PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers
A risk manager schedules workshops for identifying risks about an initiative involving multiple business units, recruitments for different roles, procurements, technological uplift, training, and changes in the ways of working. Who should participate in the risk management activity?
A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project ' s timeline. The project team is struggling to finalize the project ' s budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project ' s final cost. The project team will not be able to finalize the project ' s timeline until the budget is finalized.
What should the risk manager do?
At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.
How should the risk manager respond to this comment?
An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.
How should the risk manager address this concern?
There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.
What should the risk manager do to resolve this recurring situation?
A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.
What type of risk response is this?
The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?
Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager ' s company.
How should the project manager address this concern?
At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization ' s business functions are not properly identified and categorized, making it difficult to develop an effective risk response.
How should the project manager handle this situation?
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.
What should the risk manager do to resolve the sponsor and project team members ' concerns about risk identification?
Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.
What should the risk manager do?
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.
What should the risk manager do to address the new risk of increased logistics costs?
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.
What should the project manager do first?
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?
During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?
A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.
What should the risk manager do?
During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.
How should the risk manager address this concern?
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.
Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).
A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.
What type of risk is being referred to here?
A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?
A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request. What should the risk manager do first?
During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.
What should the risk manager do?
A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.
What should the risk manager do?
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from happening?
A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project ' s key stakeholders.
What is the first resource the project manager should reference?
A project manager wants to introduce a new technology to improve a project ' s performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.
What should the project manager do in this situation?
An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B.
Which action should the risk manager for Project A take?
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor, who is the IT manager, has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings.
What should the IT manager ' s role be in the project team meetings?
Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.
What should the risk manager do to avoid the previous issues?
An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.
What should the risk management expert recommend the agency do first to identify risks and develop the handbook?
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?
The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?
A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.
Which response should the risk manager recommend for these risk items?
A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.
How should the risk manager respond?
A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time
What should the risk manager do in this situation?
The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)
A project manager is assigned to a new project and is told they need to develop the project ' s risk register. When should the project manager identify the project risks?
A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.
Which analytical tool should the risk manager use?
A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.
What should the risk manager have done to prevent missing the milestone?
A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?
A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team ' s tasks have yet to be completed.
What should the risk manager do next?
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?
What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?
A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.
What should the risk manager do next?
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?
Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project ' s budget.
What should the project manager do next?
A project manager has requested the risk manager ' s support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.
What should the risk manager recommend?
An international telecommunications company is preparing to launch a new service across multiple regions. The project team is concerned about the varied technical issues and regulatory challenges in each region. The risk manager is tasked with identifying and analyzing risks to prioritize them based on their potential impact.
Which two actions should the risk manager take? Choose two.
An agile project manager has noticed their team ' s declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?
The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.
What should the risk manager do?
A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.
What should the risk manager do next?
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?
A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.
Which analysis should the risk manager do to provide the project manager with the performance report?
During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.
What should the risk manager do to educate stakeholders?
A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?
As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.
What additional information should the risk manager prioritize in the risk register updates?
When selecting strategies as an activity of Plan Risk Response, what is the overall goal?
During project development, a risk manager notices that a major update in the country ' s regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.
Which tool should the project team use to determine this?
A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.
Which risk identification approach should the risk manager use to achieve this goal?
A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.
What should the risk manager advise the project manager to do to address this situation?
.
A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board ' s response?
After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?
The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.
What should the risk manager do?
A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company ' s business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.
What should the project manager do next?
A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.
What should the project manager have done differently?
A major data center initiative involves performing a sensitivity analysis to determine the center ' s required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor ' s advertised plans.
What should the risk manager do to quantify the risk?
In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.
Which measures should the risk manager implement?
In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers
this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about
to drop their intention to continue executing the project. The risk manager does not understand their decision.
What should the risk manager do next to understand the major stakeholder ' s decision regarding the project?
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
A project team is concluding the first monthly meeting on a new engineering project, with regular review of project risks. Which document should the risk manager update to reflect the risks ' current status?
A nonprofit organization is working on a project to deliver a fundraising concert event. The concert is only a few weeks away, and the project team has completed revising the risk processes when an opportunity is identified. The key stakeholders want to capitalize on it.
What should the risk manager do?
During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.
What should the risk manager document as the risk trigger?
Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project ' s risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?
An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.
What should the risk management team leader do in the early stages of the project?