Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

PSP Planning & Scheduling Professional (PSP) Exam Questions and Answers

Questions 4

The Scope of Work divides the major deliverables into smaller more manageable components for all of the following EXCEPT to:

Options:

A.

improve the accuracy of cost, time, and resource estimates

B.

facilitate clear responsibility assignments

C.

define a baseline for performance measurement and control

D.

establish the Performance Measurement Baseline values

Buy Now
Questions 5

If all other work proceeds according to the Baseline plan, how many times will the critical path change?

PSP Question 5

Options:

A.

2.

B.

1.

C.

Does not change.

D.

3.

Buy Now
Questions 6

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

Options:

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Buy Now
Questions 7

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Buy Now
Questions 8

Who will receive the most benefit from a master schedule of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE. Inc

C.

BILCO

D.

SDOT

Buy Now
Questions 9

Each of the following accurately describes total float in a schedule EXCEPT:

Options:

A.

The amount of time an activity can be delayed without delaying the overall project completion time.

B.

Can be positive or negative.

C.

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.

D.

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Buy Now
Questions 10

Time-scaled logic diagrams are

Options:

A.

Only calculated using a computer.

B.

The same as a pure-logic diagram.

C.

Used to calculate the most probable activity duration.

D.

Logic networks that are drawn to match the calendar.

Buy Now
Questions 11

Value engineering is:

Options:

A.

targeted at the design itself

B.

intended to provide the least life-cycle cost

C.

established to provide the greatest value

D.

intended to determine if the project will be completed economically

Buy Now
Questions 12

What is the relationship depicted between Activity G and Activity H?

PSP Question 12

Options:

A.

You cannot tell with the supplied information.

B.

Start-to-start.

C.

Finish-to-start.

D.

Finish-to-finish.

Buy Now
Questions 13

The primary determination of schedule detail is:

Options:

A.

The frequency of update periods

B.

The contract specifications

C.

The staffing of planners and schedulers

D.

The number of subcontractors working on a work package

Buy Now
Questions 14

During the Bid Phase, do the planning and scheduling project documents impact the Bid pricing?

Options:

A.

The bid does not reflect details of planning and scheduling

B.

The bid should reflect the level of planning and scheduling noted on similar projects with this client

C.

The bid should reflect the project plan incorporating all planning and scheduling elements

D.

The bid should incorporate input from the manager responsible for planning and scheduling if the bid is successful

Buy Now
Questions 15

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

PSP Question 15

Options:

A.

$195 per day

B.

S1.772 per day

C.

General conditions do not need to be reduced to break even

D.

$1.223 per day

Buy Now
Questions 16

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

Options:

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days

Buy Now
Questions 17

What day would Activity C complete if the duration of Activity A was reduced by five days?

Options:

A.

35

B.

30

C.

45

D.

40

Buy Now
Questions 18

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

Options:

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Buy Now
Questions 19

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor's baseline schedule submittal includes a bar chart, but no CPM diagram. Which of the following is the most significant shortcoming to using a bar chart to review the baseline?

Options:

A.

A bar chart cannot accurately reflect the impact of changes in durations or logic to the baseline

B.

A bar chart is always an oversimplified view of the project schedule

C.

A tor chart does not show all the activities required to construct the project

D.

A bar chart does not show whether the project with be completed within the allowable time

Buy Now
Questions 20

Project Life Cycle Phases do NOT include the following item:

Options:

A.

procurement

B.

budgeting

C.

design

D.

start-up

Buy Now
Questions 21

Who can define KPls?

Options:

A.

The client and the performing/contracting entity

B.

Environmental regulators

C.

The subcontractors and suppliers

D.

Accounting and Finance

Buy Now
Questions 22

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Options:

A.

ahead of schedule

B.

on schedule

C.

complete

D.

behind schedule

Buy Now
Questions 23

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

PSP Question 23

Options:

A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Buy Now
Questions 24

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

PSP Question 24

Options:

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

Buy Now
Questions 25

The BEST reason to use multiple calendars is to:

Options:

A.

more accurately show how the project will be built

B.

allow each specialty contractor to have a unique schedule of work/non-work periods

C.

track owner activities according to their specific calendar in order to develop a good

working relationship

D.

evaluate float for the benefit of the contractor

Buy Now
Questions 26

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

PSP Question 26

Options:

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

Buy Now
Questions 27

The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

Options:

A.

Estimate at completion (EAC)

B.

Budget at completion (BAC)

C.

Budgeted cost of work performed (BCWP)

D.

Budgeted cost of work scheduled (BCWS)

Buy Now
Questions 28

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

Options:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

Buy Now
Questions 29

Which of the following project planning situations is the most frequent contributor to cost overruns?

Options:

A.

lack of detailed planning for operational start-up

B.

Insufficient planning for change management

C.

Inappropriate definition of work breakdown structure

D.

Inadequate definition of scope at the estimate (budget) stage

Buy Now
Questions 30

What activities are concurrent to Activity 2001 in the "normal" schedule?

PSP Question 30

Options:

A.

7001.

B.

1001.

C.

1000.

D.

2003.

Buy Now
Questions 31

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:

A.

Not suitable for complicated projects with multiple planned critical paths.

B.

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.

Not suitable for projects with long durations.

D.

Less accurate as the analysis advances through the project.

Buy Now
Questions 32

The Work Breakdown Structure (WBS) is established to reflect the:

Options:

A.

lowest level of the project estimate

B.

lowest level reporting back to the program WBS

C.

lowest level of effort scope

D.

lowest level where the work is managed

Buy Now
Questions 33

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

Options:

A.

Delay due to SDOT's other projects

B.

Delay due to labor shortage

C.

Liquidated damages on the SDOT contract

D.

Cost overruns due to cement shortage

Buy Now
Questions 34

Determine the correct formula and date for the late finish for Activity 9004.

PSP Question 34

Options:

A.

LS.10002 + 1 day -> 11-29-03.

B.

LS.10002^ Lag.7 + i day -> 11-20-03.

C.

LS.10002 - 1 day -> 11-27-03.

D.

LS.10002 - Lag.7 - l day -> 11-20-03.

Buy Now
Questions 35

How many entities/subcontractors should a scheduled activity cover?

Options:

A.

More than one it the activity is in a single calendar period

B.

More than one it the subcontractors agree

C.

Only one

D.

More than one if the concurrent work cannot be split between subcontractors

Buy Now
Questions 36

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

PSP Question 36

Options:

A.

450 lifts

B.

300 lifts

C.

45 lifts

D.

150 lifts

Buy Now
Questions 37

Baseline schedule can be submitted only__________.

Options:

A.

at the beginning or the construction

B.

once the project gets impacted try change

C.

once the design for the construction gets approved

D.

once the safety quality and insurance requirements are met

Buy Now
Questions 38

Which of the following is NOT required when initially planning a project?

Options:

A.

Resource Identification and leveling.

B.

The duration of each task.

C.

A schedule that identifies tasks required on a project.

D.

Logical relationships between the tasks.

Buy Now
Questions 39

Using the normal schedule, what is the early finish date and total float of Activity 10002?

Options:

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Buy Now
Questions 40

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

PSP Question 40

Options:

A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

C.

The activities occur in series with a 15-day lag.

D.

The activities run concurrently.

Buy Now
Questions 41

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Question 41

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

PSP Question 41

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Buy Now
Questions 42

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

Options:

A.

Is a milestone.

B.

It is on the critical path.

C.

Was completed in the past.

D.

Has yet to be completed.

Buy Now
Questions 43

Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

Options:

A.

Consideration of all stakeholders.

B.

Value engineering.

C.

Project variables.

D.

Interest rate of owner's construction bonds.

Buy Now
Questions 44

The work breakdown structure is used to organize

Options:

A.

"Smart activity ID codes" representing similar items of scheduled work

B.

The chart of accounts

C.

Similar activity coding of schedule activities

D.

The smallest defined work packet

Buy Now
Questions 45

By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

Options:

A.

Acceleration.

B.

Production output.

C.

Productivity loss.

D.

Productivity efficiency.

Buy Now
Questions 46

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

Options:

A.

$289.000

B.

$321.000

C.

$193,000

D.

$327,000

Buy Now
Questions 47

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

Options:

A.

Non-excusable delay

B.

Compensable delay

C.

Non-compensable delay

D.

Excusable delay

Buy Now
Questions 48

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?

Options:

A.

Additional extended overhead is also being shown in this activity

B.

Some costs resulting from the crashed efforts were forgotten in previous activities

C.

Generally, more equipment is used for a crashed project; therefore, it costs more to demobilize

D.

Management bonuses for early completion were included in this activity

Buy Now
Questions 49

What was the original planned duration for Activity A through Activity G?

PSP Question 49

Options:

A.

26.

B.

28.

C.

24.

D.

25.

Buy Now
Questions 50

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

Options:

A.

Budgeted cost of work scheduled

B.

Budgeted cost of work performed

C.

Schedule performance index

D.

Actual cost of work scheduled

Buy Now
Questions 51

Which of the following parties is NOT a stakeholder of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

Buy Now
Questions 52

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

Options:

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.

Replace the relationship from 'B’ to 'C’ with SSO

C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort

Buy Now
Questions 53

When project risk is reflected in scheduled activities, what is the most significant characteristic of those activities?

Options:

A.

The level of resources available to the activity

B.

The Remaining Duration of the activity

C.

The criticality of toe activities

D.

The Late Start of the last activity in that float path

Buy Now
Questions 54

At the end of month one, did the delay to the parking structure foundation delay the project?

Options:

A.

NO.

B.

Yes, by 4 calendar days.

C.

Yes, by 14 calendar days.

D.

Yes, by 9 calendar days.

Buy Now
Questions 55

The data date or status date of a schedule represents the:

Options:

A.

date the monthly update is performed

B.

date the project manager turns in the schedule update

C.

system date when the software calculates the update

D.

date on which progress is based

Buy Now
Questions 56

Control Level Schedule activities are NOT one of the following:

Options:

A.

always analogous with Control Accounts

B.

always used to establish the scope and track the status of automation control systems

C.

may be composed form multiple WBS deliverable packages

D.

always reporting the status of phase deliverables

Buy Now
Questions 57

How could the structural steel drawing delay have been prevented?

Options:

A.

Add a time buffer at the end of structural steel activities.

B.

Allow adequate time for review and resubmittal in the baseline schedule.

C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.

Switch to post-tensioned concrete construction.

Buy Now
Questions 58

The EBS is established by:

Options:

A.

The contractor s planning and scheduling office

B.

The government entity with the authority to approve/stop the work

C.

The entity with the authority to fund and direct the enterprise

D.

The contractors and subcontractors

Buy Now
Questions 59

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

Options:

A.

Using the critical chain method

B.

Fast tracking

C.

Crashing

D.

Rebaseline the project

Buy Now
Questions 60

SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?

Options:

A.

SUBCO direct labor and equipment rates

B.

BILCO liquidated damages in the SDOT contract

C.

Pending negotiations with GOUGE.

D.

The distance of SUBCO to your project

Buy Now
Questions 61

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS of 2003 less 1 day equaling to 06 Oct 2021

B.

LS of 2003 less 1 day equaling to 06 Nov 2021

C.

LS of 2003 plus 1 day equaling to 07 Oct 2021

D.

LS of 2003 less 1 day equaling to 05 Oct 2021

Buy Now
Questions 62

What does the heavy, vertical line at "X" represent?

PSP Question 62

Options:

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Buy Now
Questions 63

Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?

Options:

A.

30 lifts

B.

133 lifts

C.

42 lifts

D.

60 lifts

Buy Now
Questions 64

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

Options:

A.

Industry publications.

B.

Critical path schedules prepared by you for similar completed projects.

C.

The Petrochemical Industry New Plant Task Duration Handbook.

D.

The cost estimate for the plant prepared by your firm's estimating department.

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Oct 15, 2025
Questions: 216

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99