PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers
The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.
What should the risk management team have done to manage this situation?
A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.
How should the risk manager respond?
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?
After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project ' s risk exposure to an acceptable level?
A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?
A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be
mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.
Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).
At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.
How should the risk manager respond to this comment?
After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product ' s characteristics and quality. What should the risk manager propose to the project manager what to do?
A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.
Which response should the risk manager recommend for these risk items?
During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?
An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource ' s availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.
What should the risk manager do next?
There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.
What should the risk manager do to resolve this recurring situation?
During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.
What should the risk manager document as the risk trigger?
The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?
A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?
A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.
Which analytical tool should the risk manager use?
During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.
What should the risk manager do?
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?
The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.
What should the project manager do regarding those risks?
When selecting strategies as an activity of Plan Risk Response, what is the overall goal?
A software company has recently completed a project that delivered a new web application. Throughout the project, several issues were realized that resulted in cost and schedule overruns. The project ' s executive sponsor has requested a deep-dive into what went wrong since the company will be developing additional web applications in the future.
What should the risk manager do?
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?
The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.
How should this documentation be utilized in the future?
While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?
A project manager wants to introduce a new technology to improve a project ' s performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.
What should the project manager do in this situation?
A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.
What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)
The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.
What should the risk manager do?
A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.
What should the risk manager do to address the risk?
A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.
What three artifacts should the project manager consult or review during this process? (Choose three.)
The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)
Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.
What should the risk manager do?
As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
What should the project manager do next?
A risk manager has been assigned to prepare a risk management plan for a new project. Which factor should the risk manager prioritize when tailoring the risk management processes for the new project?
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?
A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.
What should the risk manager do to address this situation?
A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.
Which approach should the risk manager take to improve the quality of the project risk analysis?
A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.
What should the risk manager do?
A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.
What should the risk manager do?
Many customers using the global positioning system (GPS) of several automobile companies are complaining about errors due to a recent update. This update included a major technological change to mitigate emerging risks with software deployment. Upon investigation, the risk manager realized that this issue was identified as a high-risk item during risk analysis, which required secondary risk identification that was never completed.
What was missed in the risk management process that led to this incident?
The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?
While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?
While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.
What should the risk manager do to manage this risk?
Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simu-lation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing.
Which tool should the risk manager consider for assessing the test risk?
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers
this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about
to drop their intention to continue executing the project. The risk manager does not understand their decision.
What should the risk manager do next to understand the major stakeholder ' s decision regarding the project?
During project implementation, a risk manager wants to determine the effectiveness of risk response plans and which risk will have an impact on the project outcome. Which analysis should the risk manager do?
A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?
The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.
What should the project risk manager do next to identify risks?
The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?
Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project ' s budget.
What should the project manager do next?
What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?
An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.
What should the risk management expert recommend the agency do first to identify risks and develop the handbook?
A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project ' s timeline. The project team is struggling to finalize the project ' s budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project ' s final cost. The project team will not be able to finalize the project ' s timeline until the budget is finalized.
What should the risk manager do?
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.
As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.
What additional information should the risk manager prioritize in the risk register updates?
In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.
What should the risk manager do?
During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.
What should the risk manager do next to understand the differences between planning and execution?
An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.
Which document will need to be updated?
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?
In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.
Which measures should the risk manager implement?
The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.
What should the team perform in this scenario?
During a project ' s initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk ' s likelihood and impact with the risk manager.
What should the risk manager do?
A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.
How should the project manager work with these risk handling strategies?
it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.
Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?
A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.
Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.
How should a professional risk manager manage the risks in such situations?
A project team is presenting a delivery plan to a client. Some of the client ' s experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.
What should the risk manager do first?
During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.
What could have been done during project planning to avoid overspending?
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option ' s success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?
A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.
What should the risk manager advise the team to do first?
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?