Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

CAPM Certified Associate in Project Management (CAPM) Questions and Answers

Questions 4

What tools or techniques can be used in all cost management processes ' ?

Options:

A.

Decision making and expert judgment

B.

Expert judgment and data analysis

C.

Data analysis and meetings

D.

Meetings and cost aggregation

Buy Now
Questions 5

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

Options:

A.

Diversity background

B.

Stakeholder ' s relationships

C.

Technical expertise

D.

Knowledge management

Buy Now
Questions 6

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Options:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Buy Now
Questions 7

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Buy Now
Questions 8

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Buy Now
Questions 9

What can the project manager find among the factors that could lead a project to be tailored

Options:

A.

Company Culture

B.

Return on investment

C.

Earned Value

D.

Schedule Performance Index

Buy Now
Questions 10

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?

Options:

A.

Review the project management plan.

B.

Share the requirements traceability matrix the same way it was shared previously.

C.

Consult the business analysis communications management plan.

D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.

Buy Now
Questions 11

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

Options:

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7

Buy Now
Questions 12

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

Options:

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Buy Now
Questions 13

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

Options:

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

Buy Now
Questions 14

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

Options:

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

Buy Now
Questions 15

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Buy Now
Questions 16

In which of the risk management processes is the processes is the project charter used as an input?

Options:

A.

Palm Risk Responses

B.

Implement Risk Responses

C.

Plan Risk Management

D.

Perform Quantitative Risk Responses

Buy Now
Questions 17

The individual or group that provides resources and support for a project and is accountable for success is the:

Options:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Buy Now
Questions 18

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Buy Now
Questions 19

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Options:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Buy Now
Questions 20

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

Options:

A.

Work performance information

B.

Bidder conferences

C.

Complexity of procurement

D.

Procurement management plan

Buy Now
Questions 21

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Buy Now
Questions 22

Which cost estimate technique includes contingencies to account for cost uncertainty?

Options:

A.

Vendor bid analysis

B.

Three-point estimates

C.

Parametric estimating

D.

Reserve analysis

Buy Now
Questions 23

What are the project management processes associated with project quantity management?

Options:

A.

Plan Quality Management, Manage Quality, and Control Quality

B.

Plan Quality Management, Manage Quality, and Cost of Quality

C.

Manage Quality, Customer Satisfaction, and Control Quality

D.

Customer Satisfaction, Control Quality, and Continuous Improvement

Buy Now
Questions 24

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

Options:

A.

Implement Appropriate Response

B.

Plan Project Risk Management

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 25

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Buy Now
Questions 26

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Buy Now
Questions 27

Which tool or technique is used in validating the scope of a project?

Options:

A.

Facilitated workshops

B.

Interviews

C.

Inspection

D.

Meetings

Buy Now
Questions 28

What is the process of determining the stakeholders impacted by a business problem or opportunity?

Options:

A.

Stakeholder requirements

B.

Stakeholder identification

C.

Stakeholder analysis

D.

Stakeholder characteristics

Buy Now
Questions 29

A project manager is preparing to meet with three crucial project stakeholders on a new project Which tools and techniques can the project manager use to capture stakeholder interest?

Options:

A.

Review stakeholder register and meeting

B.

Data analysis and communication skills

C.

Data gathering and data analysis

D.

Communication skills and cultural awareness

Buy Now
Questions 30

Why is tailoring in a project necessary?

Options:

A.

Requirements keep changing.

B.

An artifact must be produced.

C.

A tool or technique is required.

D.

Each project is unique.

Buy Now
Questions 31

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Options:

A.

Pareto

B.

Ishikawa

C.

Shewhart-Deming

D.

Delphi

Buy Now
Questions 32

An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

Options:

A.

Task switching

B.

Multitasking

C.

Prediction

D.

Full allocation

Buy Now
Questions 33

An input to the Collect Requirements process is the:

Options:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Buy Now
Questions 34

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Buy Now
Questions 35

A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?

Options:

A.

Earned Schedule + Actual Time

B.

Actual Time - Earned Schedule

C.

Planned Value - Earned Value

D.

Earned Value - Planned Value

Buy Now
Questions 36

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

Options:

A.

Detailed estimation

B.

Lightweight estimation

C.

Parametric estimation

D.

A mix of them

Buy Now
Questions 37

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Buy Now
Questions 38

How many Project Management Process Groups are there?

Options:

A.

3

B.

4

C.

5

D.

6

Buy Now
Questions 39

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

Options:

A.

Get expert judgment.

B.

Count on personal experience.

C.

Ask project sponsors.

D.

Delay the project until technical uncertainty is clarified

Buy Now
Questions 40

An input of the Plan Procurement Management process is:

Options:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Buy Now
Questions 41

What is the key benefit of the Monitor Stakeholder Engagement process?

Options:

A.

Ensures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts

B.

Ensures that the project includes all the work required and only the work required—to complete the project successfully

C.

Increases the probability and/or impact of positive risks, and decreases the probability and/or Impact of negative risks or issues

D.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves

Buy Now
Questions 42

The precedence diagramming method (PDM) is also known as:

Options:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Buy Now
Questions 43

Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?

Options:

A.

Conduct Procurements B Plan Procurement Management

B.

Plan Risk Responses

C.

Plan Risk Management

Buy Now
Questions 44

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Buy Now
Questions 45

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Buy Now
Questions 46

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Buy Now
Questions 47

Perform Quantitative Risk Analysis focuses on:

Options:

A.

compiling a list of known risks and preparing responses to them.

B.

assessing the probability of occurrence and Impact for every risk in the risk register.

C.

evaluating the contingency and management reserves required for the project.

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives.

Buy Now
Questions 48

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Options:

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Buy Now
Questions 49

Risk categorization is a tool or technique used in which process?

Options:

A.

Plan Risk Responses

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 50

What tool or technique is used in the Collect Requirements process?

Options:

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

Buy Now
Questions 51

The ability to influence cost is greatest during which stages of the project?

Options:

A.

Early

B.

Middle

C.

Late

D.

Completion

Buy Now
Questions 52

What conflict resolution technique involves delaying the issue or letting others resolve it?

Options:

A.

Smooth/accommodate

B.

Collaborate/problem solve

C.

Withdraw/avoid

D.

Force/direct

Buy Now
Questions 53

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Buy Now
Questions 54

Who identifies project requirements in the early phase of the project?

Options:

A.

Business analyst, product team, and key stakeholders

B.

Project manager, business analyst, and key stakeholders

C.

Project manager, business analyst, and project sponsor

D.

Project sponsor, business analyst, and key stakeholders

Buy Now
Questions 55

The following is a network diagram for a project.

CAPM Question 55

The total float for the project is how many days?

Options:

A.

5

B.

9

C.

12

D.

14

Buy Now
Questions 56

In agile projects while performing scope management. What is the definition of requirements

Options:

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

Buy Now
Questions 57

Which behavior relates to team leadership ' ?

Options:

A.

Centering on systems and structure

B.

Providing guidance using the power of relationships

C.

Accepting the status quo

D.

Focusing on operational issues and problem solving

Buy Now
Questions 58

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

Options:

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

Buy Now
Questions 59

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.

Bidder conference

Buy Now
Questions 60

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

Options:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Buy Now
Questions 61

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (TandM).

Buy Now
Questions 62

Which process involves determining, documenting, and managing stakeholders ' needs and requirements to meet project objectives?

Options:

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Buy Now
Questions 63

Which of the following reduces the probability of potential consequences of project risk events?

Options:

A.

Preventive action

B.

Risk management

C.

Corrective action

D.

Defect repair

Buy Now
Questions 64

A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?

Options:

A.

Time and material (T8M)

B.

Fixed price incentive fee (FPIF)

C.

Cost plus fixed fee (CPFF)

D.

Cost plus award fee (CPAF)

Buy Now
Questions 65

A large portion of a projects budget is typically expended on the processes in which Process Group?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Buy Now
Questions 66

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Buy Now
Questions 67

Which statement correctly describes the value of a business case?

Options:

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Buy Now
Questions 68

Match the method for categorizing stakeholders with its corresponding description

CAPM Question 68

Options:

Buy Now
Questions 69

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Buy Now
Questions 70

Labor, materials, equipment, and supplies are examples of:

Options:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Buy Now
Questions 71

What does the creation of a project management plan accomplish?

Options:

A.

Defines the basis of all project work and how it will be performed

B.

Acknowledges the existence of a project and defines its high-level information

C.

Authorizes the project manager to apply organizational resources to project activities

D.

Provides the project manager with organizational standards, policies, processes, and procedures

Buy Now
Questions 72

What is the term assigned to products or services having the same functional use but different technical characteristics?

Options:

A.

Scope

B.

Quality

C.

Specification

D.

Grade

Buy Now
Questions 73

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Buy Now
Questions 74

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Buy Now
Questions 75

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.

B.

The scope baseline.

C.

Work performance information.

D.

Procurement audits.

Buy Now
Questions 76

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

Buy Now
Questions 77

Which type of project life cycle uses an iteration plan?

Options:

A.

Agile

B.

Predictive

C.

Waterfall

D.

Product

Buy Now
Questions 78

Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?

Options:

A.

Project Schedule Management

B.

Project Scope Management

C.

Project Resource Management

D.

Project Integration Management

Buy Now
Questions 79

Which of the following is an output from Control Scope?

Options:

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Buy Now
Questions 80

What does an S-curve from a Monte Carlo analysis show?

Options:

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time

Buy Now
Questions 81

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Options:

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

Buy Now
Questions 82

Which of these is true of project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Buy Now
Questions 83

Which is the correct formula for calculating expected activity cost for three-point estimating?

Options:

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Buy Now
Questions 84

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Buy Now
Questions 85

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Buy Now
Questions 86

What is a tool to improve team performance?

Options:

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Buy Now
Questions 87

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

Options:

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

Buy Now
Questions 88

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.

What should the project manager do to address this issue?

Options:

A.

Apply emotional intelligence (El) skills, such as active listening, to understand the team ' s issues.

B.

Instruct the team members to self-organize and resolve any outstanding issues.

C.

Ask the team members to record their concerns in the lessons learned log for future action.

D.

Encourage the team to follow the project plan that was developed with team input.

Buy Now
Questions 89

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Buy Now
Questions 90

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Buy Now
Questions 91

Which task will a project manager undertake while conducting Project Resource Management?

Options:

A.

Identity the different aspects of me team to manage and control physical resources efficiently.

B.

Procure equipment, materials, facilities, and infrastructure for the project.

C.

Train the team members in project skill sets.

D.

Define the roles and responsibilities of each team member.

Buy Now
Questions 92

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

Options:

A.

Storyboarding

B.

Wireframes

C.

Data simulation

D.

Report prototyping

Buy Now
Questions 93

During the project life cycle for a major product, a stakeholder asked to add a new feature. Which document should they consult for guidance?

Options:

A.

Product release plan

B.

Project release plan

C.

Project management plan

D.

Product management plan

Buy Now
Questions 94

In a project using agile methodology, who may perform the quality control activities?

Options:

A.

A group of quality experts at specific times during the project

B.

The project manager only

C.

All team members throughout the project life cycle

D.

Selected stakeholders at specific times during the project

Buy Now
Questions 95

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Buy Now
Questions 96

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

Options:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

Buy Now
Questions 97

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Buy Now
Questions 98

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Buy Now
Questions 99

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Buy Now
Questions 100

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Buy Now
Questions 101

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Buy Now
Questions 102

After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?

Options:

A.

Appraisal costs

B.

Management reserves

C.

Cost of nonconformance

D.

Cost of conformance

Buy Now
Questions 103

Which sentence summarizes the salience model?

Options:

A.

Classifies stakeholders based on assessment of their power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Buy Now
Questions 104

Which process is included in the Project Integration Management Knowledge Area?

Options:

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Buy Now
Questions 105

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Buy Now
Questions 106

Which type of organizational structure is displayed in the diagram provided?

CAPM Question 106

Options:

A.

Balanced matrix

B.

Projectized

C.

Strong matrix

D.

Functional

Buy Now
Questions 107

The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

Options:

A.

1.33

B.

2

C.

0.75

D.

0.5

Buy Now
Questions 108

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Buy Now
Questions 109

Company A’s accountant sends notification about a change in the company’s tax classification.

What would a project have to be initiated?

Options:

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Buy Now
Questions 110

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Buy Now
Questions 111

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Buy Now
Questions 112

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Buy Now
Questions 113

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

Options:

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Buy Now
Questions 114

Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Buy Now
Questions 115

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Buy Now
Questions 116

Which of the following are outputs of the Define Scope process in Project Scope Management?

Options:

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project scope statement and project documents updates

D.

Scope baseline and project documents updates

Buy Now
Questions 117

During a virtual kick-off session, the project sponsor highlights the significance of the project to the company. What message should be conveyed to the team in this meeting?

Options:

A.

Bonuses based on accomplishment criteria

B.

New working contract with more benefits

C.

Promotion opportunities with this project

D.

Assignment of key roles and responsibilities

Buy Now
Questions 118

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options:

A.

Discuss the processes and deliverables needed to meet the project objectives with the team.

B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.

C.

Identify the processes and deliverables for only the current phase first.

D.

Follow organizational methodology and produce all required deliverables.

Buy Now
Questions 119

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Buy Now
Questions 120

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 121

Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

Options:

A.

Project

B.

Functional

C.

Program

D.

Portfolio

Buy Now
Questions 122

A project lead asks the team to create a work breakdown structure (WBS) of the project ' s scope. The team is confused about how far they should break down the scope.

What should the project lead tell the team?

Options:

A.

Decompose to the activity or task level.

B.

Decompose until all of the risks are identified.

C.

Decompose to the work package level.

D.

Decompose until a WBS dictionary is obtained.

Buy Now
Questions 123

On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.

What is the advantage of using this tool?

Options:

A.

Scope creep will be prevented.

B.

Resource allocation will be kept to a minimum.

C.

Project closure will be established.

D.

Project costs will be controlled.

Buy Now
Questions 124

A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.

Which technique is the team using?

Options:

A.

Checklists

B.

Interview

C.

Focus group

D.

Brainstorming

Buy Now
Questions 125

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

Options:

A.

Risk, resource, and communications management plans

B.

Scope, quality, and resource management plans

C.

Procurement, integration, and risk management plans

D.

Communications, schedule, and cost management plans

Buy Now
Questions 126

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to evaluate the solution in the larger context to ensure it does not behave in unacceptable ways when deployed to production.

Which evaluation technique should be used here?

Options:

A.

Performance testing

B.

Integration testing

C.

Day-in-the-life testing

D.

Exploratory testing

Buy Now
Questions 127

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Buy Now
Questions 128

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

Options:

A.

stakeholder management strategy.

B.

communications management plan,

C.

stakeholder register,

D.

performance report.

Buy Now
Questions 129

A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?

Options:

A.

The subject matter experts (SMEs) identified in the stakeholder register

B.

The senior experts with high status in the academic community

C.

The major stakeholders nominated by the project sponsor

D.

The usual review participants holding recognized certifications

Buy Now
Questions 130

A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

Options:

A.

Provide the information to the product manager for approval.

B.

Provide the information to the project manager to seek approval or rejection.

C.

Reject the change as the project scope has already been defined.

D.

Accept the modification and update the requirements traceability matrix.

Buy Now
Questions 131

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.

What are the four elements of a RACI chart?

Options:

A.

Recommend, approve, coordinate, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, accountable, consult, and inform

D.

Responsible, accountable, coordinate, and inform

Buy Now
Questions 132

How should a project manager plan communication for a project which has uncertain requirements?

Options:

A.

Include stakeholders in project meetings and reviews, use frequent checkpoints, and co-locate team members only.

B.

Invite customers to sprint planning and retrospective meetings, update the team quickly and on a daily basis, and use official communication channels.

C.

Adopt social networking to engage stakeholders, issue frequent and short messages, and use informal communication channels.

D.

Adopt a strong change control board process, establish focal points for main subjects, and promote formal and transparent communication.

Buy Now
Questions 133

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 134

What tool should a project manager use to efficiently manage project resources?

Options:

A.

List of project resources

B.

Resource breakdown structure

C.

Resources detailed in the project scope

D.

Resource requirements

Buy Now
Questions 135

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Buy Now
Questions 136

Which tasks should a project manager accomplish in order to manage project scope correctly?

Options:

A.

Define. Validate, and Control Scope. Control Schedule; Control Costs and Manage Stakeholder Engagement

B.

Collect Requirements. Define Scope. Create WBS. Develop Schedule, and Manage Stakeholder Engagement

C.

Plan Scope Management; Collect Requirements; Define. Validate, and Control Scope; and Create WBS

D.

Define. Validate, and Control Scope. Control Costs. Manage Stakeholder Engagement, and keep budget under control

Buy Now
Questions 137

In an organization with a projectized organizational structure, who controls the project budget?

Options:

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Buy Now
Questions 138

An output of the Perform Integrated Change Control process is:

Options:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

Buy Now
Questions 139

Which of the following tools and techniques is used in the Verify Scope process?

Options:

A.

Inspection

B.

Variance analysis

C.

Expert judgment

D.

Decomposition

Buy Now
Questions 140

A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?

Options:

A.

Traceability matrixB Lessons learned

B.

Change control proceduresD Resource availability

Buy Now
Questions 141

A project manager has been assigned to a project with a short duration and given funding to form a small team. The project manager needs to choose team members based on their availability and other aspects.

What other features should the project manager consider?

Options:

A.

Skill set, expertise, and training readiness

B.

Past project performance, wage rate, and network base

C.

Collaborative skills, quality focus, and political connections

D.

Priorities, resource demand, and expertise

Buy Now
Questions 142

What describes the relationship between projects, programs, and portfolios?

Options:

A.

Portfolio management focuses on doing the " right " programs and projects.

B.

Project management focuses on doing the " right " programs and portfolios.

C.

Program management focuses on doing the " specific " portfolios and projects.

D.

Portfolio management focuses on doing the ' ' specific’’ programs and projects.

Buy Now
Questions 143

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Buy Now
Questions 144

An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?

Options:

A.

Project charter

B.

Product roadmap

C.

Project management plan

D.

Product requirements

Buy Now
Questions 145

Which process requires implementation of approved changes?

Options:

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Buy Now
Questions 146

What is purpose of using the building information model (BIM) in software tools in the construction field?

Options:

A.

Reduce significant amount of time and money

B.

Help manage risks in large projects

C.

Keep up with emerging trends

D.

Provide sellers with multiple sources for documents

Buy Now
Questions 147

What is the most important skill that project managers should possess to lead stakeholders throughout a project?

Options:

A.

Communication

B.

Problem-solving

C.

Negotiating

D.

Trust-building

Buy Now
Questions 148

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

Options:

A.

Extend an iteration review invite to the new stakeholder.

B.

Perform qualitative risk analysis.

C.

Engage with the new stakeholder.

D.

Allow team members to share project status reports.

Buy Now
Questions 149

What can the cost management plan be established?

Options:

A.

Cost baseline

B.

Cost estimates

C.

Basis of estimates

D.

Control thresholds

Buy Now
Questions 150

With regard to a project manager ' s sphere of influence in a project, which of the following does the project manager influence most directly?

Options:

A.

Suppliers

B.

Customers

C.

Governing bodies

D.

Project team

Buy Now
Questions 151

What are the objectives of Initiation processes?

Options:

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.

B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.

C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders ' goals.

D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Buy Now
Questions 152

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.

What should the project manager do?

Options:

A.

Inform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.

B.

Share the project management plan with the team members again to bring them up to speed on the requirements.

C.

Schedule additional meetings with the customer to explain the requirements for each deliverable at length.

D.

Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.

Buy Now
Questions 153

In the Control Quality process, which tools and techniques can be applied to verify deliverable?

Options:

A.

Statistical sampling, inspection, and meetings

B.

Lessons learned register, control charts, and product evaluation

C.

Checklists, retrospective documents, and approved change requests

D.

Black box tests, questionnaires and surveys, and lessons learned register

Buy Now
Questions 154

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

Options:

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Buy Now
Questions 155

Which tool or technique is used in the Plan Scope Management process?

Options:

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Buy Now
Questions 156

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

Options:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Buy Now
Questions 157

When can pre-assignment of project team members occur?

Options:

A.

When the project uses capital expenditures

B.

When the required staff can be acquired from outside sources

C.

When the project would be ignored due to travel expenses

D.

When the project is the result of specific people being promised as part of a competitive proposal

Buy Now
Questions 158

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?

Options:

A.

Risk management plan

B.

Communications management plan

C.

Change management plan

D.

Stakeholder engagement plan

Buy Now
Questions 159

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

Options:

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Buy Now
Questions 160

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Buy Now
Questions 161

Which tools or techniques are used in the Plan Schedule Management process?

Options:

A.

Benchmarking, expert judgment, and analytical techniques

B.

Statistical sampling, benchmarking, and meetings

C.

Negotiations, pre-assignment, and multi-criteria decision analysis

D.

Expert judgment, analytical techniques, and meetings

Buy Now
Questions 162

What does earned value (EV) measure?

Options:

A.

Budgeted work that has been completed

B.

Total costs incurred while accomplishing work

C.

Budget associated with planned work

D.

Cost efficiency of budgeted resources

Buy Now
Questions 163

The Agile principle " welcome changing requirement, even late in development " relates to which agile manifesto?

Options:

A.

Working software over comprehensive documentation

B.

Individuals and interactions over processes and tools

C.

Customer collaboration over contract negotiation

D.

Responding to change over following a plan

Buy Now
Questions 164

Which statement describes the Monitor Communications process?

Options:

A.

Evaluates the differences between the communications management plan and the reality of communications in a project

B.

Ensures that the information needs of the project and the stakeholders are met

C.

Ensures that project information is created, collected, and distributed in a timely and appropriate manner

D.

Develops an appropriate approach and plan for communication of project activities

Buy Now
Questions 165

Which project performance domain is the work breakdown structure (WBS) developed?

Options:

A.

Development approach and life cycle

B.

Delivery performance

C.

Project work

D.

Planning

Buy Now
Questions 166

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

Options:

A.

Expand the scope of the project.

B.

Schedule the tasks in sequence.

C.

Increase quality review cycles.

D.

Schedule the tasks in parallel.

Buy Now
Questions 167

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)

Options:

A.

Project audit

B.

Deliverable acceptance

C.

Risk register tracking

D.

Stakeholder mapping

E.

Issue log update

Buy Now
Questions 168

What does leadership involve?

Options:

A.

Working with others through discussion or debate to guide them from one point to another

B.

Directing another person from one point to another using a known set of expected behaviors

C.

Working with a person using expert judgment to develop the technical deliverables

D.

Directing another person to develop the necessary expertise to establish technical deliverables

Buy Now
Questions 169

What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?

Options:

A.

Resources and stakeholders

B.

Operations and performance

C.

Subsidiary projects

D.

Project manager

Buy Now
Questions 170

A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone.

To reduce the risk with this approach, which step should the business analyst take?

Options:

A.

Add the risk to the risk register so other stakeholders are aware of the approach.

B.

Distribute the documented requirements to relevant stakeholders in all time zones for review and comment.

C.

Ask the stakeholders in the elicitation sessions to speak on behalf of stakeholders in other time zones.

D.

Request the project sponsor to approve this requirements elicitation approach for this project.

Buy Now
Questions 171

A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.

What should the project manager do?

Options:

A.

Escalate the issue to the project management office (PMO).

B.

Organize a meeting between the two managers.

C.

Ask the project team to resolve all of the open issues.

D.

Escalate to the sponsor to decide when to commence the rollout.

Buy Now
Questions 172

For what project management process is work performance information an output?

Options:

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

Buy Now
Questions 173

Types of internal failure costs include:

Options:

A.

inspections.

B.

equipment and training.

C.

lost business.

D.

reworking and scrapping.

Buy Now
Questions 174

After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?

Options:

A.

Ability to manage strategic goals across multiple projects

B.

Skills to manage a large project

C.

Competency to manage multiple projects that align departments

D.

Capability of managing project schedules

Buy Now
Questions 175

An input used in developing the communications management plan is:

Options:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Buy Now
Questions 176

Which of the following are outputs from the process of creating a work breakdown structure (WBS)?

Options:

A.

Project scope statement and accepted deliverables

B.

Scope baseline and project documents update

C.

Accepted deliverables and enterprise environmental factors

D.

Scope baseline and work performance information

Buy Now
Questions 177

An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?

Options:

A.

Risk register

B.

Sprint board

C.

Sprint planning

D.

User story

Buy Now
Questions 178

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

Options:

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Buy Now
Questions 179

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Buy Now
Questions 180

An output of the Develop Project Team process is:

Options:

A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

Buy Now
Questions 181

What should be the frequency for meetings when transitioning from Scrum to Kanban?

Options:

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Buy Now
Questions 182

What organizational process asset (OPA) can impact a project?

Options:

A.

Marketplace conditions

B.

Preapproved supplier lists

C.

Physical environmental elements

D.

Legal restrictions

Buy Now
Questions 183

The Verify Scope process is primarily concerned with:

Options:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Buy Now
Questions 184

What is the difference between the critical path and the critical chain?

Options:

A.

Scope changes

B.

Resource limitations

C.

Risk analysis

D.

Quality audits

Buy Now
Questions 185

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Buy Now
Questions 186

Which kind of communication should the project manager use when creating reports for government bodies?

Options:

A.

Hierarchical

B.

External

C.

Formal

D.

Official

Buy Now
Questions 187

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

Options:

A.

Activity level

B.

Deliverable level

C.

Task level

D.

Work package level

Buy Now
Questions 188

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

Options:

A.

Utilize the change control process.

B.

Crash the schedule to fix the defect.

C.

Leave the defect in and work around it.

D.

Fast-track the remaining development.

Buy Now
Questions 189

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

Options:

A.

Matrix - strong

B.

Matrix - balanced

C.

Virtual

D.

Functional

Buy Now
Questions 190

An adaptive team ' s velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.

How should the project manager calculate the anticipated velocity for future sprints?

Options:

A.

Use the velocity of the last sprint, as it is the most recent one to share.

B.

Add a 30% buffer to the velocity to calculate future velocity.

C.

Calculate the average of the past five sprints to predict future velocity.

D.

Change the adaptive tool that the team is using to calculate velocity.

Buy Now
Questions 191

An output of the Validate Scope process is:

Options:

A.

A requirements traceability matrix.

B.

The scope management plan.

C.

Work performance reports.

D.

Change requests.

Buy Now
Questions 192

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Questions 193

What important qualities should project managers possess for strategic and business management?

Options:

A.

Skills and behaviors related to specific domains of project management

B.

Knowledge and competencies needed to guide and motivate a team

C.

Skills and behaviors needed to help an organization achieve its goals

D.

Expertise in the industry and organization that deliver better outcomes

Buy Now
Questions 194

Exhibit A is an example of which of the following types of Sequence Activities?

Options:

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Buy Now
Questions 195

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

Options:

A.

Project Plan

B.

Responsibility Matrix

C.

Issue Log

D.

Scope Document

Buy Now
Questions 196

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

Options:

A.

Projectized

B.

Weak matrix

C.

Functional

D.

Balanced matrix

Buy Now
Questions 197

In a typical project, project managers spend most of their time:

Options:

A.

Estimating

B.

Scheduling

C.

Controlling

D.

Communicating

Buy Now
Questions 198

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Buy Now
Questions 199

What risk response strategy involves removing high- risk scope elements from a project?

Options:

A.

Transfer

B.

Avoid

C.

Exploit

D.

Accept

Buy Now
Questions 200

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.

What is this an example of?

Options:

A.

Monitoring the traceability matrix

B.

Managing the scope

C.

Maintaining the product backlog

D.

Managing the cost benefit

Buy Now
Questions 201

DRAG DROP

Match the praxes manager ' s sphere of influence with the associated primary role:

CAPM Question 201

Options:

Buy Now
Questions 202

When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?

Options:

A.

Update the schedule baseline

B.

Review the schedule baseline

C.

Initiate a change request

D.

Update the risk register

Buy Now
Questions 203

What does a CPI value greater than 1.0 indicate?

Options:

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

Buy Now
Questions 204

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:

A.

appetite

B.

tolerance

C.

threshold

D.

management

Buy Now
Questions 205

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Buy Now
Questions 206

Which of the following is an example of an internal factor that influences the outcome of the project?

Options:

A.

Legal restrictions

B.

Financial considerations

C.

Commercial database

D.

Geographic distribution of facilities

Buy Now
Questions 207

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Options:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Buy Now
Questions 208

A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.

Which approach should the project manager take?

Options:

A.

Escalate

B.

Mitigate

C.

Avoid

D.

Transfer

Buy Now
Questions 209

The project management processes presented in the PMBOK Guide® should:

Options:

A.

always be applied uniformly.

B.

be selected as appropriate by the sponsor.

C.

be selected as appropriate by the project team.

D.

be applied based on ISO guidelines.

Buy Now
Questions 210

Those who enter into a contractual agreement to provide services necessary for a project are:

Options:

A.

buyers

B.

sellers

C.

business partners

D.

product users

Buy Now
Questions 211

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Buy Now
Questions 212

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

Options:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Buy Now
Questions 213

During what project management process does the project team begin identifying risks?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 214

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 215

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Buy Now
Questions 216

Construction of a building has stopped due to a supplier ' s failure to deliver concrete. The project schedule is behind by three months.

What should the project manager do to overcome this problem and put the project back on track?

Options:

A.

Follow the risk response plan and allocate resources, if needed, to overcome the issue.

B.

Consult the legal department and subject matter experts (SMEs) regarding what to do to avoid failure.

C.

Extend the time of product delivery and use management reserve to cover any losses.

D.

Accept any penalties that might occur and continue working as initially planned.

Buy Now
Questions 217

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Buy Now
Questions 218

An input of the Control Schedule process is the:

Options:

A.

resource calendar.

B.

activity list.

C.

risk management plan.

D.

organizational process assets.

Buy Now
Questions 219

Which is the order of steps in the Procurement Management process?

Options:

A.

Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements

B.

Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements

C.

Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors

D.

Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements

Buy Now
Questions 220

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Options:

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Buy Now
Questions 221

An issue log is an input to which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Buy Now
Questions 222

Which technique helps to determine the risks that have the most potential impact on a project?

Options:

A.

Cost risk simulation analysis

B.

Expected monetary value analysis

C.

Modeling and simulation

D.

Sensitivity analysis

Buy Now
Questions 223

Match each Project Cost Management process with its appropriate keyword

CAPM Question 223

Options:

Buy Now
Questions 224

What type of stakeholder is part of a project manager ' s sphere of influence on a project?

Options:

A.

Customers

B.

Sponsors

C.

Directors

D.

Resource managers

Buy Now
Questions 225

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Buy Now
Questions 226

Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?

Options:

A.

Send the meeting minutes to all team members to verify that the required information is readily available.

B.

Ask the team members to provide feedback for meetings in the phase retrospective.

C.

Review the actions from the meeting with each of the project team members to ensure their understanding.

D.

Consult the communications management plan to determine the success criteria for meetings.

Buy Now
Questions 227

Agile release planning provides a high-level summary timeline of the release schedule based on.

Options:

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Buy Now
Questions 228

Creating the project scope statement is part of which process?

Options:

A.

Manage Scope

B.

Collect Requirements

C.

Define Scope

D.

Validate Scope

Buy Now
Questions 229

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Options:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Buy Now
Questions 230

What is project management?

Options:

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Buy Now
Questions 231

Which are examples of processes that may be used once or at predefined points in the project life cycle?

Options:

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Buy Now
Questions 232

A temporary endeavor that creates a unique product or service is called a:

Options:

A.

Project

B.

Plan

C.

Program

D.

Portfolio

Buy Now
Questions 233

What can a project manager review to understand the status of a project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Buy Now
Questions 234

Which is an enterprise environmental factor?

Options:

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Buy Now
Questions 235

What is a tool or technique used in the Control Quality process?

Options:

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Buy Now
Questions 236

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Buy Now
Questions 237

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Buy Now
Questions 238

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Buy Now
Questions 239

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Buy Now
Questions 240

How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?

Options:

A.

Adopt co-creation, sharing responsibilities with stakeholders

B.

Adopt participation of stakeholders in main meetings, listening to their opinion.

C.

Adopt social media tools, improving communication with stakeholders

D.

Adopt involvement of stakeholders in lessons learned sessions, sharing experiences with them

Buy Now
Questions 241

A project manager who communicates to the project team though email is using which type of communication?

Options:

A.

Formal

B.

Informal

C.

Horizontal

D.

Unofficial

Buy Now
Questions 242

When would resource leveling be applied to a schedule model?

Options:

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Buy Now
Questions 243

A graphic display of project team members and their reporting relationships is known as a:

Options:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Buy Now
Questions 244

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?

Options:

A.

Strategic and business management skills

B.

Leadership skills

C.

Technical project management

D.

Organizational management

Buy Now
Questions 245

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Buy Now
Questions 246

Which of the following lists represents the outputs of the Monitor Communications process?

Options:

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Buy Now
Questions 247

What are the inputs of the Estimate Costs process?

Options:

A.

Project management plan, work performance data, enterprise environmental factors, and organizational process assets

B.

Project management plan, project documents, enterprise environmental factors, and organizational process assets

C.

Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets

D.

Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets

Buy Now
Questions 248

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

Options:

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Buy Now
Questions 249

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

Options:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Buy Now
Questions 250

Which of the following are outputs of define scope process in project scope management

Options:

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project Scope statement and project documents updates

D.

Scope baseline and project documents updates

Buy Now
Questions 251

Which of the following strategic considerations often results in project authorization?

Options:

A.

Customer requests and/or issue resolution

B.

Stakeholder expectations and/or strategic opportunity (business need)

C.

Technological advancement and/or senior executive request

D.

Market demand and/or legal requirements

Buy Now
Questions 252

Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?

Options:

A.

Increased support and minimized resistance from stakeholders

B.

Increased performance of the project team

C.

Maintenance of stakeholder satisfaction because costs and scope are under control

D.

Updated project documents, as requested by stakeholders

Buy Now
Questions 253

The following is a network diagram for a project.

How many possible paths are identified for this project?

Options:

A.

3

B.

4

C.

6

D.

7

Buy Now
Questions 254

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Buy Now
Questions 255

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

Options:

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

Buy Now
Questions 256

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Buy Now
Questions 257

A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.

What should the project manager do next to avoid project failure?

Options:

A.

Adopt a change management approach and delay the project to decide on the direction.

B.

Develop a focus group to face the issue and decide on the appropriate direction.

C.

Request a meeting with top management to state concerns about their ability to handle the situation.

D.

Delay the project by adopting a fast-fail approach, mitigating the risk of having a bigger impact on the company.

Buy Now
Questions 258

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller ' s performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Buy Now
Questions 259

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Buy Now
Questions 260

A project manager called for a team meeting...................method did the team use

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?

Options:

A.

Rolling wave planning

B.

Expert Judgement

C.

Decomposition

D.

Data analysis

Buy Now
Questions 261

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

Options:

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group

Buy Now
Questions 262

The process of formalizing acceptance of the completed project deliverables is known as:

Options:

A.

Validate Scope.

B.

Close Project or Phase.

C.

Control Quality.

D.

Verify Scope.

Buy Now
Questions 263

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

Options:

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

Buy Now
Questions 264

What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders ' ?

Options:

A.

Prioritization

B.

Directions of influence

C.

Salience model

D.

Power/influence grid

Buy Now
Questions 265

A business analyst has encountered a conflict related to competing requirements on an existing project. What tool should the business analyst use to resolve this issue?

Options:

A.

Peer review

B.

Procurement management

C.

Weighted ranking

D.

Risk assessment

Buy Now
Questions 266

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

Options:

A.

Withdraw/avoid

B.

Smooth /accommodate

C.

Collaborate/problem solve

D.

Compromise/ reconcile

Buy Now
Questions 267

Which project documents can determine the budget?

Options:

A.

Procurement documents, contracts, requirements documentation, and basis of estimates

B.

Basis of estimates, cost estimates, project schedule, and risk register

C.

Business case, project charter, statement of work, and cost estimates

D.

Scope baseline, resource management plan, activity list, and assumption log

Buy Now
Questions 268

Which statement summarizes the role of the change control board?

Options:

A.

The change control board is responsible for presenting the change for approval.

B.

The change control board will analyze the change impact in terms of cost and schedule.

C.

The change control board is responsible for managing the change management and configuration management systems.

D.

The change control board is responsible for reviewing and approving changes to the project.

Buy Now
Questions 269

Which role does the project manager resemble best?

Options:

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

Buy Now
Questions 270

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Buy Now
Questions 271

In complex projects/ initiating processes should be completed:

Options:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Buy Now
Questions 272

The process for performing variance analysis may vary, depending on:

Options:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Buy Now
Questions 273

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Buy Now
Questions 274

The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?

Options:

A.

Plan Cost Management

B.

Estimate Activity Resources

C.

Estimate Costs

D.

Determine Budget

Buy Now
Questions 275

Which of the following tools or techniques is used for Estimate Activity Durations?

Options:

A.

Critical path method

B.

Rolling wave planning

C.

Precedence diagramming method

D.

Parametric estimating

Buy Now
Questions 276

In which Knowledge Area is the project charter developed?

Options:

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Buy Now
Questions 277

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Buy Now
Questions 278

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Buy Now
Questions 279

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

Options:

A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Buy Now
Questions 280

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Buy Now
Questions 281

A software team has completed a critical feature and demonstrated it to the project sponsor.

What kind of stakeholder communication was used in this scenario?

Options:

A.

Informal written

B.

Formal verbal

C.

Formal written

D.

Informal verbal

Buy Now
Questions 282

A project team member identifies a possibility......the team member ' s idea?

A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.

How should the project manager evaluate the team member ' s idea?

Options:

A.

Treat the idea using risk management processes, to handle it in a controlled and managed way.

B.

Perform an experiment simulation to confirm idea results, to make sure the cost to implement is worthwhile.

C.

Do a feasibility analysis study to confirm if an investment to explore a solution will add value.

D.

Submit the idea as a change request to the change control board to ensure that all interests are met.

Buy Now
Questions 283

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

Options:

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Buy Now
Questions 284

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Buy Now
Questions 285

A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.

Which evaluation technique should be used here?

Options:

A.

Exploratory testing

B.

Integration testing

C.

User acceptance testing

D.

Day-in-the-life testing

Buy Now
Questions 286

Which tool or technique is used in the Develop Project Management Plan process?

Options:

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Buy Now
Questions 287

The features and functions that characterize a result, product, or service can refer to:

Options:

A.

project scope

B.

product scope

C.

service scope

D.

product breakdown structure

Buy Now
Questions 288

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

Options:

A.

Supportive

B.

Leading

C.

Neutral

D.

Resistant

Buy Now
Questions 289

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

Options:

A.

management

B.

response

C.

tolerance

D.

appetite

Buy Now
Questions 290

A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?

Options:

A.

-9

B.

37

C.

9

D.

322

Buy Now
Questions 291

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

Options:

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Buy Now
Questions 292

What tool or technique can improve a products final characteristics?

Options:

A.

Design for X (DfX)

B.

Problem solving

C.

Process analysis

D.

Risk report

Buy Now
Questions 293

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Buy Now
Questions 294

Why is tailoring required in a project?

Options:

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

Buy Now
Questions 295

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Buy Now
Questions 296

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

Options:

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Buy Now
Questions 297

What happens to a stakeholder ' s project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Buy Now
Questions 298

Which of the following is a goal of the project charter?

Options:

A.

Detail requirements for the project tasks.

B.

Empower the project manager to manage the project.

C.

List all tasks the team should perform in the project.

D.

Develop a business case to support the project.

Buy Now
Questions 299

Which Process Group and Knowledge Area include the Sequence Activities process?

Options:

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Buy Now
Questions 300

An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

Options:

A.

smooth/accommodate.

B.

force/direct,

C.

collaborate/problem solve,

D.

compromise/reconcile.

Buy Now
Questions 301

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Buy Now
Questions 302

When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?

Options:

A.

Iterative scheduling with backlog

B.

On-demand scheduling

C.

Life cycle scheduling with backlog

D.

Defining Iterative activities

Buy Now
Questions 303

An organization ' s project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?

Options:

A.

Organizational systems access

B.

Organizational process assets

C.

Resources management plan

D.

Procurement management plan

Buy Now
Questions 304

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

Options:

A.

Mitigate

B.

Transfer

C.

Share

D.

Avoid

Buy Now
Questions 305

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Buy Now
Questions 306

The process of defining how the project scope will be validated and controlled is known as:

Options:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Buy Now
Questions 307

A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?

Options:

A.

Create a risk in the risk register for each S1 defect and assign actions.

B.

Consult the risk register and implement the risk response actions.

C.

Ask the developers to work longer hours and resolve the defects.

D.

Review the organizational chart to find out who else can sign off UAT.

Buy Now
Questions 308

Inputs to the Plan Schedule Management process include:

Options:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

Buy Now
Questions 309

Change requests are processed for review and disposition according to which process?

Options:

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Questions 310

What is a tailoring consideration for Project Scope Management ' ?

Options:

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Buy Now
Questions 311

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Options:

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

Buy Now
Questions 312

Which item is an input to the Define Activities process?

Options:

A.

Schedule data

B.

Activity list

C.

Risk register

D.

Scope baseline

Buy Now
Questions 313

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Buy Now
Questions 314

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

Options:

A.

Customers.

B.

Business partners.

C.

Sellers.

D.

Functional managers.

Buy Now
Questions 315

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (TandM)

Buy Now
Questions 316

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Buy Now
Questions 317

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

Options:

A.

Brainstorming, Monte Carlo simulation, analogous estimation

B.

Three-point estimation, resources leveling, iteration burndown chart

C.

Milestone charts, parametric estimation, schedule baseline

D.

Parametric estimation, three-point estimation, meetings

Buy Now
Questions 318

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Buy Now
Questions 319

Which tool uses an algorithm based on historical data to calculate cost?

Options:

A.

Three-point estimating

B.

Parametric estimating

C.

Analogous estimating

D.

Relative estimating

Buy Now
Questions 320

Projects are separated into phases or subprojects; these phases include:

Options:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Buy Now
Questions 321

Which of the following correctly explains the term " progressive elaboration ' ?

Options:

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

Buy Now
Questions 322

What purpose does the hierarchical locus of stakeholder communications serve?

Options:

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Buy Now
Questions 323

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Buy Now
Questions 324

An intentional activity to modify a nonconforming product or product component is called:

Options:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

Buy Now
Questions 325

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Buy Now
Questions 326

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Buy Now
Questions 327

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

Options:

A.

The development team ran out of time and did not pull the social media story from the backlog.

B.

The development team completed all of the stories identified by the product owner as having the highest customer value.

C.

The sprint demo went smoothly and the team did not find any open issues.

D.

The social media story is a marketing priority and less important than other priorities.

Buy Now
Questions 328

An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed.

What project management approach should the organization use?

Options:

A.

Predictive

B.

Hybrid

C.

Iterative

D.

Adaptive

Buy Now
Questions 329

Which process numerically analyzes the effect of identified risks on overall project objectives?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 330

What should a project manager use to determine how much money is needed to complete a project?

Options:

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Buy Now
Questions 331

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Buy Now
Questions 332

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Buy Now
Questions 333

Which statement describes the relationship between Manage Quality process and Control process?

Options:

A.

Manage Quality is all about following planned processes and provedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.

B.

Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.

C.

Manage Quality and Control Quality are the same

D.

Manage Quality is part of Quality Management and Control is a subset of the Stakeholder Management Process group

Buy Now
Questions 334

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Buy Now
Questions 335

A project sponsor has asked the project manager to determine how soon the project can be completed. Which of the following methods can a project manager use to find this information?

Options:

A.

Scope baseline

B.

Decomposition

C.

Critical path method (CPM)

D.

Work breakdown structure (WBS)

Buy Now
Questions 336

Which of the following includes how requirements activities will be planned, tracked, and reported?

Options:

A.

Configuration management plan

B.

Scope baseline

C.

Requirements management plan

D.

Schedule baseline

Buy Now
Questions 337

Which Process Group includes the Manage Stakeholder Engagement process?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

Buy Now
Questions 338

Which process involves developing an approximation of the monetary resources needed to complete project activities?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Buy Now
Questions 339

An input to the Manage Project Team process is:

Options:

A.

Work performance reports.

B.

Change requests.

C.

Activity resource requirements.

D.

Enterprise environmental factors.

Buy Now
Questions 340

A project manager held a meeting and listed all team members ' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

Options:

A.

Focus groups

B.

Interviews

C.

Brainstorming

D.

Delphi technique

Buy Now
Questions 341

What tool or technique will establish expected behaviors for project team members?

Options:

A.

Ground rules

B.

Decision mating

C.

Power/influence grid

D.

Stakeholder engagement assessment matrix

Buy Now
Questions 342

The staffing management plan is part of the:

Options:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Buy Now
Questions 343

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

Options:

A.

2.0

B.

45

C.

0.5

D.

15

Buy Now
Questions 344

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

Options:

A.

Work breakdown structure (WBS)

B.

Approval from the stakeholders

C.

Feasibility study of the solution

D.

Root cause analysis of the problem

Buy Now
Questions 345

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client ' s project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

Options:

A.

Cost management plan

B.

Business management plan

C.

Stakeholder engagement plan

D.

Resource management plan

Buy Now
Questions 346

What tool or technique is primarily used to plan risk responses ' ?

Options:

A.

Risk categorization

B.

Project risk document updates

C.

Strategies for overall project risk

D.

Risk management plan

Buy Now
Questions 347

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

Options:

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Buy Now
Questions 348

Which of the following types of a dependency determination is used to define the sequence of activities?

Options:

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Buy Now
Questions 349

Change request status updates are an output of which process?

Options:

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Buy Now
Questions 350

What purpose does the hierarchical focus of stakeholder communications serve?

Options:

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the focus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Buy Now
Questions 351

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 352

Which process determines the risks that might affect the project?

Options:

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 353

Which is an output from Distribute Information?

Options:

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

Buy Now
Questions 354

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Buy Now
Questions 355

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

Options:

A.

Control charts

B.

Pareto diagrams

C.

Ishikavva diagrams

D.

Checksheets

Buy Now
Questions 356

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

Options:

A.

Scope and impact of change to stakeholders

B.

Project scope and stakeholders goals

C.

Engagement level of key stakeholders

D.

Stakeholders expectations for the project

Buy Now
Questions 357

Which of the following are three inputs to the risk register?

Options:

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Buy Now
Questions 358

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

Options:

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Buy Now
Questions 359

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Buy Now
Questions 360

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 361

A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?

Options:

A.

Prioritize requirements.

B.

Document requirements.

C.

Trace requirements.

D.

Validate requirements.

Buy Now
Questions 362

In which project risk management process is the data analysis technique not used?

Options:

A.

Plan Risk Management

B.

Implement Risk Response

C.

Monitor Risks

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 363

Perform Quantitative Analysis focuses on:

Options:

A.

compiling a lsit of known risks and preparing responses to them

B.

assessing the probability of occurrence and impact for every risk in the risk register

C.

evaluating the contingency and management reserves required for the project

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives

Buy Now
Questions 364

Which characteristic do projects and operational work share in common?

Options:

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Buy Now
Questions 365

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

Options:

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

Buy Now
Questions 366

A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team ' s workflow at any moment, the project manager will need to restrict the maximum amount of activities to be performed.

Which element will the project manager handle?

Options:

A.

Capacity limit

B.

Pull system

C.

Work in progress

D.

Virtual board

Buy Now
Questions 367

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Options:

A.

List of identified risks, potential risk owners, list of potential risk response

B.

List of identified risks, list of causes, list of risk categories

C.

Short risk titles, list of potential risk owners, list of impacts on objectives

D.

List of activities affected, list of potential risk responses, list of causes

Buy Now
Questions 368

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Buy Now
Questions 369

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Buy Now
Questions 370

Which of the following items is a technique for data gathering?

Options:

A.

Facilitation

B.

Meeting management

C.

Conflict management

D.

Interviews

Buy Now
Questions 371

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

Options:

A.

Direct

B.

Interactive

C.

Pull

D.

Push

Buy Now
Questions 372

Which tasks should a project manager perform in order to manage the project schedule effectively?

Options:

A.

Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities. Develop Schedule

B.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule. Control Schedule

C.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities. Develop Schedule

D.

Define Activities. Sequence Activities, Estimate Activity Durations. Define Quality of Activities. Estimate Cost of Activities, Develop Schedule

Buy Now
Questions 373

Which are required to create the schedule management plan?

Options:

A.

Scope baseline, work breakdown structure (WBS), estimated costs, and milestone list

B.

Resource management plan, organizational process assets, activity list, and business case

C.

Enterprise environmental factors, organizational process assets, project charter, and project management plan

D.

Activity list, project statement of work, project charter, and communications management plan

Buy Now
Questions 374

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Buy Now
Questions 375

An input to Develop Project Charter is a/an:

Options:

A.

Business case.

B.

Activity list.

C.

Project management plan.

D.

Cost forecast.

Buy Now
Questions 376

How can a project manager ensure effective project stakeholder engagement?

Options:

A.

Build a stakeholder responsibility matrix

B.

Hold weekly project staff meetings

C.

Improve interpersonal and team leadership skills

D.

Create detailed project reports for stakeholders

Buy Now
Questions 377

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Buy Now
Questions 378

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options:

A.

Acquire Resources

B.

Control Resources

C.

Manage Team

D.

Develop Team

Buy Now
Questions 379

Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?

Options:

A.

Interactive communications

B.

Pull communications

C.

Push communications

D.

Communication style assessment

Buy Now
Questions 380

" Tailoring " is defined as the:

Options:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

B.

act of creating a project team with the specialized skills required to produce a required product or service.

C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Buy Now
Questions 381

During project selection, which factor is most important?

Options:

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Buy Now
Questions 382

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Buy Now
Questions 383

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Requested changes

B.

Approved change requests

C.

Work performance information

D.

Implemented defect repair

Buy Now
Questions 384

Which tool or technique is effective in a project in which the deliverable is not a service or result?

Options:

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Buy Now
Questions 385

Which of the following lists of tools and techniques is used when conducting procurements?

Options:

A.

Expert judgement, procurement negotiations, bidder conferences, proposal evaluation advertising and independent estimates

B.

Budgeting procurement negotiations, bidder conferences, proposal evaluation and advertising, and seller ' s proposal C. Expert judgement, procurement negotiations bidder conferences, proposal evaluation and advertising, and make-or-buy decisions

C.

Agreements procurement negotiations, bidder conferences, proposal evaluation and advertising selected seller

Buy Now
Questions 386

What is the goal of the control quality process in project management?

Options:

A.

To monitor the activities of the project and ensure Iho work is being executed as it was planned

B.

To obtain a quality cerlific ation for the product of the project service or result

C.

To assess performance and ensure the project product, service, or result meets the customer ' s expectations

D.

To test the product service, or result to determine if the errors observed are within the defined quality margins

Buy Now
Questions 387

How can a project manager represent a contingency reserve in the schedule?

Options:

A.

Additional weeks of work to account for unknown-unknowns risks

B.

Task duration estimates of the best case scenarios

C.

Addition Duration estimates in response to identified risks that have been accepted

D.

Milestones representing the completion of deliverables

Buy Now
Questions 388

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Buy Now
Questions 389

Which process determines the correctness of deliverables?

Options:

A.

Verify Deliverables

B.

Validate Deliverables

C.

Review Deliverables

D.

Analyze Deliverables

Buy Now
Questions 390

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

Options:

A.

0.45

B.

0.56

C.

0.70

D.

1.36

Buy Now
Questions 391

Assigned risk ratings are based upon:

Options:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders ' tolerances.

Buy Now
Questions 392

Portfolio Management is management of:

Options:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Buy Now
Questions 393

Match each dimension of the communications management plan to its corresponding focus.

CAPM Question 393

Options:

Buy Now
Questions 394

What is the name of a graphic display of project team members and their reporting relationships?

Options:

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Buy Now
Questions 395

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Options:

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Buy Now
Questions 396

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jun 5, 2026
Questions: 1320

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99