PRINCE2-7-Practitioner PRINCE2 Project Management Practitioner (Version 7) Questions and Answers

Questions 4

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

Buy Now
Questions 5

During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.

Which role is accountable for selecting the project approach?

Options:

A.

Business layer

B.

Project executive

C.

Project manager

D.

Senior supplier

Buy Now
Questions 6

During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick’s later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.

Which practice is being applied through the ‘controlling a stage’ process?

Options:

A.

Business case

B.

Organization

C.

Plans

D.

Quality

Buy Now
Questions 7

During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.

Is this an appropriate application of the ‘manage by exception’ principle, and why?

Options:

A.

Yes, because establishing a minimum and a preferred number of charging bays creates a defined scope tolerance that enables the design team to work within an agreed range without needing to escalate every individual design decision

B.

Yes, because specifying a minimum and a preferred number of charging bays constitutes a quality tolerance that the design team must meet within the agreed work package

C.

No, because the precise number of electric charging bays to be included should be fully specified in the product description for the underground car park rather than treated as a tolerance

D.

No, because the project board should approve the precise number of charging spaces rather than delegate a permissible range to the design team

Buy Now
Questions 8

During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.

During which closing activity should this be done?

Options:

A.

Prepare planned closure

B.

Confirm project acceptance

C.

Evaluate the project

D.

Request project closure

Buy Now
Questions 9

During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.

Is this an appropriate application of the progress practice, and why?

Options:

A.

Yes, because an issue report is sufficient whenever a sustainability target is forecast to be missed

B.

Yes, because the forecast shortfall should be treated only as an off-specification in the issue report

C.

No, because the forecast breach should be escalated to the portfolio office rather than the project board

D.

No, because it is an exception which should be escalated in an exception report

Buy Now
Questions 10

A product description contains only the following quality specification for the car-parking component: “The shopping centre will include an underground car park.”

Is this an effective application of the quality practice, and why?

Options:

A.

Yes, because confirming that a car park exists completely specifies its required quality

B.

Yes, because the statement provides sufficient information to confirm whether the required component has been delivered

C.

No, because all details of the car park should be recorded only in the quality management approach

D.

No, because the product description needs sufficiently detailed, measurable quality specifications and tolerances to support planning and verification

Buy Now
Questions 11

While preparing the risk management approach, the project manager holds a workshop to review the project context: the historic surroundings, sustainability targets and the need to minimize disruption to residents and businesses.

Is this an appropriate application of the risk practice, and why?

Options:

A.

Yes, because the contextual statement is itself a complete set of cause-event-effect risk descriptions

B.

Yes, because understanding the project’s context and objectives is necessary to design a risk management approach

C.

No, because risk responses must be selected before the risk management approach can be fully prepared

D.

No, because project objectives should not influence how risk is managed

Buy Now
Questions 12

The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.

Does this represent an appropriate application of the ‘business case’ practice, and why?

Options:

A.

Yes, because developing the business case from multiple perspectives – strategic, economic, and commercial – ensures a comprehensive and robust justification for the project investment

B.

Yes, because the project should align its approach to business case development with the City Council’s established procedure, which serves as the equivalent of PRINCE2’s recommended business case lifecycle

C.

No, because the full business case should be developed from an outline business case prepared during the ‘starting up a project’ process, and using a ‘strategic business case’ instead is not compliant with the method

D.

No, because responsibility for developing the full business case for each project in the portfolio lies with the portfolio office, not the project team

Buy Now
Questions 13

Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.

During which ‘managing product delivery’ activity should this be done?

Options:

A.

Notify work package completion

B.

Execute a work package

C.

Evaluate a work package

D.

Accept a work package

Buy Now
Questions 14

Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because a mature organizational approach should always be used without alteration

B.

Yes, because portfolio funding gives the portfolio office authority to prohibit all project-level tailoring

C.

No, because the project manager should consider the nature of the products, delivery method and project context when preparing the issue management approach

D.

No, because product version control must be decided outside the issue management approach by the delivery teams alone

Buy Now
Questions 15

Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.

Which role agrees to carry out the work package in the ‘managing product delivery’ process?

Options:

A.

Project manager

B.

Team manager

C.

Senior supplier

D.

Project support

Buy Now
Questions 16

During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.

Is this an appropriate application of the ‘learn from experience’ principle, and why?

Options:

A.

Yes, because the regular knowledge-sharing sessions provide a structured mechanism for team managers to identify and apply lessons arising during the current stage

B.

Yes, because the subcontractors are expected to contribute lessons from previous construction projects that are directly relevant to the current stage

C.

No, because subcontractors should concentrate on meeting their work package commitments and tolerances rather than attending sessions that take them away from delivery

D.

No, because the Regeneration Manager should gather lessons through individual interviews with team managers and document them formally in a lessons report at the end of the stage

Buy Now
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Nov 11, 2026
Questions: 56

PDF + Testing Engine

$139.99

Testing Engine

$104.99

PDF (Q&A)

$89.99