PMI-PBA PMI Professional in Business Analysis (PMI-PBA) Questions and Answers

Questions 4

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

Options:

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Buy Now
Questions 5

A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

Options:

A.

Work breakdown structure

B.

Requirements management plan

C.

Use cases

D.

Traceability matrix

Buy Now
Questions 6

Which document best provides the boundaries for product development?

Options:

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

Buy Now
Questions 7

Which of the following is an example of a functional requirement?

Options:

A.

The system is able to require passwords.

B.

The system can be accessed from multiple locations.

C.

The system provides an user-friendly interface.

D.

The system can handle 3,000 user requests concurrently.

Buy Now
Questions 8

Which of the following would be the best practice in product validation?

Options:

A.

The measurement of the requirement should be based on the average of two or more evaluations.

B.

There should be two separate measurements for evaluating each functional requirement.

C.

Two or more testers should test the product using the same test cases so that their evaluations are consistent.

D.

The evaluation criteria should be the same as what was used to measure the requirement.

Buy Now
Questions 9

What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?

Options:

A.

Validate the requirements deemed important by the stakeholders.

B.

B. Obtain approval from engineering for partial testing of the requirements.

C.

Negotiate with the client to standardize the requirements.

D.

Assign a verification method to each requirement.

Buy Now
Questions 10

After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased. Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?

Options:

A.

Questionnaires and surveys

B.

Document analysis

C.

Observation

D.

Traceability matrix

Buy Now
Questions 11

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?

Options:

A.

The product was not adequately tested in accordance with the test plan.

B.

The requirements matrix did not adequately track back to client requirements.

C.

Requirement changes were not properly identified in the project charter.

D.

The product design was not properly reviewed by the quality department.

Buy Now
Questions 12

The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders’ views conflict.

Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?

Options:

A.

Weighted matrix, process flow, and organizational chart

B.

Stakeholder register, decision tree, and capability matrix

C.

Traceability matrix, context diagrams, and scope document

D.

Decision trees, weighted matrix, and context diagrams

Buy Now
Questions 13

Which statement accurately depicts what changes can be made to requirements after they are baselined?

Options:

A.

Requirements can be changed only with sponsor approval.

B.

Requirements can be changed through a defined process.

C.

Requirements cannot be changed once development begins.

D.

Requirements cannot be changed once user acceptance testing begins.

Buy Now
Questions 14

When modeling processes or analyzing tasks, business rules can be uncovered by asking about:

Options:

A.

tasks that overlap with each other.

B.

work that may be performed out of sequence.

C.

reasons for choosing a particular course of action.

D.

task transitions that hinder organizational performance.

Buy Now
Questions 15

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

Options:

A.

Data modeling

B.

B. Interface modeling

C.

Rules modeling

D.

Enterprise modeling

Buy Now
Questions 16

A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.

Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?

Options:

A.

Data dictionary

B.

Configuration management system

C.

Sequence diagram

D.

Process model

Buy Now
Questions 17

The business analyst has been assigned to a project involving a low number of stakeholders. Which technique should be used to elicit requirements?

Options:

A.

Survey

B.

Interview

C.

Document analysis

D.

Interface analysis

Buy Now
Questions 18

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

Options:

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Buy Now
Questions 19

A project team has completed the system use cases along with accompanying screen mockups. The business analyst schedules a review meeting with the client team to walk through the artifacts.

What is the purpose of this meeting?

Options:

A.

To verify that the system is aligned with the quality requirements

B.

To verify that the documents are aligned with the transition requirements

C.

To validate that the system is aligned with the stakeholder requirements

D.

To validate that the documents are aligned with the solution requirements

Buy Now
Questions 20

A company’s management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices.

The business analyst should:

Options:

A.

adhere to the project plan to achieve project objectives.

B.

voice user concerns to management and recommend that the project be closed.

C.

clearly communicate project objectives and attempt to defuse tensions.

D.

delay the application's deployment until the conflicts have been resolved.

Buy Now
Questions 21

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Buy Now
Questions 22

When a change request is received, the business analyst is responsible for:

Options:

A.

analyzing the impact to the project schedule and budget.

B.

ensuring that change-related incidents are minimized in production.

C.

analyzing the impact on business and underlying systems.

D.

prioritizing and scheduling the changes requested.

Buy Now
Questions 23

The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.

Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid

recommendation?

Options:

A.

Gap

B.

Risk

C.

Cost-benefit

D.

SWOT

Buy Now
Questions 24

A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.

Which technique or tool should be used?

Options:

A.

Competitive analysis

B.

Benchmarking

C.

Trend analysis

D.

Focus group

Buy Now
Questions 25

In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be

reported.

What should the business analyst use?

Options:

A.

Configuration management system

B Work breakdown structure

B.

Traceability matrix

C.

Context models

Buy Now
Questions 26

A company has developed a new product for a customer. The customer provided a specification, but the company did not produce the system requirements in the verification matrix.

The customer is having difficulty determining if the product is meeting the requirements during the test event because the:

Options:

A.

customer did not adequately review the test procedure before the test.

B.

test engineer is not communicating effectively with the customer.

C.

requirements in the technical specification are unclear and ambiguous.

D.

customer cannot make this determination until the entire test is complete.

Buy Now
Questions 27

What can a business analyst use to track requirements documentation?

Options:

A.

Affinity diagram

B.

Data dictionary

C.

Business rules matrix

D.

Version control system

Buy Now
Questions 28

How can a SWOT analysis help when deciding between several possible options to address a business problem?

Options:

A.

It can help the product owner to determine opportunity cost of not choosing an option.

B.

It can help the stakeholders to determine how to avoid the threats of each option.

C.

It can help the project sponsor to determine the valuation of each option.

D.

It can help the stakeholders identify the strengths and weaknesses of each option.

Buy Now
Questions 29

The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.

What should the team do to reduce the risk of rework?

Options:

A.

Ask the project sponsor to prioritize the requirements.

B.

Organize a new elicitation workshop.

C.

Perform a Pareto analysis on the requirements.

D.

Validate the requirements before continuing with development.

Buy Now
Questions 30

A new project's goal is to replace an existing system. What is an input into solution evaluation and decision making in this context?

Options:

A.

A Cost-benefit analysis of the existing system

B.

Technical readiness of the development team

C.

New solution design specification

D.

Customer metrics on the existing system

Buy Now
Questions 31

A business analyst is developing a traceability matrix to determine whether or not any gaps exist and to identify any discrepancies.

Which critical field is needed to ensure that the traceability matrix is usable?

Options:

A.

Status

B.

Hierarchy

C.

Owner

D.

Requirements description

Buy Now
Questions 32

Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?

Options:

A.

Brainstorming

B.

Interviewing

C.

Prototyping

D.

Surveying

Buy Now
Questions 33

A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.

Which of the following documents should be used?

Options:

A.

Stakeholder impact matrix

B.

Business analysis plan

C.

Project charter

D.

Business case

Buy Now
Questions 34

Which of the following is a method for requirements change control?

Options:

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Buy Now
Questions 35

A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.

Which course of action should the business analyst take?

Options:

A.

Evaluate if the new set of regulations is aligned with the business case.

B.

Evaluate the impact of the change on the project schedule.

C.

Obtain management sign-off on the new set of regulations.

D.

Check the traceability matrix to identify affected use cases.

Buy Now
Questions 36

A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new

functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create

project plans, schedule meetings, and provide meeting minutes.

In the scenario above, what is the role of the technical staff and testing team from Company A?

Options:

A.

Accountable

B.

Consult

C.

Responsible

D.

Inform

Buy Now
Questions 37

Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?

Options:

A.

PEST analysis

B.

B. Force-field analysis

C.

Feasibility analysis

D.

Gap analysis

Buy Now
Questions 38

Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?

Options:

A.

Solution design

B.

Business requirements

C.

Solution scope

D.

Business case

Buy Now
Questions 39

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

Options:

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Buy Now
Questions 40

A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.

What should the business analyst do to ensure that the business need can be validated?

Options:

A.

Document an assumption.

B.

Document a constraint.

C.

Document a defect.

D.

Document a business rule.

Buy Now
Questions 41

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Buy Now
Questions 42

After implementation of the product, the customer reports defects. What is the best course of action to take?

Options:

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Buy Now
Questions 43

When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts. What should the business analyst do?

Options:

A.

Start development activities without traceability items.

B.

Explain the value of requirements traceability.

C.

Negotiate for a quick approval of a reduced set of traceability artifacts.

D.

Eliminate traceability activities for the project.

Buy Now
Questions 44

A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?

Options:

A.

Meet with the stakeholder and discuss timeline impact.

B.

Refer changes to the project manager.

C.

Define requirements baseline and implement a change control process.

D.

Implement only the original requirements.

Buy Now
Questions 45

A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.

What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will

need to have a discussion about the budget?

Options:

A.

Selected project life cycle

B.

Business analysis deliverables to be produced

C.

Type of elicitation activities to be conducted

D.

Decision on the type of models to be used

Buy Now
Questions 46

A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.

From the business analysis perspective, the main reason for this business failure was a failure to:

Options:

A.

set the product positioning.

B.

review and evaluate market expectations.

C.

gather the appropriate usability requirements.

D.

establish measurable success criteria in the business case.

Buy Now
Questions 47

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

Options:

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Buy Now
Questions 48

A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.

Which tool or technique could have been used by business analyst to avoid this situation?

Options:

A.

Prototyping

B.

Surveys

C.

Document analysis

D.

Decision tree

Buy Now
Questions 49

A business analyst is trying to determine which analysis technique will be best suited to elicit information from a large number of users in a short period of time. Which elicitation technique is best suited for this purpose?

Options:

A.

Ongoing observation

B.

Facilitated workshop

C.

Questionnaire

D.

Group brainstorming

Buy Now
Questions 50

A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.

At this point, the business analyst should first:

Options:

A.

verify that the test case is incorrect.

B.

let the users decide if the test result 1s acceptable.

C.

change the requirement according to the test result.

D.

ask the tester to perform the test again.

Buy Now
Questions 51

A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.

Which of the following types of surveys would be most appropriate to create and why?

Options:

A.

A closed-ended survey to pose several multiple-choice questions and ask the users if the current business process Is correct

B.

A closed-ended survey using the Likert scale to rank specific areas of the current business process

C.

An open-ended survey to allow users the opportunity to explain their opinions on the current business process

D.

An open-ended survey to collect different opinions on the current business process

Buy Now
Questions 52

During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

Options:

A.

Ask the developer to correct the logo as stated in the requirement.

B.

Confront the stakeholder that requested the change.

C.

Follow the change control process as defined in the business analysis plan.

D.

Discuss the change in the next stakeholder meeting.

Buy Now
Questions 53

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

Options:

A.

Create prototype proof-of-concept models.

B.

Conduct requirement walkthrough sessions.

C.

Review performance data with the project sponsor.

D.

Talk to distinct testing groups to check testing status.

Buy Now
Questions 54

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

Options:

A.

Requirements cards

B.

Requirements baseline

C.

Requirements management tool

D.

Requirements traceability matrix

Buy Now
Questions 55

A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.

Which approach will better cope with the requirements’ volatility?

Options:

A.

Storyboarding

B.

Multivoting

C.

Phased baselining

D.

Comparative analysis

Buy Now
Questions 56

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

Options:

A.

Perform solution evaluation.

B.

Formulate a weighted-ranking matrix.

C.

Review the stakeholder analysis.

D.

Recommend the SVP's choice, as it is most likely to be adopted.

Buy Now
Questions 57

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

Options:

A.

Evaluate the solution against the project charter.

B.

Conduct user acceptance testing.

C.

Evaluate the solution with the sponsor(s).

D.

Conduct performance testing.

Buy Now
Questions 58

A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 59

When managing a product backlog, which statement best describes how to determine the value of backlog items?

Options:

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Buy Now
Exam Code: PMI-PBA
Exam Name: PMI Professional in Business Analysis (PMI-PBA)
Last Update: May 2, 2024
Questions: 199

PDF + Testing Engine

$249

Testing Engine

$225

PDF (Q&A)

$199