PRINCE2-7-Practitioner PRINCE2 Project Management Practitioner (Version 7) Questions and Answers
The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.
Is this an appropriate approach to leading a successful team, and why?
During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.
Which role is accountable for selecting the project approach?
During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick’s later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.
Which practice is being applied through the ‘controlling a stage’ process?
During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.
Is this an appropriate application of the ‘manage by exception’ principle, and why?
During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.
During which closing activity should this be done?
During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.
Is this an appropriate application of the progress practice, and why?
A product description contains only the following quality specification for the car-parking component: “The shopping centre will include an underground car park.”
Is this an effective application of the quality practice, and why?
While preparing the risk management approach, the project manager holds a workshop to review the project context: the historic surroundings, sustainability targets and the need to minimize disruption to residents and businesses.
Is this an appropriate application of the risk practice, and why?
The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.
Does this represent an appropriate application of the ‘business case’ practice, and why?
Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.
During which ‘managing product delivery’ activity should this be done?
Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.
Is this an appropriate application of the issues practice, and why?
Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.
Which role agrees to carry out the work package in the ‘managing product delivery’ process?
During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.
Is this an appropriate application of the ‘learn from experience’ principle, and why?