Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

PSPO-I Professional Scrum Product Owner (PSPO I) Exam Questions and Answers

Questions 4

Why do the Developers need a Sprint Goal?

(choose the best answer)

Options:

A.

A Sprint Goal only gives purpose to Sprint O.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

The Developers are more focused with a common yet specific goal.

D.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

Buy Now
Questions 5

A Sprint Retrospective should be held:

(choose the best answer)

Options:

A.

Only when the Scrum Team determines it needs one.

B.

At the end of the last Sprint in a project or a release.

C.

At the end of each Sprint.

D.

At the beginning of each Sprint.

Buy Now
Questions 6

Which are appropriate topics for discussion in a Sprint Retrospective?

(choose the best three answers)

Options:

A.

Team relations.

B.

The value of work currently represented in the Product Backlog.

C.

How the Scrum Team does its work.

D.

Definition of Done.

E.

Arranging the Sprint Backlog for the next Sprint.

Buy Now
Questions 7

Who has the final decision about the order of items in the Product Backlog?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The Stakeholders.

C.

The Scrum Team.

D.

The Developers.

E.

The Product Owner.

Buy Now
Questions 8

What is the responsibility of the Product Owner in crafting the Sprint Goal?

(choose the best answer)

Options:

A.

The Product Owner has no responsibility for the Sprint Goal. It is the soleresponsibility of the Developers.

B.

The Product Owner cannot attend Sprint Planning without having documented theSprint Goal in advance.

C.

The Product Owner should come to Sprint Planning with a business objective in mind and work with the Developers to craft the Sprint Goal.

D.

The Product Owner must work with stakeholders to set each Sprint ' s Goal.

E.

The Product Owner defines the scope for a Sprint and therefore also the Sprint Goal.

Buy Now
Questions 9

Which best describes the Product Backlog?

(choose the best answer)

Options:

A.

It is allowed to grow and change as more is learned about the product and itscustomers.

B.

It contains all foreseeable tasks and requirements from which the Scrum Team candevelop and maintain a complete project plan.

C.

It provides just enough information to enable a Scrum Team to start the design phaseof a product.

D.

It is baselined to follow change management processes.

Buy Now
Questions 10

Scrum is based on empiricism. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. How can the Scrum Team maintain the Product Backlog to maximize its transparency?

(choose the best answer)

Options:

A.

The Product Backlog is only updated at the Sprint Review, when both the ScrumTeam and the stakeholders are available.

B.

Product Backlog items should hold no more than 8 points of work, which is theaverage in the range of acceptable sizes of 1, 2, 3, 5, 8, and 13.

C.

Product Backlog items must be sized such that the highest ordered items are no bigger than a Sprint.

D.

The Product Backlog is only updated at a release planning meeting with thestakeholders and the change control board present.

E.

The Product Backlog is continually kept up to date with the most recent insights.

Buy Now
Questions 11

What happens if the Scrum Team cannot complete its work by the end of the Sprint?

(choose the best answer)

Options:

A.

The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

B.

The Sprint is extended and future Sprints use this new duration.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it does not happenagain.

Buy Now
Questions 12

True or False: The Product Owner must write all of the Product Backlog items (e.g., user stories, requirements, etc.) on the Product Backlog before handing them over to the Scrum Team.

Options:

A.

True

B.

False

Buy Now
Questions 13

True or False: Product Owners must create clear and unambiguous acceptance criteria for each Product Backlog item before it may be selected in Sprint Planning.

Options:

A.

True

B.

False

Buy Now
Questions 14

Developers are self-managing, which of the following do they manage?

(choose the best answer)

Options:

A.

Product Backlog ordering.

B.

When to release, based on its progress.

C.

Sprint Backlog.

D.

Stakeholders for the Sprint Review.

E.

Sprint length.

Buy Now
Questions 15

A Product Owner is accountable for maximizing the value of the product that is the result of the work of the Scrum Team. Which of the following can be delegated to others, while the Product Owner remains accountable for the work?

(choose the best two answers)

Options:

A.

Attending the Sprint Retrospective.

B.

Attending the Sprint Review.

C.

Ordering Product Backlog items.

D.

Developing and communicating the Product Goal.

Buy Now
Questions 16

Which of the following is required by Scrum?

(choose the best answer)

Options:

A.

Sprint Retrospective.

B.

Developers must stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release Planning.

E.

All of the above.

Buy Now
Questions 17

What is the timebox for the Sprint Review?

(choose the best answer)

Options:

A.

2 hours for a one-month Sprint.

B.

1 day.

C.

4 hours for a one-month Sprint.

D.

As long as needed.

Buy Now
Questions 18

How much of the Sprint Backlog must be defined during the Sprint Planning event?

(choose the best answer)

Options:

A.

Just enough to understand design and architectural implications.

B.

Enough so the Developers can create their forecast of what work they can do.

C.

The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.

D.

Just enough tasks for the Scrum Master to be confident in the Developers ' understanding of the Sprint.

Buy Now
Questions 19

When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?

(choose the best answer)

Options:

A.

Whenever a team member can accommodate more work.

B.

At the Sprint Planning Event.

C.

During the Daily Scrum.

D.

Never. The entire Scrum Team is accountable for creating value every Sprint.

Buy Now
Questions 20

How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?

(choose the best answer)

Options:

A.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint.

B.

As much as is required to meet the Scrum Team ' s Definition of Done.

C.

All development work and at least some testing.

D.

A proportional amount of time on analysis, design, development, and testing.

Buy Now
Questions 21

Which two ways of creating Scrum Teams are consistent with Scrum ' s values?

(choose the best two answers)

Options:

A.

Managers personally re-assign current subordinates to new teams.

B.

The Chief Product Owner determines the new team structures and assignments.

C.

Managers collaborate to assign individuals to specific teams.

D.

Existing teams propose how they would like to go about organizing into the newstructure.

E.

Bring all the people together and let them organize into Scrum Teams.

Buy Now
Questions 22

When should the Product Owner update the project plan?

(choose the best answer)

Options:

A.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

B.

The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.

C.

After the Daily Scrum to ensure an accurate daily overview of project progress.

D.

The project plan must be updated prior to the Sprint Retrospective.

Buy Now
Questions 23

What might indicate to a Product Owner that she needs to work more with the Scrum Team?

(choose the best answer)

Options:

A.

The acceptance criteria do not appear to be complete.

B.

She is not working full time with the Scrum team.

C.

People leave the Scrum Team.

D.

The Increment presented at the Sprint Review does not reflect what she thought she had asked for.

Buy Now
Questions 24

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder

just started using the product. The stakeholder is unhappy with the quality of the product. What

are two good options for the Scrum Master?

(choose the best two answers)

Options:

A.

Coach the Product Owner on how to talk with the Developers about thisconcern.

B.

Wait to bring this up until the Sprint Retrospective.

C.

Explain to the Product Owner that it is up to the Developers to decide onacceptable quality standards.

D.

Encourage the Product Owner to put quality specifications on the ProductBacklog and express the stakeholder ' s concern to the Developers.

E.

Bring the concern to the testers to improve how the Product is verified.

Buy Now
Questions 25

What should the Scrum Team do during the first Sprint?

(Choose the best answer)

Options:

A.

Make up a plan for the rest of the project.

B.

Define the major product features and a release plan architecture.

C.

Create at least one valuable and useful Increment.

D.

Analyze, describe, and document the requirements for the subsequent Sprints.

Buy Now
Questions 26

True or False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.

Options:

A.

True

B.

False

Buy Now
Questions 27

True or False: Scrum has a role called " Project Manager " .

Options:

A.

True

B.

False

Buy Now
Questions 28

When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected?

(Choose the best answer)

Options:

A.

The Product Owner and all stakeholders.

B.

The Scrum Master and the Developers.

C.

The Scrum Master, project manager and the Developers.

D.

The Product Owner and the Developers.

Buy Now
Questions 29

A Scrum Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what done means.

(choose the best two answers)

Options:

A.

No work is left to meet the Definition of Done.

B.

Whatever the Product Owner defines as quality.

C.

Ready for integration.

D.

Ready to be released to end users.

E.

All work the Developers are willing to do.

Buy Now
Questions 30

When multiple Scrum Teams are working on a single product, what best describes the

Definition of Done?

(choose the best answer)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed andreconciled during a hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all otherteams so the differences are known.

D.

When multiple Scrum Teams are working together on a product, they must mutuallydefine and comply with the same Definition of Done.

Buy Now
Questions 31

True or False: All planned work for the Product done by the Scrum Team must originate from the Product Backlog.

Options:

A.

True

B.

False

Buy Now
Questions 32

Who determines how many Product Backlog items the Developers select for a Sprint?

(choose the best answer)

Options:

A.

The Scrum Team

B.

The Developers.

C.

The Product Owner.

D.

The Scrum Master.

E.

The stakeholders attending Sprint Planning.

Buy Now
Questions 33

When Developers are having trouble delivering an Increment because they do not understand a

functional requirement, what should they do?

(choose the best answer)

Options:

A.

Partially complete the functionality, and discuss the remaining work at the SprintReview.

B.

Add a specialist to the Development Team.

C.

Collaborate with the Product Owner to determine what is possible and acceptable.

D.

Defer the work to a more appropriate Sprint.

Buy Now
Questions 34

Which topics should be discussed in the Sprint Review?

(choose the best answer)

Options:

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

The product Increment.

D.

All of the above.

Buy Now
Questions 35

True or False: During the Sprint Review the stakeholder ' s role is to reorder the Product Backlog.

Options:

A.

True

B.

False

Buy Now
Questions 36

Which of these may a Scrum Team deliver at the end of a Sprint?

(choose the best answer)

Options:

A.

Failing unit tests, to identify acceptance tests for the next Sprint.

B.

A single document, if that is what management asked for.

C.

An Increment of software with minor known bugs in it.

D.

A valuable, useful Increment that meets the Definition of Done.

Buy Now
Questions 37

The Product Owner is the person who will be held accountable if a product does not achieve its goals or deliver value. Does this mean that the Product Owner has the final say over the Definition of Done?

(choose the best answer)

Options:

A.

Yes, the Product Owner decides the Definition of Done. The Developers may beconsulted.

B.

No, the Scrum Team decides the Definition of Done, if it is not a standard of the organization. The Product Owner is just one member of the Scrum Team.

Buy Now
Questions 38

At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the

Definition of Done. What two things should happen with the undone Product Backlog item?

(choose the best two answers)

Options:

A.

Review the item, add the done part of the estimate to the velocity and create aStory for the remaining work.

B.

If the stakeholders agree, the Product Owner can accept it and release it to theusers.

C.

Do not include the item in the Increment this Sprint.

D.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

Buy Now
Questions 39

Which statement best describes Scrum?

(choose the best answer)

Options:

A.

A defined and predictive process that conforms to the principles of Scientific Management.

B.

A complete methodology that defines how to develop software.

C.

A framework to generate value through adaptive solutions for complex problems.

D.

A cookbook that defines best practices for software development.

Buy Now
Questions 40

True or False: A Product Owner should measure product value by the increase in the team ' s velocity.

Options:

A.

True

B.

False

Buy Now
Questions 41

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

(choose the best answer)

Options:

A.

The Project Manager.

B.

The Scrum Team.

C.

The Developers.

D.

The Product Owner.

Buy Now
Questions 42

What is the timebox for the Sprint Planning event?

(choose the best answer)

Options:

A.

Monthly.

B.

Whenever it is done.

C.

8 hours for a one-month Sprint.

D.

4 hours for a one-month Sprint.

Buy Now
Questions 43

What are the two responsibilities of testers in a Scrum Team?

(choose the best two answers)

Options:

A.

Tracking quality metrics.

B.

Scrum has no " tester " role.

C.

Verifying the work of programmers.

D.

The Developers are responsible for quality.

E.

Finding bugs.

Buy Now
Questions 44

Who creates the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Master

B.

The Scrum Team

C.

The Product Owner

D.

The Developers

Buy Now
Questions 45

True or False: An Increment must be released to customers or users at the end of each Sprint.

Options:

A.

True

B.

False

Buy Now
Questions 46

The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should:

(choose the best answer)

Options:

A.

Tell the Developers to fit the report into the Sprint Backlog.

B.

Ask the Product Owner to send the manager the report.

C.

Create and deliver the report to the manager herself.

D.

Tell the Scrum Team to figure it out themselves.

E.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

Buy Now
Questions 47

How much time must a Product Owner spend with the Developers?

(choose the best answer)

Options:

A.

Enough so that the Product Owner is confident the Increment will meet the intended value.

B.

40%, or more if the stakeholders agree.

C.

As much time as the Developers tell the Product Owner to be present.

D.

100%

Buy Now
Questions 48

A Scrum Team is a cohesive unit of professionals that consists of which of the following?

(choose the best three answers)

Options:

A.

One Product Owner.

B.

Developers.

C.

Customers.

D.

One Scrum Master.

E.

Users.

Buy Now
Questions 49

What are two effective ways for a Scrum Team to ensure security concerns are satisfied? (choose the best two answers)

Options:

A.

Add security concerns to the Definition of Done.

B.

Delegate the work to the security department.

C.

Have the Scrum Team create Product Backlog items for each concern.

D.

Add a Sprint to specifically resolve all security concerns.

E.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

Buy Now
Questions 50

Which statement best describes the Sprint Backlog as the output of the Sprint Planning?

(choose the best answer)

Options:

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Developers plan for the Sprint.

E.

It is ordered by the Product Owner.

Buy Now
Questions 51

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

Options:

A.

The Product Owner with input from the Developers.

B.

The Scrum Master.

C.

The Developers, alone.

D.

The Developers after clarifying requirements with the Product Owner.

E.

The most senior people in the organization, including architects and subject matterexperts.

Buy Now
Exam Code: PSPO-I
Exam Name: Professional Scrum Product Owner (PSPO I) Exam
Last Update: Apr 15, 2026
Questions: 173

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99