Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

INTE Supply Management Integration Questions and Answers

Questions 4

In sourcing packaging for industrial purposes, which of the following will be MOST useful for monitoring price behavior?

Options:

A.

Consumer Price Index - All Items

B.

Producer Price Index - Intermediate Materials

C.

Producer Price Index - Finished Goods

D.

Consumer Price Index - All Items Less Food & Energy

Buy Now
Questions 5

A sourcing manager needs to outsource production in order to meet demand for a specific product. The internal production schedule and forecasted sales have been provided for the next nine months. Internal production follows a level schedule of 4,000 units per month and up to 7,000 units may be stored in inventory. There is no beginning inventory for January. During what month(s) will outsourced production be required to meet forecasted sales?

MonthJanFebMarAprMayJunJulAugSep

Unit Sales3,0003,0004,0001,0009,0005,0004,0003,0005,000

Options:

A.

June, July and September

B.

June only

C.

July only

D.

May, June and September

Buy Now
Questions 6

A manufacturing firm prepares the following materials requirement plan (MRP):

Master Production Schedule

Week123456

Item A101015152020

Relevant Information

ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory

ANone1 weekLFL50

BA2 weeks5010

CB2 weeks5010

Using MRP methodology, how much of Item B should be ordered, and when should it be ordered7

Options:

A.

50 items immediately and 50 items in week 3

B.

20 items in week 4 and 20 items in week 5

C.

10 items in week 2 and 20 items in week 3

D.

50 items in week 2

Buy Now
Questions 7

A supply manager receives four bids for a special piece of equipment. The equipment is large and does not fit into a normal sea container. The bids are as follows:

Supplier 1Supplier 2Supplier 3Supplier 4

Bid$2,110,000$2,105,000$2,110,000$2,115,000

Incoterms® 2020 RuleGIFDPUFCAFAS

The costs of transportation, included within each bid price, are as follows:

Responsibility for Payment to CarrierTransfer of Risk to BuyerCost of Transportation

Supplier, before goods are loaded onto vessel: purchaser thereafterAlongside vessel nominated by purchaser$50,000

Supplier to named port of destination: purchaser thereafterOnce goods have been loaded onto the vessel$55,000

Supplier to named place of destination once unloaded: purchaser thereafterOnce goods have been unloaded at named place of destination540,000

PurchaserWhere goods are loaded onto the collecting vehicle$30,000

The supply manager has taken account the firm's risk profile and wishes to use FCA for its Incoterms® 2020 rules. Adjusting the pricing in the tenders to reflect this, which supplier should be awarded the contract (based on the lowest price)?

Options:

A.

Supplier 4

B.

Supplier 2

C.

Supplier 1

D.

Supplier 3

Buy Now
Questions 8

A manufacturing firm redesigns its premier product to benefit from material standardization. This will entail re-tooling its manufacturing facility. The firm conducts a cost analysis using net present value (NPV) and considers four options. Option 1 is to make no change at all. Options 2, 3, and 4 represent different re-tooling configurations. The discount rate for NPV calculation is 10% per annum, and material costs are fixed for the next 3 years. The firm follows a three-year planning cycle and wishes to apply NPV over that time period to the calculations:

Option 1Option 2Option 3Option 4

Re-tooling Costs$0$500,000$800,000$950,000

Annual Material Costs$1,100,000$900,000$800,000$750,000

NPV = £ r.i (l*r/

What is the 3-year NPV of the best option’

Options:

A.

$2,939,000

B.

$2,692,712

C.

$2,961,983

D.

$2,735,537

Buy Now
Questions 9

A manufacturer of gardening products has many international suppliers. Because of extended lead-times and logistical concerns, it is critical that the company provides accurate seasonal demand planning data to its suppliers. Given this situation, which of the following types of feedback from the supplier would be MOST critical to the manufacturer?

Options:

A.

Price increases on key components

B.

Anticipated production schedules and capacity planning

C.

Notification of any constraints to meeting demands

D.

Planned delivery schedules

Buy Now
Questions 10

A project charter addresses which of the following areas?

Options:

A.

Problem statement, budget, timeline, work breakdown structure, project team, and sponsor's approval

B.

Problem statement, scope, constraints, milestones, team and authority, risk, and sponsor's approval

C.

Problem statement, statement of work, resource requirements, milestones, and sponsor's approval

D.

Problem statement, team, roles and responsibilities, cost structure, timelines, and sponsor's approval

Buy Now
Questions 11

Which of the following circumstances MOST warrants expediting?

Options:

A.

A new order placement for standard inventory parts

B.

A purchase order for a part under evaluation for an engineering change

C.

A purchase order that is currently past due from the supplier

D.

A purchase order for parts with a history of defects

Buy Now
Questions 12

A firm hires a contractor to build a new warehouse. During construction, the firm decides it wants to modify the contract to add an office area to the facility. Which of the following is the BEST course of action for the firm to take in this situation?

Options:

A.

Verbally notify the contractor of the changes, negotiate the costs, and instruct the contractor to proceed with the change and write the change order at the time of project completion

B.

Develop a written description of the changes, and negotiate a written change order that minimizes the cost impact while work continues on the warehouse

C.

Stop construction on the warehouse and negotiate the change order with the contractor before resuming work

D.

Advise the contractor on how much the firm has available to build the new office area, and write a change order based on the final amount of the revisions

Buy Now
Questions 13

A supplier of aircraft seating receives a forecast from a major aircraft manufacturer. The forecast information is considered confidential, and thus the supplier must sign a Non-Disclosure Agreement (NDA). Given this situation, which of the following is MOST likely to be protected by the NDA?

Options:

A.

The time frame expected for completion

B.

The start date of the project

C.

The number of aircraft anticipated to be built

D.

The name of the end customer submitting the request for bid

Buy Now
Questions 14

A company finds that delays and cost overruns are creating problems in its service contracts. To improve this situation, which of the following should the firm do FIRST?

Options:

A.

Renegotiate pricing with current service suppliers

B.

Convert cost reimbursable contracts into fixed prices

C.

Revise the company's standard contract template for all of its services

D.

Establish progress milestones and monitoring for existing contracts

Buy Now
Questions 15

A large retailer and one of its suppliers establish a process to combine intelligence from both organizations in order to improve product availability while reducing inventory, transportation, and logistics costs. This process is known as which of the following?

Options:

A.

Vendor-managed inventory

B.

Collaborative planning, forecasting and replenishment

C.

Sales and operations planning

D.

Enterprise resource planning

Buy Now
Questions 16

A cell phone retailer experiences excess inventory of a particular model due to errors in demand forecasting. In addition, remorse returns of this model are greater than anticipated. Which of the following is the BEST course of action the company can take to recover value from these assets?

Options:

A.

Execute an online auction in the secondary market to resell the new devices and the remorse returns

B.

Deploy a permanent e-commerce platform for the sale of the assets, as this will be useful for any future instances of excess and remorse return

C.

Contract with a third-party specialist for the destruction of the returned assets and the resale of the raw materials that result

D.

Use an e-commerce provider for the sale of the device using a revenue share and risk compliance model

Buy Now
Questions 17

Based on the global reach and complexity of supply chains, resiliency planning and risk assessment are necessary because of which of the following’

Options:

A.

Supplier bankruptcies in competitive markets

B.

Natural and man-made disasters

C.

Lack of training within the organization

D.

Uncollected receivables

Buy Now
Questions 18

Which of the following requires investment recovery action’

Options:

A.

Finished goods

B.

Work-in-process

C.

Raw materials

D.

Slow-moving materials

Buy Now
Questions 19

To ensure items frequently employed in production are immediately available for Kanban replenishment, a storage location is established specifically for these items. This inventory location is known as a(n)

Options:

A.

overflow location

B.

random location

C.

point-of-use location

D.

fixed location

Buy Now
Questions 20

Which of the following is a key requirement of xRP7

Options:

A.

Data integrity

B.

Supplier consolidation

C.

Smoothing algorithms

D.

Should-cost data

Buy Now
Questions 21

MNO, Inc. is a national retail home goods chain formed of local franchisees. Each franchisee uses its own returns processing systems. A key advertising point for MNO is its liberal return policy, which is part of its overall focus on excellent customer service. While feedback from customers is positive regarding MNO’s return policy, there have been inquiries as to why stores handle returns via different processes. MNO’s supply manager suggests the implementation of a reverse supply chain to deal with this issue and possibly yield cost enhancement opportunities. In order to implement this, which of the following is the FIRST course of action the supply manager should take’’

Options:

A.

Define a consistent return process and integrate it into the forward supply chain

B.

Hire an external returns specialist to monitor the situation

Buy Now
Questions 22

A company produces and distributes its products in the continental United States, mostly to customers located in metropolitan areas. The company conducts an ABC analysis to classify items, and determines that A and B items have variable demand, while C items have relatively stable demand. The logistics group wants to use this information to minimize transportation costs. Which of the following is the BEST combination of modes for the firm to use in order to minimize costs?

Options:

A.

Use water service for A and B items, motor carriage for C items, and air freight only as needed

B.

Use intermodal rail for A and B items, air freight for C items, and motor carriage only as needed

C.

Use air freight for A and B items, motor carriage for C items, and intermodal rail only as needed

D.

Use motor carriage for A and B items, intermodal rail for C items, and air freight only as needed

Buy Now
Questions 23

FGH, Inc., a specialty construction company located in Italy, orders bulky customized sound equipment from a sole-source supplier in Asia. The equipment is to be installed in a new auditorium that FGH is constructing. Failure to complete the project in time for its scheduled opening will subject FGH to penalties. FGH receives notice from the supplier that the equipment is packaged and ready to ship as planned via ocean freight but that an impending storm may cause delays. FGH needs to stay within budget. In this situation, which of following is the BEST course of action for FGH to take?

Options:

A.

Wait until the storm's path can be predicted more accurately

B.

Evaluate options for a multimodal shipment

C.

Arrange for immediate air freight of the equipment

D.

Use ocean freight after the storm subsides

Buy Now
Questions 24

Which of the following BEST explains why forecast accuracy is important in contracts with suppliers?

Options:

A.

It locks in the lowest possible cost to the organization over the life of the contract.

B.

. It allows the buying firm to gauge supplier performance degradation over the life of the contract.

C.

It improves continuity of supply while allowing the supplier to reduce costs over time.

D.

It allows the organization more freedom in procuring supply in the market.

Buy Now
Questions 25

A company determines that demand for an item is steady at 800 units per month, and that the cost of ordering and receiving the item is $300, regardless of how much is ordered. The per item charge is $5, and holding costs are 20% annually. Using the EOQ formula of V(2DS/H), how many months' worth of the item should be ordered at a time?

Options:

A.

2

B.

4

C.

3

D.

1

Buy Now
Questions 26

A company needs 1,000 widgets in Year 1 and projects that it will need 1,200 widgets in Year 2. The Year 1 order cost for widgets is $5, and the Year 1 carrying cost is S4. A recent contract renewal with the company's 3PL warehouse supplier will increase carrying costs in Year 2 to S6. How, if at all, will the Economic Order Quantity (EOQ) be affected?

Options:

A.

The EOQ will increase in Year 2 to 54 units.

B.

The EOQ will stay the same in Year 2.

C.

The EOQ will decrease in Year 2 to 32 units.

D.

The EOQ will decrease in Year 2 to 45 units.

Buy Now
Questions 27

A manufacturer has facilities around the world and purchases steel from various global markets. The firm uses decentralized purchasing, with a procurement team in each of its various markets. Management would like to see a corporate approach to steel procurement. Which of the following should the firm's supply manager recommend?

Options:

A.

A lead business unit for steel, to interface and handle procurement and strategy for each market

B.

A sourcing committee with a representative from each market, to facilitate global steel strategy

C.

Regional procurement groups that focus on steel negotiations and strategies for each market

D.

A corporate steering committee to advise on strategy and act as a liaison with major suppliers

Buy Now
Questions 28

An ERP purchasing module indicates a gross requirement of 100 units for part number A123. There is an open purchase order for 55 units. The item master for this supplier shows an order lot size of 30 units each. In this situation, how many units of this part will the exception report indicate should be ordered7

Options:

A.

60

B.

100

C.

45

D.

30

Buy Now
Questions 29

Over the past 90 days, a buying company's manufacturing engineers have reported an increase in the number of defective parts received from a key supplier. The engineers report that there are three different types of defects occurring, and that they are all being discovered during production. The supplier states that it does not have enough resources to assess the root cause of the three types of defects all at one time. Which of the following should the buying firm do in this instance?

Options:

A.

Work with engineering to determine the impact each defect type has on the customer base and assist the supplier in prioritizing and solving the defect type with the highest customer impact first

B.

Calculate the number of times each of the defect types have occurred over the past 90 days, and instruct the supplier to work on finding the root cause of the defect with the highest frequency

C.

Calculate the number of times each of the defect types have occurred over the past two weeks, and instruct the supplier to work on finding the root cause of the defect with the highest frequency

D.

Work with engineering to submit three corrective action requests and ask the supplier to address all three

Buy Now
Questions 30

Identifying risks is MOST associated with which of the following stages of a project?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Buy Now
Questions 31

A company finds that tracking demand for products sold at its retail outlets makes forecasting a challenge. Which of the following would be MOST useful in providing rapid updates when dealing with suppliers?

Options:

A.

Regression analysis of future sales

B.

Safety stock review

C.

Point-of-sale system

D.

Probability modeling

Buy Now
Questions 32

A manufacturing firm redesigns its premier product to benefit from material standardization. The change will entail re-tooling costs. The firm conducts a cost benefit analysis on four possible options. Option 1 is to make no change at all. Options 2, 3, and 4 represent different re-tooling configurations involving different materials:

Option 1Option 2Option 3Option 4

Re-tooling Costs (Year 1)$0$800,000$1,000,000$1,200,000

Material Costs

Year 151,000,000$700,000$650,000$600,000

Year 2$1,100,000$750,000$700,000$650,000

Year 3SI,200,000$800,000$750,000$700,000

Year 451,300,000$850,000$800,000$750,000

Year 551,400,000$900,000$850,000$800,000

Total$6,000,000$4,000,000$3,750,000$3,500,000

Labor Costs

Year 1$1,000,000$700,000$650,000$600,000

Year 2$1,100,000$770,000$715,000S660,000

Year 3$1,210,000$847,000$786,500$726,000

Year 4$1,331,000$931,700$865,150$798,600

Year 5$1,464,100$1,024,870$951,665$878,460

Total$6,105,100$4,273,570$3,968,315$3,663,060

In addition to this, there will be a cost of $3.5 million in lost production during Year 1, should any of the re-tooling options (2, 3, or 4) be selected.

The firm wants to rank the options in order of financial preference, from the best option to the worst. Based on this information, how should the four options be ranked?

Options:

A.

2, 3, 1, 4

B.

4, 1, 3, 2

C.

4, 3, 2, 1

D.

1, 2, 3, 4

Buy Now
Questions 33

A manufacturer is working to standardize high-volume, low-cost hardware components used in its assembly process. The manufacturer wants to transfer some of the risks associated with inventory carrying costs, warehousing costs, and re-stocking costs to the supplier. Which of the following will be MOST useful in accomplishing this goal?

Options:

A.

Vendor-managed inventory

B.

Reorder-point system

C.

Safety stock

D.

Kanban

Buy Now
Questions 34

A utility installation company conducts an annual review of its assets. Included with its equipment are several trenching machines that were purchased three years ago at a cost of $85,000 each. How should this value be categorized in the asset management system?

Options:

A.

Equity

B.

Book

C.

Market

D.

Historic

Buy Now
Questions 35

A company supply manager conducts a review of current freight contracts and finds that payments to the primary carrier for outbound shipments have been based on a published rate schedule, which is revised annually. The supply manager believes the shipping costs may be higher than necessary. In order to reduce outbound transportation costs, which of the following should the supply manager do FIRST’

Options:

A.

Initiate a carrier cost audit

B.

Explore savings opportunities with the primary carrier

C.

Perform a carrier performance review

D.

Solicit proposals from several other reputable carriers

Buy Now
Questions 36

A firm is looking to expand to a larger warehouse. Which of the following should be given the GREATEST consideration when determining the new warehouse's environmental impact?

Options:

A.

The building's total carbon footprint

B.

The efficiency of the warehouse's air conditioning unit

C.

The cost of replacing single pane windows

D.

The cost of changing light bulbs to LED lights

Buy Now
Questions 37

A manufacturer purchased a piece of production equipment over 20 years ago. The equipment is still in use, though for the last few quarters, it has been getting more difficult to keep it operational, as many of the required components are turning obsolete. According to the service agreement, the supplier must ensure the availability of the component parts for 3 more years. In this situation, the buying firm should expect that the supplier will

Options:

A.

create a list of components expected to become obsolete in the next 3 years, identify new parts to replace the existing ones, and propose the plan to the buyer

B.

explain the situation to the buyer and suggest that it source the required components on its own

C.

propose to revise the remaining timeline of the service agreement from 3 years to 6 months

D.

create a list of components expected to become obsolete within the next 3 years, and purchase the required parts before they are actually needed, in order to support the agreement

Buy Now
Questions 38

A firm hires a new staff member in its warehousing department. As a FIRST step in the training of this employee, the warehouse manager should

Options:

A.

verify that the employee knows how to operate the warehouse equipment and tools correctly

B.

demonstrate how to package products in the correct manner, so that the employee can begin with packaging assignments

C.

explain the company's safety policy and verify that the employee understands all safety-related requirements

D.

show the employee how to separate disposable vs recyclable packaging, to ensure the employee understands environmental compliance requirements

Buy Now
Questions 39

Which of the following refers to the practice of buying a commodity on the open market for immediate delivery?

Options:

A.

Hedging

B.
C.
D.

Answer:

E.

Forward buying

F.

Spot buying

G.

Speculative buying

Buy Now
Questions 40

Which of the following are the quickest ways to ship food products in order to ensure they do not spoil?

Options:

A.

Motor carriage and rail

B.

Water and motor carriage

C.

Air freight and rail

D.

Air freight and motor carriage

Buy Now
Questions 41

A company develops long range material forecasts, analyzes industry trends, determines commodities for value analysis, and assesses supplier capabilities to assure continual economic supply of goods and services. This company is engaged in

Options:

A.

supply chain mapping

B.

market intelligence

C.

early supplier involvement

D.

inventory control

Buy Now
Questions 42

Which of the following is the PRIMARY benefit of project governance?

Options:

A.

Projects considered essential are prioritized over others already in progress.

B.

Business projects need less monitoring, which allows local managers freedom to execute their projects.

C.

Projects that are behind targets may be allowed to continue, if the cause of the delay can be resolved.

D.

Business cases and associated benefits are subject to effective scrutiny, which helps with setting project timelines.

Buy Now
Questions 43

How long after the delivery date must a freight claim on a motor carriage shipment be presented and filed with the carrier in the United States’

Options:

A.

3 months

B.

120 days

C.

30 days

D.

9 months

Buy Now
Questions 44

A manufacturer of gas-powered motors realigns its supply chain to fit a new business segment. In the past, the firm focused on customized designs. Now, it wishes to compete in the electric motor market, which is highly competitive and price-sensitive. Given this situation, which of the following will ensure that the firm has the proper planning in place?

Options:

A.

Negotiating prices with suppliers with a focus on total cost of ownership models, to minimize inventory and logistics costs

B.

Working with engineering to ensure the inclusion of customizable product and service features, in order to meet customer demands

C.

Requiring suppliers to verify that sustainability metrics for various programs are closely monitored

D.

Working with engineering and suppliers to develop new product designs

Buy Now
Questions 45

An organization purchases materials beyond current and anticipated requirements in expectation of a price increase or shortage, in the hope that it will profit from the sale of the materials at a later date. This describes which of the following buying strategies?

Options:

A.

Consignment

B.

Forward

C.

Speculative

D.

Spot

Buy Now
Questions 46

The sourcing manager for a regional retail bakery chain reviews order quantities and stocking for perishable condiments on a quarterly basis. Which of the following factors should be the MOST critical consideration in this analysis?

Options:

A.

Setting reasonable delivery performance metrics for suppliers

B.

Understanding the tradeoff between freight costs and inventory levels

C.

Balancing customer service expectations with risk of stockouts

D.

Maintaining profitability for low margin items

Buy Now
Questions 47

A manufacturer has historically ordered fasteners utilizing monthly fixed order quantities. The firm wishes to explore the feasibility of using economic order quantity (EOQ), and determines that the EOQ is less than the supplier’s quoted price break. Which of the following is the BEST course of action for the firm to take?

Options:

A.

Place orders using the economic order quantity

B.

Negotiate a new contract with the supplier to modify price breaks

C.

Implement a Vendor Managed Inventory program with the supplier to transfer carrying costs

D.

Compare the price break to the carrying cost of buying at the economic order quantity

Buy Now
Questions 48

A company purchases raw materials from a domestic supplier that offers competitive overland transportation rates. The firm requires the goods be delivered to its manufacturing plant. Which of the following Incoterms® 2020 rules should be used if the firm wants risk to transfer at the manufacturing plant?

Options:

A.

CIP

B.

DAP

C.

FCA

D.

FOB

Buy Now
Questions 49

XYZ, Inc. is a manufacturer and distributor of fishing gear. XYZ relies on poorly-executed forecasts from its retail partners, which leads to exaggerated demand. This in turn leads to XYZ experiencing increased inventory, material handling concerns, and difficulties managing its accounts payable. Which of the following BEST describes what is occurring in this situation?

Options:

A.

Bullwhip effect

B.

Speculative buying

C.

Adaptive smoothing

D.

Backflush

Buy Now
Questions 50

A disaster response manager plans to deliver pallets of bottled water to volunteers at a disaster site. The water comes from a nearby bottling company at a preferential cost of $50 per pallet. The number of pallets of bottled water needed is impossible to know in advance due to numerous variables, although experience indicates that the likelihood of consumption is equal: a 25% chance each for 1, 2, 3 or 4 pallets of bottled water. If a full pallet is returned, a restocking fee of 520 is charged. If not enough water is brought in, the cost of purchasing a pallet of water on location is expected to be $200.

How many pallets should the manager deliver?

Options:

A.

3 pallets

B.

1 pallet

C.

2 pallets

D.

4 pallets

Buy Now
Exam Code: INTE
Exam Name: Supply Management Integration
Last Update: Sep 11, 2025
Questions: 167

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99