Questions 4

You want to set up a make-to-order planning scenario for a finished material. The bill of materialcontains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

Options:

A.

Choose planning strategy 50 (Planning without final assembly) and select the — corresponding Individual/Collective indicator.

B.

Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator.

C.

Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator.

D.

Choose planning strategy 20 (Make-to-Order) and select the corresponding ndividual/Collectiveindicator.

Buy Now
Questions 5

How would you define pegging in the context of Advanced Planning?

Options:

A.

An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements

B.

An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements

C.

An evaluation to verify if there are material or capacity shortages in the ^ network after the production planning run

D.

An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run

Buy Now
Questions 6

How can you characterize dependent requirements in material requirements planning?

Note: There are 2 correct answers to this question.

Options:

A.

They are created with exact times in Advanced Planning.

B.

They are created when an independent requirement is created for the finished product.

C.

They are created on assembly level during the planning run.

D.

They are only created for multilevel bill of material (BOM) structures

Buy Now
Questions 7

What are some benefits of planning with planned independent requirements? Note: There are 2 correct answers to this question.

Options:

A.

Reduced production times

B.

Reduced delivery times

C.

Option to use make-to-order production

D.

Option to forecast planning for production resources

Buy Now
Questions 8

For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis. Which of the following do you have to consider?

Note: There are 2 correct answers to this question.

Options:

A.

In pro duct-related COC, all costs are debited and credited to a product cost collector.

B.

Order-related COC is beneficial in a flexible production environment

C.

Product-related COC is used in manufacturing for co-products

D.

In order-related COC, individual production orders do NOT have cost segments.

Buy Now
Questions 9

How can a material availability check be triggered automatically for a production order?

Note: There are 2 correct answers to this question.

Options:

A.

By capacity planning

B.

By mass processing

C.

By order release

D.

By order confirmation

Buy Now
Questions 10

Which time elements can be reduced by a reduction strategy?

Note: There are 3 correct answers to this question.

Options:

A.

Goods receipt processing time

B.

Move time

C.

Wait time

D.

Float after production

E.

Queue time

Buy Now
Questions 11

How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,

Options:

A.

By Plant

B.

By Period

C.

By Industry

D.

By Material Status

Buy Now
Questions 12

in your Plant, MRP is activated.

which options do you have to exclude a material from the MRP run?

Note: there are 2 correct answers to this question.

Options:

A.

Use a specific material status

B.

Use a specific material group

C.

Use a specific MRP type

D.

Use a specific MRP list

Buy Now
Questions 13

You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?

Options:

A.

Manual Planning Without Check

B.

Consumption-Based Planning

C.

Material Requirements Planning

D.

Advanced Planning

Buy Now
Questions 14

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?

Options:

A.

The new operation is inserted at the desired time; the previous dispatched operation is moved forward.

B.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward

C.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

D.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

Buy Now
Questions 15

What is the work center hierarchy in capacity planning?

Options:

A.

A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of alternative work centers for production, structured in hierarchy levels by priorities

Buy Now
Questions 16

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a propagation range.

B.

Use a resource group

C.

Use a planning area.

D.

Use a planning group.

Buy Now
Questions 17

Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.

Options:

A.

Routing

B.

Work Center

C.

Bill of material (BOM)

D.

Material Master

Buy Now
Questions 18

What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

Options:

A.

Order type

B.

Planning strategy

C.

Requirements profile

D.

Requirements type

Buy Now
Questions 19

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

Options:

A.

Move Time

B.

Pick/pack time

C.

Setup time

D.

Float before production

E.

Queue time

Buy Now
Questions 20

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

Options:

A.

Planning with final assembly (40)

B.

Production by lot size (30)

C.

Planning at assembly level (70)

D.

Make-to-order production (20)

Buy Now
Questions 21

You Have a scheduling agreement with a vendor, you want classic MRP to automatically create

schedule lines in case of material shortage, what must you do?

Note: there are 2 correct answers to this question.

Options:

A.

Add the agreement to the source list and mark it for MRP relevance.

B.

Set the creation indicator for purchase requisition on the initial screen of the MRP run.

C.

Add the agreement to the quota arrangement and mark it for MRP relevance.

D.

Set the creation indicator for delivery schedule lines on the initial screen the MRP run.

Buy Now
Questions 22

Which business processes are affected by settings in the order-type-dependent parameters?

Note: There are 2 correct answers to this question.

Options:

A.

Check material availability.

B.

Schedule production orders.

C.

Define integration with cost accounting.

D.

Select master data.

Buy Now
Questions 23

which SAP application can be used for forecasting in Supply Chain Planning?

Note: there are 2 correct answers to this question.

Options:

A.

Integration Business Planning (IBP)

B.

Capacity Requirement Planning (CRP)

C.

Supply Chain Management (SCM)

D.

Material Requirement Planning (MRP)

Buy Now
Questions 24

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.

Note: there are 2 correct answers to this question.

Options:

A.

Manual maintenance

B.

100% check

C.

First in First out (FIFO).

D.

Simultaneous

Buy Now
Exam Code: C_TS422_2022
Exam Name: SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing