plan

D.

Resource requirements, resource assignments, and team performance assessments

Buy Now
Questions 256

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

Options:

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Buy Now
Questions 257

What is the difference between quality metrics and quality measurements?

Options:

A.

Quality metrics are product attributes and the measurement is the result of the Monitor and Control Project process

B.

Quality metrics are the result of the Monitor and Control Project process and the measurements are product attributes

C.

Quality metrics and measurements are the same concept

D.

Quality metrics is the general objective and the measurements are the specific objectives

Buy Now
Questions 258

In which domain of project management would a Pareto chart provide useful information?

Options:

A.

Project Scope Management

B.

Project Time Management

C.

Project Communications Management

D.

Project Quality Management

Buy Now
Questions 259

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Buy Now
Questions 260

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Buy Now
Questions 261

Which risk response strategy is common for both positive and negative risks?

Options:

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Buy Now
Questions 262

Which of the following are outputs of Develop Project Team?

Options:

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Buy Now
Questions 263

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Buy Now
Questions 264

An input to the Perform Integrated Change Control process is:

Options:

A.

expert judgment

B.

seller proposals

C.

the project charter

D.

the project management plan

Buy Now
Questions 265

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Buy Now
Questions 266

An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.

Which of the following changes has caused this loss in productivity?

Options:

A.

Two of the team members have been working in silos using different methods to validate their performance.

B.

The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.

C.

The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.

D.

Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.

Buy Now
Questions 267

Risk responses reflect an organization ' s perceived balance between:

Options:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Buy Now
Questions 268

In an agile or adaptive environment. when should risk be monitored and prioritized?

Options:

A.

Only during the initiation and Closing phases

B.

During the initiation and Planning phases

C.

During each iteration as the project progresses

D.

Throughout the Planning process group and retrospective meeting

Buy Now
Questions 269

What tool should a project manager use to efficiently manage project resources?

Options:

A.

List of project resources

B.

Resource breakdown structure

C.

Resources detailed in the project scope

D.

Resource requirements

Buy Now
Questions 270

A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?

Options:

A.

Linear project management; project schedule and project backlog

B.

Adaptive project management; project schedule and work breakdown structure

C.

Linear project management; project schedule and work breakdown structure (WBS)

D.

Adaptive project management; project schedule and project backlog

Buy Now
Questions 271

The project scope statement and resource calendars are inputs to which Project Time Management process?

Options:

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Buy Now
Questions 272

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Buy Now
Questions 273

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

Options:

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

Buy Now
Questions 274

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

Options:

A.

Power/influence grid

B.

Power/interest grid

C.

Influence/impact grid

D.

Salience model

Buy Now
Questions 275

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Options:

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Buy Now
Questions 276

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Buy Now
Questions 277

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Buy Now
Questions 278

During which process does the project team receive bids and proposals?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

Buy Now
Questions 279

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

Options:

A.

Direct

B.

Interactive

C.

Pull

D.

Push

Buy Now
Questions 280

A project manager builds consensus and overcomes obstacles by employing which communication technique?

Options:

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Buy Now
Questions 281

The project manager released a report A few stakeholders express the view that report should

have been directed to them

Which of the 5Cs of written communications does the project manager need to address?

Options:

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Buy Now
Questions 282

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Buy Now
Questions 283

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

Options:

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

Buy Now
Questions 284

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

Options:

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Buy Now
Questions 285

Which process is engaged when a project team member makes a change to project budget with project manager ' s approval

Options:

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 286

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Options:

A.

Checksheets

B.

Histograms

C.

Flowcharts

D.

Control charts

Buy Now
Questions 287

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Buy Now
Questions 288

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

Options:

A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Buy Now
Questions 289

What is main purpose of Project Quantity Management?

Options:

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Buy Now
Questions 290

Which type of graphic is displayed below?

CAPM Question 290

Options:

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Buy Now
Questions 291

Which item is an example of personnel assessment?

Options:

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Buy Now
Questions 292

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

Options:

A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Buy Now
Questions 293

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Buy Now
Questions 294

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

Options:

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Buy Now
Questions 295

Which statement correctly describes the value of a business case?

Options:

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Buy Now
Questions 296

When developing a schedule which tools and techniques should a project manager use?

Options:

A.

Schedule Networfc Analysis and Critical Path Method

B.

Activity list and expert Judgement

C.

Milestone Iist and Risk Register

D.

Basis ot estimates and Rolling Wave Planning

Buy Now
Questions 297

Which statement describes the Monitor Communications process?

Options:

A.

Evaluates the differences between the communications management plan and the reality of communications in a project

B.

Ensures that the information needs of the project and the stakeholders are met

C.

Ensures that project information is created, collected, and distributed in a timely and appropriate manner

D.

Develops an appropriate approach and plan for communication of project activities

Buy Now
Questions 298

Which of the following documents ate created as part of Project Integration Management?

Options:

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Buy Now
Questions 299

In which Knowledge Area is the project charter developed?

Options:

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Buy Now
Questions 300

An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee ' s duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?

Options:

A.

Strategic

B.

Finance

C.

Project

D.

Operations

Buy Now
Questions 301

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Buy Now
Questions 302

Perform Integrated Change Control is the process of:

Options:

A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

Buy Now
Questions 303

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Questions 304

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.

What should the project manager do to address this issue?

Options:

A.

Apply emotional intelligence (El) skills, such as active listening, to understand the team ' s issues.

B.

Instruct the team members to self-organize and resolve any outstanding issues.

C.

Ask the team members to record their concerns in the lessons learned log for future action.

D.

Encourage the team to follow the project plan that was developed with team input.

Buy Now
Questions 305

What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?

Options:

A.

Resources and stakeholders

B.

Operations and performance

C.

Subsidiary projects

D.

Project manager

Buy Now
Questions 306

Which project documents can determine the budget?

Options:

A.

Procurement documents, contracts, requirements documentation, and basis of estimates

B.

Basis of estimates, cost estimates, project schedule, and risk register

C.

Business case, project charter, statement of work, and cost estimates

D.

Scope baseline, resource management plan, activity list, and assumption log

Buy Now
Questions 307

Which sentence summarizes the salience model?

Options:

A.

Classifies stakeholders based on assessment of their power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Buy Now
Questions 308

During which process would stakeholders provide formal acceptance of the completed project scope?

Options:

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Buy Now
Questions 309

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

Options:

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Buy Now
Questions 310

What can the project manager find among the factors that could lead a project to be tailored

Options:

A.

Company Culture

B.

Return on investment

C.

Earned Value

D.

Schedule Performance Index

Buy Now
Questions 311

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager. What should the project manager do to address this issue?

Options:

A.

Encourage the team to follow the project plan that was developed with team input.

B.

Apply emotional intelligence (EI) skills, such as active listening, to understand the team ' s issues.

C.

Instruct the team members to self-organize and resolve any outstanding issues.

D.

Ask the team members to record their concerns in the lessons learned log for future action.

Buy Now
Questions 312

A software development team is working on a project to adapt an application to new, government-established data-privacy rules. What factor led to the creation of this project?

Options:

A.

Legal requirement

B.

New technology

C.

Social need

D.

Economic change

Buy Now
Questions 313

In agile projects while performing scope management. What is the definition of requirements

Options:

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

Buy Now
Questions 314

The product scope description is used to:

Options:

A.

Gain stakeholders ' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Buy Now
Questions 315

At the end of the project, what will be the value of SV?

Options:

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Buy Now
Questions 316

What is the purpose of the project schedule management.

Options:

A.

Estimates specific time and the deadline when the products, services and results will be delivered.

B.

Determines in details the resources and time that each task will require to be done

C.

Represents how and when the project will deliver the results defined in the project scope.

D.

It provides the relationships among the project activities and their risks.

Buy Now
Questions 317

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

Options:

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

Buy Now
Questions 318

What describes the relationship between projects, programs, and portfolios?

Options:

A.

Portfolio management focuses on doing the " right " programs and projects.

B.

Project management focuses on doing the " right " programs and portfolios.

C.

Program management focuses on doing the " specific " portfolios and projects.

D.

Portfolio management focuses on doing the ' ' specific’’ programs and projects.

Buy Now
Questions 319

Which technique is used in Perform Quantitative Risk Analysis?

Options:

A.

Sensitivity analysis

B.

Probability and impact matrix

C.

Risk data quality assessment

D.

Risk categorization

Buy Now
Questions 320

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

Options:

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Buy Now
Questions 321

What can a project manager review to understand the status of a project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Buy Now
Questions 322

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Buy Now
Questions 323

Which Process Group typically consumes the bulk of a project ' s budget?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

Buy Now
Questions 324

Which of the following is an output of the Distribute Information process?

Options:

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Buy Now
Questions 325

A software team has completed a critical feature and demonstrated it to the project sponsor.

What kind of stakeholder communication was used in this scenario?

Options:

A.

Informal written

B.

Formal verbal

C.

Formal written

D.

Informal verbal

Buy Now
Questions 326

What are the objectives of Initiation processes?

Options:

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.

B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.

C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders ' goals.

D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Buy Now
Questions 327

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options:

A.

Acquire Resources

B.

Control Resources

C.

Manage Team

D.

Develop Team

Buy Now
Questions 328

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

Options:

A.

Resource availability

B.

Infrastructure

C.

Academic research

D.

Corporate knowledge base

Buy Now
Questions 329

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

Options:

A.

Diversity background

B.

Stakeholder ' s relationships

C.

Technical expertise

D.

Knowledge management

Buy Now
Questions 330

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

Options:

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Buy Now
Questions 331

Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three)

Options:

A.

Focus groups

B.

Facilitation

C.

Meeting management

D.

Conflict management

E.

Interviews

Buy Now
Questions 332

Which of the following is part of the project sponsor ' s responsibility?

Options:

A.

Monitoring the business value

B.

Advocating the business value

C.

Tracking the business value

D.

Auditing the business value

Buy Now
Questions 333

What does ’verified’ in verified deliverable represent?

Options:

A.

The correctness of a deliverable

B.

The completeness of a deliverable

C.

The deliverable requirements

D.

The customer acceptance of a deliverable

Buy Now
Questions 334

What tools or techniques can be used in all cost management processes ' ?

Options:

A.

Decision making and expert judgment

B.

Expert judgment and data analysis

C.

Data analysis and meetings

D.

Meetings and cost aggregation

Buy Now
Questions 335

What estimating technique is used when there is limited information?

Options:

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Buy Now
Questions 336

A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?

Options:

A.

Earned Schedule + Actual Time

B.

Actual Time - Earned Schedule

C.

Planned Value - Earned Value

D.

Earned Value - Planned Value

Buy Now
Questions 337

Which is one of the major outputs of Sequence Activities?

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list

Buy Now
Questions 338

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Buy Now
Questions 339

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity ' s prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?

Options:

A.

Perform Integrated Change Control.

B.

Conduct a risk assessment with the team.

C.

Update the schedule to include compliance.

D.

Manage Stakeholder Engagement.

Buy Now
Questions 340

In project management, which document is used to start the initial risk identification?

Options:

A.

Assumption log

B.

Risk management plan

C.

Risk register

D.

Issue log

Buy Now
Questions 341

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

Options:

A.

Develop Schedule

B.

Control Schedule

C.

Estimate Activity Durations

D.

Define Activities

Buy Now
Questions 342

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

Options:

A.

Plan Communications Management

B.

Plan Stakeholder Engagement

C.

Perform Integrated Change Control

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 343

Which three processes are generally included in risk management? (Choose three)

Options:

A.

Monitor Risk Costs

B.

Identify Risks

C.

Plan Risk Responses

D.

Perform Qualitative Risk Analysis

E.

Estimate Risk Activity Resources

Buy Now
Questions 344

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

Buy Now
Questions 345

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

Options:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Buy Now
Questions 346

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Buy Now
Questions 347

The following is a network diagram for a project.

CAPM Question 347

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Buy Now
Questions 348

Which statement describes the various purposes of project scheduling?

Options:

A.

Define the policies, rules, and techniques to run a schedule; serve as a tool to manage stakeholder expectations; and serve as a base for backlog management

B.

Define how and when deliverables will be completed, serve as communication tool, and serve as a base for performance reporting

C.

Define the life cycle, traditional or agile approach, and tools to control schedule; serve as a reference for scope management; and serve as a base for risk management

D.

Define activities, sequences, duration, and dependencies, serve as a reference for resource allocation, serve as a base for earned value analysis.

Buy Now
Questions 349

The Perform Integrated Change Control process occurs in which Process Group?

Options:

A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Buy Now
Questions 350

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Buy Now
Questions 351

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.

What should the project manager do?

Options:

A.

Inform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.

B.

Share the project management plan with the team members again to bring them up to speed on the requirements.

C.

Schedule additional meetings with the customer to explain the requirements for each deliverable at length.

D.

Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.

Buy Now
Questions 352

What should be the frequency for meetings when transitioning from Scrum to Kanban?

Options:

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Buy Now
Questions 353

What is the purpose of the Manage Quality process?

Options:

A.

To translate the quality management plan into executable quality activities

B.

To monitor and record the results of executed quality management activities

C.

To determine if project activities comply with organizational and project policies.

D.

To identify project deliverables and quality requirements and/or standards

Buy Now
Questions 354

What are the Project Procurement Management processes?

Options:

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Buy Now
Questions 355

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Buy Now
Questions 356

What is a tailoring consideration for Project Scope Management ' ?

Options:

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Buy Now
Questions 357

Which of these is a hybrid contract?

Options:

A.

Cost plus award fee (CPAF)

B.

Firm fixed price (FFP)

C.

Fixed price incentive fee (FPIF)

D.

Time and material (TandM)

Buy Now
Questions 358

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Questions 359

What does an S-curve from a Monte Carlo analysis show?

Options:

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time

Buy Now
Questions 360

The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?

Options:

A.

Payment types, delivery methods, and procurement phases

B.

Procurement metrics, make-or-buy decisions, and procurement statement of work

C.

Vendor selection criteria, stakeholder roles and responsibilitys, and prequalified sellers

D.

Timetable procurement activities, product cost, and knowledge transfer schedule

Buy Now
Questions 361

A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone.

To reduce the risk with this approach, which step should the business analyst take?

Options:

A.

Add the risk to the risk register so other stakeholders are aware of the approach.

B.

Distribute the documented requirements to relevant stakeholders in all time zones for review and comment.

C.

Ask the stakeholders in the elicitation sessions to speak on behalf of stakeholders in other time zones.

D.

Request the project sponsor to approve this requirements elicitation approach for this project.

Buy Now
Questions 362

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Buy Now
Questions 363

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Questions 364

Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

Options:

A.

Build vs. buy

B.

Expert judgment

C.

Alternatives identification

D.

Product analysis

Buy Now
Questions 365

The following chart contains information about the tasks in a project.

CAPM Question 365

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000

B.

0

C.

1,000

D.

2,000

Buy Now
Questions 366

Which are the competing constraints that project manager should address when tailoring a project?

Options:

A.

Cost, scope, schedule

B.

Sponsorship, risk, quality

C.

Schedule, sponsorship, scope

D.

Resources, Quality, Communication

Buy Now
Questions 367

A risk that arises as a direct result of implementing a risk response is called a:

Options:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Buy Now
Questions 368

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Options:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Buy Now
Questions 369

Which project document is updated in the Control Stakeholder Engagement process?

Options:

A.

Project reports

B.

Issue log

C.

Lessons learned documentation

D.

Work performance information

Buy Now
Questions 370

Which of the following response strategies are appropriate for negative risks or threats?

Options:

A.

Share, Accept, Transfer, or Mitigate

B.

Exploit, Enhance, Share, or Accept

C.

Mitigate, Share, Avoid, or Accept

D.

Avoid, Mitigate, Transfer, or Accept

Buy Now
Questions 371

Which Control Quality tool is also known as an arrow diagram?

Options:

A.

Matrix diagram

B.

Affinity diagram

C.

Tree diagram

D.

Activity network diagram

Buy Now
Questions 372

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Options:

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Buy Now
Questions 373

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Buy Now
Questions 374

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task ' ?

Options:

A.

The task will be completed on time.

B.

The task will not be completed on time.

C.

Activity A is not a critical path task

D.

The precedence diagram cannot be used to provide answers for duration calculations

Buy Now
Questions 375

Who should the stakeholders consult to discuss concerns about the current work package?

Options:

A.

Project manager

B.

Business analyst

C.

Project coordinator

D.

Project sponsor

Buy Now
Questions 376

A large portion of a projects budget is typically expended on the processes in which Process Group?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Buy Now
Questions 377

Which are examples of processes that may be used once or at predefined points in the project life cycle?

Options:

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Buy Now
Questions 378

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

Options:

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Buy Now
Questions 379

The purpose of developing a project scope management plan is to:

Options:

A.

Manage the timely completion of the project.

B.

Ensure that the project includes all of the work required.

C.

Make sure the project will satisfy the needs for which it was begun.

D.

Reduce the risk of negative events in the project.

Buy Now
Questions 380

A tool and technique used during the Define Scope process is:

Options:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

Buy Now
Questions 381

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement

B.

program

C.

result

D.

portfolio

Buy Now
Questions 382

Specification of both the deliverables and the processes is the focus of:

Options:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Buy Now
Questions 383

Which project risk listed in the table below is most likely to occur?

CAPM Question 383

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 384

What characteristic of servant leadership supports resource management in an agile environment?

Options:

A.

Lecturing

B.

Construing

C.

Measuring

D.

Coaching

Buy Now
Questions 385

What is the goal of the control quality process in project management?

Options:

A.

To monitor the activities of the project and ensure Iho work is being executed as it was planned

B.

To obtain a quality cerlific ation for the product of the project service or result

C.

To assess performance and ensure the project product, service, or result meets the customer ' s expectations

D.

To test the product service, or result to determine if the errors observed are within the defined quality margins

Buy Now
Questions 386

A business manager wants to start a project to launch a new product. How should the manager initiate the project?

Options:

A.

Ask a small team to produce a prototype of the product before full-scale development.

B.

Assign a project manager to the project and ask them to document the project scope.

C.

Prepare a detailed business case to document project objectives and success criteria.

D.

Discuss the project requirements with the team for alternative products in the market.

Buy Now
Questions 387

Which of the following are components of the project management plan?

Options:

A.

Scope management plan, scope baseline, risk management plan, and configuration managemet plan

B.

Scope management plan, issue log, risk register and project schedule network diagram

C.

Scope management plan, schedule baseline, milestone list, and assumption log

D.

Scope management plan, cost estimates, duration estimates, and resource calenders

Buy Now
Questions 388

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 389

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Buy Now
Questions 390

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Cost-benefit analysis

B.

Updated project charter

C.

Approved change request

D.

Multicriteria decision analysis

Buy Now
Questions 391

Which statement summarizes the role of the change control board?

Options:

A.

The change control board is responsible for presenting the change for approval.

B.

The change control board will analyze the change impact in terms of cost and schedule.

C.

The change control board is responsible for managing the change management and configuration management systems.

D.

The change control board is responsible for reviewing and approving changes to the project.

Buy Now
Questions 392

When cost variance is negative and schedule variance is positive, the project is:

Options:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Buy Now
Questions 393

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Buy Now
Questions 394

Which component of the project management plan should be updated if a change occurs?

Options:

A.

Project charter

B.

Project baseline

C.

Assumption log

D.

Schedule forecast

Buy Now
Questions 395

When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?

Options:

A.

Requirements matrix

B.

Presentation slides

C.

Story map

D.

Project management plan

Buy Now
Questions 396

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

Options:

A.

Predictive

B.

Hybrid

C.

Kanban

D.

Adaptive

Buy Now
Questions 397

The process of defining how the project scope will be validated and controlled is known as:

Options:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 21, 2026
Questions: 1326

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99