A Scrum Team is required to deliver a Done Increment by the end of a Sprint. Select two statements that explain what Done means. (choose the best two answers)
Based on "Sprint 7 Burn-Down Chart," would you do anything different in Sprint 8? (choose the best two answers)
Which best describes the practice of expressing requirements as acceptance tests?
If multiple teams are working on the same product, each team should have its own product owner
The CEO demands a feature from the developers during the sprint. What should the developers do?
The goal of the daily scrum is inspecting the progress toward the sprint goal and producing an actionable plan for the next day of work
True or False: Product documentation may be required as part of a working Increment.
While developing a new feature, you find a bug delivered in a previous Increment. What should you do? (choose the best answer)
Which concept is described by the Last Responsible Moment? (choose the best answer)
Database design must be complete before coding starts to ensure a solid foundation
True or False: A high-performance Scrum Team ensures that each Increment is complete by running a Release Sprint.
Is it a good idea to follow each automated build with the execution of automated tests?
What should the Scrum Team do during the first Sprint? (choose the best answer)
Developers are blocked by an impediment in the middle of the Sprint. The impediment is outside the Developer’s control. What should they do? (choose the best answer)
Several scrum teams share the scrum master. Developers of multiple teams approach the scrum master, because they need fulltime commitment from the same technical specialist for the next sprint. What should the scrum master consider for the response to this problem? Choose the two best answers.
How do you know that a Scrum Team is cross-functional? (choose the best answer)