In sourcing packaging for industrial purposes, which of the following will be MOST useful for monitoring price behavior?
A sourcing manager needs to outsource production in order to meet demand for a specific product. The internal production schedule and forecasted sales have been provided for the next nine months. Internal production follows a level schedule of 4,000 units per month and up to 7,000 units may be stored in inventory. There is no beginning inventory for January. During what month(s) will outsourced production be required to meet forecasted sales?
MonthJanFebMarAprMayJunJulAugSep
Unit Sales3,0003,0004,0001,0009,0005,0004,0003,0005,000
A manufacturing firm prepares the following materials requirement plan (MRP):
Master Production Schedule
Week123456
Item A101015152020
Relevant Information
ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory
ANone1 weekLFL50
BA2 weeks5010
CB2 weeks5010
Using MRP methodology, how much of Item B should be ordered, and when should it be ordered7
A supply manager receives four bids for a special piece of equipment. The equipment is large and does not fit into a normal sea container. The bids are as follows:
Supplier 1Supplier 2Supplier 3Supplier 4
Bid$2,110,000$2,105,000$2,110,000$2,115,000
Incoterms® 2020 RuleGIFDPUFCAFAS
The costs of transportation, included within each bid price, are as follows:
Responsibility for Payment to CarrierTransfer of Risk to BuyerCost of Transportation
Supplier, before goods are loaded onto vessel: purchaser thereafterAlongside vessel nominated by purchaser$50,000
Supplier to named port of destination: purchaser thereafterOnce goods have been loaded onto the vessel$55,000
Supplier to named place of destination once unloaded: purchaser thereafterOnce goods have been unloaded at named place of destination540,000
PurchaserWhere goods are loaded onto the collecting vehicle$30,000
The supply manager has taken account the firm's risk profile and wishes to use FCA for its Incoterms® 2020 rules. Adjusting the pricing in the tenders to reflect this, which supplier should be awarded the contract (based on the lowest price)?
A manufacturing firm redesigns its premier product to benefit from material standardization. This will entail re-tooling its manufacturing facility. The firm conducts a cost analysis using net present value (NPV) and considers four options. Option 1 is to make no change at all. Options 2, 3, and 4 represent different re-tooling configurations. The discount rate for NPV calculation is 10% per annum, and material costs are fixed for the next 3 years. The firm follows a three-year planning cycle and wishes to apply NPV over that time period to the calculations:
Option 1Option 2Option 3Option 4
Re-tooling Costs$0$500,000$800,000$950,000
Annual Material Costs$1,100,000$900,000$800,000$750,000
NPV = £ r.i (l*r/
What is the 3-year NPV of the best option’
A manufacturer of gardening products has many international suppliers. Because of extended lead-times and logistical concerns, it is critical that the company provides accurate seasonal demand planning data to its suppliers. Given this situation, which of the following types of feedback from the supplier would be MOST critical to the manufacturer?
A firm hires a contractor to build a new warehouse. During construction, the firm decides it wants to modify the contract to add an office area to the facility. Which of the following is the BEST course of action for the firm to take in this situation?
A supplier of aircraft seating receives a forecast from a major aircraft manufacturer. The forecast information is considered confidential, and thus the supplier must sign a Non-Disclosure Agreement (NDA). Given this situation, which of the following is MOST likely to be protected by the NDA?
A company finds that delays and cost overruns are creating problems in its service contracts. To improve this situation, which of the following should the firm do FIRST?
A large retailer and one of its suppliers establish a process to combine intelligence from both organizations in order to improve product availability while reducing inventory, transportation, and logistics costs. This process is known as which of the following?
A cell phone retailer experiences excess inventory of a particular model due to errors in demand forecasting. In addition, remorse returns of this model are greater than anticipated. Which of the following is the BEST course of action the company can take to recover value from these assets?
Based on the global reach and complexity of supply chains, resiliency planning and risk assessment are necessary because of which of the following’
To ensure items frequently employed in production are immediately available for Kanban replenishment, a storage location is established specifically for these items. This inventory location is known as a(n)
MNO, Inc. is a national retail home goods chain formed of local franchisees. Each franchisee uses its own returns processing systems. A key advertising point for MNO is its liberal return policy, which is part of its overall focus on excellent customer service. While feedback from customers is positive regarding MNO’s return policy, there have been inquiries as to why stores handle returns via different processes. MNO’s supply manager suggests the implementation of a reverse supply chain to deal with this issue and possibly yield cost enhancement opportunities. In order to implement this, which of the following is the FIRST course of action the supply manager should take’’
A company produces and distributes its products in the continental United States, mostly to customers located in metropolitan areas. The company conducts an ABC analysis to classify items, and determines that A and B items have variable demand, while C items have relatively stable demand. The logistics group wants to use this information to minimize transportation costs. Which of the following is the BEST combination of modes for the firm to use in order to minimize costs?
FGH, Inc., a specialty construction company located in Italy, orders bulky customized sound equipment from a sole-source supplier in Asia. The equipment is to be installed in a new auditorium that FGH is constructing. Failure to complete the project in time for its scheduled opening will subject FGH to penalties. FGH receives notice from the supplier that the equipment is packaged and ready to ship as planned via ocean freight but that an impending storm may cause delays. FGH needs to stay within budget. In this situation, which of following is the BEST course of action for FGH to take?
Which of the following BEST explains why forecast accuracy is important in contracts with suppliers?
A company determines that demand for an item is steady at 800 units per month, and that the cost of ordering and receiving the item is $300, regardless of how much is ordered. The per item charge is $5, and holding costs are 20% annually. Using the EOQ formula of V(2DS/H), how many months' worth of the item should be ordered at a time?
A company needs 1,000 widgets in Year 1 and projects that it will need 1,200 widgets in Year 2. The Year 1 order cost for widgets is $5, and the Year 1 carrying cost is S4. A recent contract renewal with the company's 3PL warehouse supplier will increase carrying costs in Year 2 to S6. How, if at all, will the Economic Order Quantity (EOQ) be affected?
A manufacturer has facilities around the world and purchases steel from various global markets. The firm uses decentralized purchasing, with a procurement team in each of its various markets. Management would like to see a corporate approach to steel procurement. Which of the following should the firm's supply manager recommend?
An ERP purchasing module indicates a gross requirement of 100 units for part number A123. There is an open purchase order for 55 units. The item master for this supplier shows an order lot size of 30 units each. In this situation, how many units of this part will the exception report indicate should be ordered7
Over the past 90 days, a buying company's manufacturing engineers have reported an increase in the number of defective parts received from a key supplier. The engineers report that there are three different types of defects occurring, and that they are all being discovered during production. The supplier states that it does not have enough resources to assess the root cause of the three types of defects all at one time. Which of the following should the buying firm do in this instance?
Identifying risks is MOST associated with which of the following stages of a project?
A company finds that tracking demand for products sold at its retail outlets makes forecasting a challenge. Which of the following would be MOST useful in providing rapid updates when dealing with suppliers?
A manufacturing firm redesigns its premier product to benefit from material standardization. The change will entail re-tooling costs. The firm conducts a cost benefit analysis on four possible options. Option 1 is to make no change at all. Options 2, 3, and 4 represent different re-tooling configurations involving different materials:
Option 1Option 2Option 3Option 4
Re-tooling Costs (Year 1)$0$800,000$1,000,000$1,200,000
Material Costs
Year 151,000,000$700,000$650,000$600,000
Year 2$1,100,000$750,000$700,000$650,000
Year 3SI,200,000$800,000$750,000$700,000
Year 451,300,000$850,000$800,000$750,000
Year 551,400,000$900,000$850,000$800,000
Total$6,000,000$4,000,000$3,750,000$3,500,000
Labor Costs
Year 1$1,000,000$700,000$650,000$600,000
Year 2$1,100,000$770,000$715,000S660,000
Year 3$1,210,000$847,000$786,500$726,000
Year 4$1,331,000$931,700$865,150$798,600
Year 5$1,464,100$1,024,870$951,665$878,460
Total$6,105,100$4,273,570$3,968,315$3,663,060
In addition to this, there will be a cost of $3.5 million in lost production during Year 1, should any of the re-tooling options (2, 3, or 4) be selected.
The firm wants to rank the options in order of financial preference, from the best option to the worst. Based on this information, how should the four options be ranked?
A manufacturer is working to standardize high-volume, low-cost hardware components used in its assembly process. The manufacturer wants to transfer some of the risks associated with inventory carrying costs, warehousing costs, and re-stocking costs to the supplier. Which of the following will be MOST useful in accomplishing this goal?
A utility installation company conducts an annual review of its assets. Included with its equipment are several trenching machines that were purchased three years ago at a cost of $85,000 each. How should this value be categorized in the asset management system?
A company supply manager conducts a review of current freight contracts and finds that payments to the primary carrier for outbound shipments have been based on a published rate schedule, which is revised annually. The supply manager believes the shipping costs may be higher than necessary. In order to reduce outbound transportation costs, which of the following should the supply manager do FIRST’
A firm is looking to expand to a larger warehouse. Which of the following should be given the GREATEST consideration when determining the new warehouse's environmental impact?
A manufacturer purchased a piece of production equipment over 20 years ago. The equipment is still in use, though for the last few quarters, it has been getting more difficult to keep it operational, as many of the required components are turning obsolete. According to the service agreement, the supplier must ensure the availability of the component parts for 3 more years. In this situation, the buying firm should expect that the supplier will
A firm hires a new staff member in its warehousing department. As a FIRST step in the training of this employee, the warehouse manager should
Which of the following refers to the practice of buying a commodity on the open market for immediate delivery?
Which of the following are the quickest ways to ship food products in order to ensure they do not spoil?
A company develops long range material forecasts, analyzes industry trends, determines commodities for value analysis, and assesses supplier capabilities to assure continual economic supply of goods and services. This company is engaged in
How long after the delivery date must a freight claim on a motor carriage shipment be presented and filed with the carrier in the United States’
A manufacturer of gas-powered motors realigns its supply chain to fit a new business segment. In the past, the firm focused on customized designs. Now, it wishes to compete in the electric motor market, which is highly competitive and price-sensitive. Given this situation, which of the following will ensure that the firm has the proper planning in place?
An organization purchases materials beyond current and anticipated requirements in expectation of a price increase or shortage, in the hope that it will profit from the sale of the materials at a later date. This describes which of the following buying strategies?
The sourcing manager for a regional retail bakery chain reviews order quantities and stocking for perishable condiments on a quarterly basis. Which of the following factors should be the MOST critical consideration in this analysis?
A manufacturer has historically ordered fasteners utilizing monthly fixed order quantities. The firm wishes to explore the feasibility of using economic order quantity (EOQ), and determines that the EOQ is less than the supplier’s quoted price break. Which of the following is the BEST course of action for the firm to take?
A company purchases raw materials from a domestic supplier that offers competitive overland transportation rates. The firm requires the goods be delivered to its manufacturing plant. Which of the following Incoterms® 2020 rules should be used if the firm wants risk to transfer at the manufacturing plant?
XYZ, Inc. is a manufacturer and distributor of fishing gear. XYZ relies on poorly-executed forecasts from its retail partners, which leads to exaggerated demand. This in turn leads to XYZ experiencing increased inventory, material handling concerns, and difficulties managing its accounts payable. Which of the following BEST describes what is occurring in this situation?
A disaster response manager plans to deliver pallets of bottled water to volunteers at a disaster site. The water comes from a nearby bottling company at a preferential cost of $50 per pallet. The number of pallets of bottled water needed is impossible to know in advance due to numerous variables, although experience indicates that the likelihood of consumption is equal: a 25% chance each for 1, 2, 3 or 4 pallets of bottled water. If a full pallet is returned, a restocking fee of 520 is charged. If not enough water is brought in, the cost of purchasing a pallet of water on location is expected to be $200.
How many pallets should the manager deliver?