Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Questions 4

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

Options:

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starting the project.

Buy Now
Questions 5

The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.

What should the junior team member do?

Options:

A.

Speak to the agile lead about the concerns.

B.

Follow the agile lead's instructions.

C.

Increase the time worked to meet objectives.

D.

Speak to all team members about the concerns.

Buy Now
Questions 6

PMI-ACP Question 6

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?

Options:

A.

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.

B.

Maintain a commitment of 46 story points, representing the most frequently completed velocity.

C.

Increase the commitment to 48 story points to push the team toward higher performance.

D.

Commit to 44 story points as it aligns with the team's average velocity for completed story points.

Buy Now
Questions 7

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.

What should the agile practitioner do?

Options:

A.

Jointly meet with the team and product owner to discuss options and determine the end date

B.

Announce that the team has exceeded the predicted velocity and that the end date will be earlier than planned

C.

Ask the product owner to include additional features in the product backlog, then replan subsequent iterations

D.

Ask the team to decrease velocity to meet contractual obligations and document this decision

Buy Now
Questions 8

What should a Scrum Master do when an agile team member is behind on their tasks?

Options:

A.

Ask the team for suggestions.

B.

Move the tasks to another team member who has spare capacity in the sprint.

C.

Hold a one-on-one meeting to encourage the team member to meet task commitments.

D.

Inform key stakeholders.

Buy Now
Questions 9

Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?

PMI-ACP Question 9

Options:

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with that work

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

Buy Now
Questions 10

DRAG DROP

All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)

PMI-ACP Question 10

Options:

Buy Now
Questions 11

A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?

Options:

A.

Sort the stories in the backlog by descending story points and release the stories at the top of the list equal to the team's velocity.

B.

Prioritize the most valuable product features in the backlog first.

C.

Determine the features with the highest risk and release those first.

D.

Determine which features comprise the smallest feature set that could be successful in the market and establish viability of the product.

Buy Now
Questions 12

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?

Options:

A.

Work breakdown structure

B.

Description of all features' functions and an estimate of their cost

C.

Priority list of desired features and functions

D.

Comprehensive schedule of immediate deliverables

Buy Now
Questions 13

On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders' requirements.

Which of the following could help resolve the incomplete work?

Options:

A.

Conduct a spike so that the team can focus on defect repair without the distraction of new work items.

B.

Create a burndown chart to ensure the team understands the variance between the current and target velocity.

C.

Work with the Product Owner to reduce the complexity of the work so that the team can improve quality.

D.

Work with the team to ensure that acceptance criteria is being properly defined and understood.

Buy Now
Questions 14

Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?

Options:

A.

Ensure the teams are working together daily throughout the product development and are keeping the team's progress up to date.

B.

Ensure there is an environment where team members feel comfortable sharing their ideas, concerns, and feedback.

C.

Ensure the customer is provided with regular project status updates and that the meeting minutes are well documented.

D.

Ensure the team is able to release new features and updates frequently so that customers can see the product and provide feedback.

Buy Now
Questions 15

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?

Options:

A.

Plan activities that will require the team to work collaboratively on a regular basis.

B.

Set collaboration metrics and evaluate individuals against those metrics.

C.

Request that line management add more collaborative team members to the team.

D.

Allow the team to continue with no interference as activities are being met.

Buy Now
Questions 16

When a team member encounters an issue in an agile environment, what should they do?

Options:

A.

Limit communication between the team members and the customer to prevent unnecessary anxiety

B.

Manage communication between all team members and the customer to promote effective and transparent collaboration

C.

Manage communication between a few team members and the customer so that they may convey information to other team members

D.

Facilitate one-on-one communication between team members to reduce conflict and inefficiencies

Buy Now
Questions 17

A customer has given a project team several requests for new features on a product. The customer is upset that the requests have been placed in the backlog and are not currently being worked on by the team.

What should the team do next?

Options:

A.

Review the feature requests and reject the most complex ones.

B.

Organize the feature requests from simple to complex.

C.

Prioritize the requests for the next sprint.

D.

Turn the requests into user stories and prioritize them.

Buy Now
Questions 18

What should the agile team do?

Options:

A.

Discuss the efficiency at the next iteration retrospective

B.

Review the process value stream to determine potential improvements

C.

Review the value the customer receives from the user story to determine backlog priority

D.

Discuss the performance of the solution at the next sprint review

Buy Now
Questions 19

A technical problem arises that will likely impact the stories planned for delivery in the current sprint.

What should the Scrum Master do?

Options:

A.

Consider adding a story to the next sprint to seek resolution

B.

Immediately solve the problem on behalf of the team

C.

Ask the team to collaboratively work out a solution

D.

Engage a technical manager to assist with finding a solution

Buy Now
Questions 20

What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Buy Now
Questions 21

A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.

How should the scrum master help the team to resolve the issue?

Options:

A.

Bring a subject matter expert (SME) from the technology design team to act as a consultant for the team.

B.

Coach the team individually then the whole team during the Sprint review on how to resolve this conflict.

C.

Delegate the decision for the best feature implementation to the most senior team member.

D.

Decide on the technical implementation that best fits the purpose of the technical design.

Buy Now
Questions 22

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

Options:

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Buy Now
Questions 23

How should the agile team lead respond?

Options:

A.

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.

Work with the team to create a vision from the stakeholder's supplied requirements.

D.

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Buy Now
Questions 24

The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team's velocity drops.

Buy Now
Questions 25

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

Options:

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Buy Now
Questions 26

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

Options:

A.

Team members are sending more emails to the team.

B.

The duration of feedback cycles has increased.

C.

The velocity has increased by having the new team work on items.

D.

New team members requested to move meetings due to time differences.

Buy Now
Questions 27

A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.

What should the product owner do?

Options:

A.

Schedule regular meetings with the scrum team to write, groom, and size user stories

B.

Focus on stories based on the highest number of story points to first address those items with the highest value

C.

Seek regular input from project stakeholders, and reflect this input in the backlog’s priorities

D.

Schedule in-person monthly meetings with key stakeholders to review the project’s progress

Buy Now
Questions 28

In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?

Options:

A.

"Inspect and adapt" are two of the three pillars in Scrum. The roles in Scrum are divided among the product owner, scrum master, and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed.

B.

Scrum is a collaboration framework that encourages the Scrum team - the product owner, scrum master, and development team - to collaborate in a way that fosters fast value creation with respect for each team member's opinions and individual preferences.

C.

The product owner is responsible for the product backlog and long-term plans, the scrum master is responsible for the Scrum process, and the development team is responsible for the sprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation.

D.

The product owner is responsible for the product and sprint backlog. The scrum master follows up on progress, and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with.

Buy Now
Questions 29

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

Options:

A.

Help the team to remove impediments that stall project progress.

B.

Work with the development team to adjust the work plan.

C.

Ask the product owner to assign more resources to the project.

D.

Command and control the team to achieve plan goals.

Buy Now
Questions 30

Options:

A.

Small user stories

B.

Simple acceptance criteria

C.

Lean features

D.

Lean backlogs

Buy Now
Questions 31

What could help eliminate misunderstandings?

Options:

A.

Agree on requirements with all stakeholders

B.

Begin planning every four iterations

C.

Consider previous sprint demo feedback when planning the next sprint

D.

Include the reasons for the project in the contract

Buy Now
Questions 32

An organization is shifting to an agile delivery methodology. An agile project manager has been assigned to the transformation project.

What should the agile project manager do to ensure a high level of adoption?

Options:

A.

Focus on not just the "what," but also the "how" of delivering projects.

B.

Ensure that there is buy-in from senior management to adopt agile.

C.

Identify strong product owners to ensure project teams are delivering value.

D.

Train the team on the fundamentals of the agile mindset and principles.

Buy Now
Questions 33

What should the agile coach tell the team?

Options:

A.

Continuing to track velocity allows functional managers to assess whether or not the team is performing at the desired rate.

B.

The trends will show how the team performs against other Scrum teams in the organization.

C.

Tracking velocity will provide a baseline for the team to see how their continuous improvement efforts are working.

D.

Tracking velocity will document and communicate team health to the stakeholders.

Buy Now
Questions 34

What should the project leader do?

Options:

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Buy Now
Questions 35

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.

How should the scrum master proceed?

Options:

A.

Allow stakeholders to discuss without the scrum master's intervention.

B.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

C.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

D.

Organize training sessions to create awareness around the agile values for stakeholders.

Buy Now
Questions 36

During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration's remaining scope?

Options:

A.

Convince the team to stop planning and keep the size small

B.

Identify the technically minimal and achievable tasks

C.

Refer to the remaining prioritized backlog items

D.

Select some of the smallest items from the backlog

Buy Now
Questions 37

The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.

Which two actions should the product owner take first? (Choose two.)

Options:

A.

Determine the cost and resource requirements.

B.

Create a spike to determine the dependencies.

C.

Create a change request to formalize the requirements.

D.

Seek executive approval on the approach.

E.

Determine the purpose and value proposition on the approach.

Buy Now
Questions 38

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

Options:

A.

Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.

B.

Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.

C.

Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.

D.

Inform the customer of the challenges and lower velocity of the project to accommodate for the slower delivery pace.

Buy Now
Questions 39

Options:

A.

Document the problem, escalate to the project manager, and develop a solution for the team

B.

Add the problem to the backlog and assign resolution to a future iteration

C.

Instruct the team to try to solve the problem within the team

D.

Perform root cause analysis and report the problem to the product owner

Buy Now
Questions 40

During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?

Options:

A.

Self-organize

B.

Assign tasks to each team member

C.

Meet with the customer

D.

Identify the Scrum Master

Buy Now
Questions 41

Options:

A.

The increase in velocity and cost

B.

A buffer in the sprint to mitigate unexpected risks

C.

Assigning extra points to each task to allow time for changes

D.

Stories describing infrastructure tasks and analysis tasks

Buy Now
Questions 42

An agile team often fails to deliver its sprint goal. At a sprint retrospective, the more experienced team members complain that the less experienced team members are working too slowly. This creates tension in the team.

What should the scrum master do to remove this tension?

Options:

A.

Ask human resources for a training budget so the less experienced team members can increase their skill level and work more efficiently.

B.

Have an individual meeting with the experienced team members and ask them to be more empathic when the less experienced members tail to deliver.

C Remind the team that they are jointly responsible for their deliverables and should consider the different competency levels when agreeing to sprint goals

C.

Initiate a meeting with the team and ask them to decompose the product backlog items further so they become clearer and easier to deliver on time.

Buy Now
Questions 43

A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?

Options:

A.

The purpose of the daily coordination meeting is for the scrum master to be able to follow up on the sprint plan. The team should explain what may be impeding them from reaching the sprint goal.

B.

According to the Scrum guide, the daily coordination meeting is part of the Scrum framework. The purposes of this meeting are to enable the scrum master to verify the team is on track and to escalate impediments.

C.

The daily coordination meeting is an effective way for the development team to follow up on progress toward the sprint goal and discuss anything that may hinder their work. It is a way to actively manage risks and dependencies.

D.

The daily coordination meeting is held to verify that people are working on the right things. The whole Scrum team should be able to answer these questions: What did I do yesterday, what will I do today, and what can stop me from making progress?

Buy Now
Questions 44

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

Options:

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.

B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.

C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.

D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.

Buy Now
Questions 45

An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?

Options:

A.

Escalate the issue to the project sponsor.

B.

Remove stories to increase velocity.

C.

Hold a stand-up to address the issue.

D.

Facilitate a team retrospective.

Buy Now
Questions 46

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project's total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Buy Now
Questions 47

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

Options:

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Buy Now
Questions 48

All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)

Options:

A.

Due to frequent context switching, the daily 15-minute touchpoints last an hour even/ day, reducing the team's time to finish activities for the demonstrations.

B.

A developer is unable to work on their tasks within an iteration, because senior management is constantly pulling them into production incident analyses.

C.

The development team needed to urgently set up all the test data the previous week; however, due to a glitch in the system this will not be available until before the demonstration.

D.

The offshore testing team is pulled away at the last minute from a high-profile initiative and testing cannot be resumed until a new testing team is assigned.

E.

Performance issues in the testing environment, leading to a 2-day delay in implementing the code.

F.

The team has started working on the iteration, but the requirements artifacts are under review by the product owner.

Buy Now
Questions 49

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.

How should this situation be handled?

Options:

A.

The Agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.

The Agile practitioner should inform the stakeholders that the UI has already been approved by the project team and sponsor, so the team is committed to staying the course.

C.

All stakeholders should go through the approved project charter and business requirements document to reduce the number of late changes or requests.

D.

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

Buy Now
Questions 50

During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.

What should the agile practitioner do?

Options:

A.

Tell the team that this is unacceptable for the upcoming project.

B.

Implement the workaround since performance issues can be addressed in the next iteration.

C.

Calculate the cost of redoing the architecture and seek management approval.

D.

Brainstorm with the team to identify a solution.

Buy Now
Questions 51

An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.

What should the team do?

Options:

A.

The team should move to test-driven development as defects are not being detected during testing.

B.

The team should account for the increased problems in their velocity forecasts since unexpected changes occur in agile projects.

C.

The team should discuss their definition of done (DoD) and make changes to ensure there is common understanding of the acceptance criteria.

D.

The team's agile project manager should facilitate the development of a new, detailed test procedure that all team members must follow.

Buy Now
Questions 52

The product owner is very concerned about work not being completed and tested before a hard release date.

What can the agile team do to mitigate this risk?

Options:

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Buy Now
Questions 53

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the Scrum Master do?

Options:

A.

Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.

B.

Ask the team to find a workaround so that they can continue with the current project management plan.

C.

Advise the team to continue working on the sprints as the release plan has been set.

D.

Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.

Buy Now
Questions 54

How should this be handled?

Options:

A.

The story should be assigned eight story points as per the majority vote

B.

The story should be added to the backlog and reassessed later

C.

The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached

D.

The decision for the number of story points should be made by the customer

Buy Now
Questions 55

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

Options:

A.

The team should have reviewed the definition of done prior to the iteration review.

B.

The testers should have ensured that test cases accurately reflected the product owner's expectations.

C.

The team should have conducted more demonstrations with the product owner during the iteration.

D.

The product owner should have provided clearer explanations during the planning meeting.

Buy Now
Questions 56

An agile project leader notices that the team's velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.

What can happen as a result?

Options:

A.

The team will be unable to understand the iteration's status

B.

The team will be unable to judge the project design's validity

C.

The team cannot give accurate updates to management

D.

Team collaboration cannot be measured effectively

Buy Now
Questions 57

A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.

Which action should the scrum master take?

Options:

A.

Share the information radiator.

B.

Email the latest release plan.

C.

Invite them to the next retrospective.

D.

Send the latest project report.

Buy Now
Questions 58

Conversation transcript between the customer and the product owner (PO):

Customer: I am requesting a calendar feature for scheduling and reminding of upcoming releases that we can manage. We also need the calendar to indicate quarterly metrics deadlines, code freeze dates for financial close, and things like that.

PO: My understanding is that this is for tracking project deadlines. Would you need to see the project deadlines on your phone calendar?

Customer: Yes. I need to see a single snapshot on my phone. So, is it possible for me to connect my phone to this calendar app?

PO: Let me write up the requirements and get the development team on board with the deadlines. What phone do you own?

Customer: I own an Android phone, but I also need integration with the Apple phones.

Identify three minimum viable product (MVP) items. (Refer to Conversation transcript between the customer and the product owner (PO). Choose three.)

Options:

A.

Monthly calendar view

B.

Android phone integration

C.

Windows end of support deadlines

D.

Vacation calendar for team members

E.

Scheduler to add events

F.

Product increment release dates

Buy Now
Questions 59

An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.

Who is responsible for protecting against distractions?

Options:

A.

Product owner

B.

Project manager

C.

Agile leader

D.

Developers

Buy Now
Questions 60

In a project, the customer asks for a requirement that clearly deviates from the contract terms.

How should the contractor react?

Options:

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

Buy Now
Questions 61

As user stories are developed, what should be done to record and update acceptance criteria?

Options:

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.

Buy Now
Questions 62

An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.

What should the agile practitioner do?

Options:

A.

Create an issue on the backlog to investigate the root cause and assign a team resource to resolve the issue immediately.

B.

Request increased velocity from the development team to clear off some defects and stay on track with the current iteration's work.

C.

Ask the team to determine how to adapt to this increase in the next retrospective.

D.

Stop work on in-progress user stories to clear defects from the product owner and increase velocity on defect resolution.

Buy Now
Questions 63

What should the team have done to improve retrospective outcomes?

Options:

A.

Invited subject matter experts (SMEs)

B.

Conducted problem detection to determine root causes

C.

Measured and reported the outcome of improvement actions to the team

D.

Kept track of all current issues in a log and then reviewed their progress at the end of every iteration

Buy Now
Questions 64

Midway through a sprint, the Scrum Master identifies that reassigning a certain task could help the team meet its sprint goals.

What should the Scrum Master do next?

Options:

A.

Alert the team that sprint goals might not be met and create an alternative plan

B.

Obtain team buy-in to perform modifications to the sprint backlog

C.

Have the sprint proceed as planned

D.

Ask the team to decide if the task should be reassigned

Buy Now
Questions 65

What should the agile practitioner do?

Options:

A.

Ask the product owner to inform all stakeholders about the project's progress.

B.

Send meeting notes to all stakeholders after each review meeting.

C.

Include the results of the review meetings in the information radiators.

D.

Convince the stakeholders of the benefits of attending the review meetings.

Buy Now
Questions 66

A company is planning to launch a new service to improve the customer checkout experience.

What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?

Options:

A.

Engage the project stakeholders to assess the best practices to apply and plan the deliverables before implementation.

B.

Recommend an Agile delivery approach and provide information to the stakeholders on Agile values and principles.

C.

Educate the team about Scrum and ensure that all members are aligned to the roles required.

D.

Consult executive leadership for the most appropriate method for delivery using existing organizational practices.

Buy Now
Questions 67

What should the Scrum Master mention at the next retrospective?

Options:

A.

Solutions to project problems that were built into the last sprint

B.

Problems that arose

C.

Solutions that saved the organization the most time and money

D.

Problems that were solved

Buy Now
Questions 68

How should the agile team address this?

Options:

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Buy Now
Questions 69

What should the Scrum Master advise the team to do?

Options:

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story's technical approach.

C.

Transfer the story to a Scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story's priority and wait until more technical details are available.

Buy Now
Questions 70

What should the Scrum Master do?

Options:

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project's trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

Buy Now
Questions 71

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?

Options:

A.

Analyze the process efficiency, cycle time, and lead time of the entire process.

B.

Estimate in story points and pull in new work per the team's capacity

C.

Add limits to all columns and only pull work in when the queue is not full.

D.

Create a cumulative flow diagram and start looking for bottlenecks.

Buy Now
Questions 72

What should the team have done to prevent this?

Options:

A.

Reprioritized requirements prior to committing to iteration work

B.

Ensured that requirements remained stable during the iteration cycle

C.

Had stakeholders focus on items created after the product backlog was initially built

D.

Worked on features rather than a set of components

Buy Now
Questions 73

An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?

Options:

A.

Review the burndown chart to identify ways to increase efficiency.

B.

Chair a weekly team retrospective focusing on identifying areas for continuous improvement.

C.

Ask a senior manager to initiate a root-cause analysis.

D.

Identify team key performance indicators (KPIs) and create positive incentives when targetsare achieved.

Buy Now
Questions 74

Why is stakeholder engagement important for project success?

Options:

A.

To participate in establishing a shared vision as a member of the team

B.

To provide the acceptance criteria for the delivered items

C.

To propose implementation methods to the development team

D.

To evaluate the performance of the development team

Buy Now
Questions 75

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

Options:

A.

Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.

B.

Ask the Scrum Master to extend the sprint's duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand-ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager.

Buy Now
Questions 76

What should the agile practitioner do?

Options:

A.

Regularly circulate an updated, detailed version of the project plan

B.

Frequently update the online project management office (PMO) repository site

C.

Invite the stakeholders to daily stand-ups

D.

Post a project board in an area where all can view it

Buy Now
Questions 77

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: "I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles."

What is the agile lead attempting to highlight?

Options:

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.

Conflict is not productive and team members should resolve issues by themselves.

C.

Better decision-making, because the team is encouraged to join in constructive conflict.

D.

Leaders should incentivize conflict because it is inevitable in the workplace.

Buy Now
Questions 78

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.

What should the agile practitioner do?

Options:

A.

Provide all information requested by the stakeholder

B.

Set expectations regarding the appropriate level of details requested during this stage

C.

Inform the stakeholder that no detailed documents are provided using agile practices

D.

Ask the team to supply the information to the stakeholder

Buy Now
Questions 79

A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.

How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?

Options:

A.

The team needs to see the product owner's body language and facial expressions to understand what they really want.

B.

An in-person meeting helps ensure the product owner will consider their feedback carefully and not ask for any unneeded rework.

C.

It typically takes more time and resources to set up and test a virtual communications tool than to meet in person.

D.

The team will be able to better address the product owner's needs if they can have a conversation and ask questions.

Buy Now
Questions 80

What is the project leader trying to create?

Options:

A.

A safe space for team members to learn to trust one another, leading to collaborative relationships.

B.

A safe space for team members to learn to be vulnerable, leading to high performance relationships.

C.

A safe space for team members to learn to share, leading to collaborative relationships.

D.

A safe space for team members to learn about each other's weaknesses and strengths.

Buy Now
Questions 81

A project team realizes that an important task on the iteration backlog will take more time than originally estimated.

What should the project team do?

Options:

A.

Continue working on the task until it is completed

B.

Remove the task owner from the project team

C.

Add resources to reduce time to task completion

D.

Stop working on the task and include it in the next iteration

Buy Now
Questions 82

Options:

A.

Coach team members to improve functional specialties and increase overall velocity.

B.

Identify where team processes misalign with accepted Scrum practices.

C.

Facilitate the identification of problems or issues and help the team resolve them.

D.

Review the backlog to ensure that it is prioritized, refined, and properly tasked.

Buy Now
Questions 83

What should the project manager do to share this project's knowledge and learning with wider organizational business groups?

Options:

A.

Invite people from across the organization to attend daily stand-ups

B.

Invite people from across the organization to attend retrospectives

C.

Invite people from across the organization to attend the release meeting and project retrospectives

D.

Regularly meet with people across the organization to share the project's lessons learned and best practices

Buy Now
Questions 84

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

Options:

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.

B.

Ask the team to review the executed tasks and follow up on the upcoming threats.

C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.

D.

Create one sprint to update and follow up on major release risks.

Buy Now
Questions 85

A project team identifies a number of technical challenges with features in the next sprint.

What should they do?

Options:

A.

Request direction from the technical manager

B.

Encourage the Product Owner to reallocate the features to another sprint

C.

Determine who is best qualified to address the challenges

D.

Ask the Product Owner to assign the tasks to the most appropriately skilled resources

Buy Now
Questions 86

What should the Scrum Master do next?

Options:

A.

Monitor the threats and risks while allowing the team member to multitask on both projects

B.

Assign more resources to the sprints to compensate for the absences of the team member

C.

Ensure that the threats and risks are communicated and addressed

D.

Assign fewer stories to the sprints so that the team member can still meet sprint goals

Buy Now
Questions 87

During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.

How should the project manager explain this to the customer and save time in the meeting?

Options:

A.

Team performance and velocity can be determined only after the project has started

B.

Point out the Walking Skeleton and highlight the basic features that provide value.

C.

Create a kanban board for visualizing the work in process (WIP) and future development.

D.

High-level release planning is part of iteration 0 and works as a proof of concept

Buy Now
Questions 88

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

Options:

A.

Discuss the issue with the team at the next daily standup meeting.

B.

Discuss the issue with the team at a special meeting for this purpose.

C.

Discuss the issue with the project stakeholders at a special meeting for this purpose.

D.

Discuss the issue with the team at the next project retrospective.

Buy Now
Questions 89

How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)

Options:

A.

Stated understanding of the release goal

B.

Complete vision of the end product

C.

Timeline of the project

D.

List of the user stories that will be part of the next releases

E.

Complete roadmap of the next iterations

Buy Now
Questions 90

What should the agile project manager do?

Options:

A.

Discuss and address this in the iteration retrospective

B.

Let the product owner know it is the project manager's responsibility to drive a team's tasks

C.

Discuss the roles and responsibilities of the project team with the product owner

D.

Ask the product owner to work extra hours to answer the team's questions

Buy Now
Questions 91

During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.

What should the product owner do to help the team?

Options:

A.

Work with the client to ensure that the requirements are clear enough to allow a correct estimation and refine the backlog if needed.

B.

Assist the team with schedule planning to mitigate risks, including the possibility of crashing if needed.

C.

Implement clear measurements to control any deviation and therefore ensure the project's success per client requirements

D.

Recommend that the team skip requirements that are too complex and estimate them later through progressive elaboration.

Buy Now
Questions 92

The project lead of a newly created Agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.

What should the project lead do to address the gaps and develop a high-performing team?

Options:

A.

Ask each team member to document their solutions extensively in a knowledge repository for knowledge exchange between the team.

B.

Pair team members and ensure review of technical deliverables by partners in each sprint before integration of the solution.

C.

Create an environment of continued learning by providing opportunities for team members to develop their skills as generalized specialists.

D.

Replace the team members with highly qualified individuals that have experience in the specific technologies required for completing delivery.

Buy Now
Questions 93

An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?

Options:

A.

Scrum master

B.

People manager

C.

Servant leader

D.

Squad leader

Buy Now
Questions 94

During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)

PMI-ACP Question 94

Options:

A.

Prioritize the stakeholder feedback, considering the impact on strategic objectives and current workload, and discuss these priorities with the team in the next sprint planning meeting to collaboratively decide on the next steps.

B.

Implement the changes in the current sprint, reallocating resources and adjusting the sprint goals to accommodate the feedback immediately, regardless of the current workload and potential impact on ongoing tasks.

C.

Update the product backlog immediately without consulting the team, ensuring that the most critical feedback is addressed as soon as possible, even if it disrupts the current workflow.

D.

Disregard the feedback until the next product release, focusing solely on the current sprint commitments to avoid any disruption and maintain the current workflow, even if it means delaying potentially valuable changes.

Buy Now
Questions 95

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.

What should the team do?

Options:

A.

Estimate only functional requirements that will impact product quality

B.

Add team resources

C.

Refer the issue to the product owner

D.

Break non-functional requirements into those that can be delivered in the given sprint

Buy Now
Questions 96

What do the principles of Extreme Programming (XP) include?

Options:

A.

Communication, respect, and courage

B.

Communication, process flow, and authoritarian structure

C.

Value people over processes, communication, respect disagreement, and strive for consensus

D.

Rapid feedback, assume simplicity, incremental change, embrace change, and quality work

Buy Now
Questions 97

The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.

How should the Agile Leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Buy Now
Questions 98

A project team for a local government is transitioning from a predictive development life cycle to an iterative development life cycle. The project sponsor has informed the team lead that the subject matter expert (SME) for the financial functions of the solution is overallocated, so the team needs to convert the previously gathered requirements into user stories.

What should the agile lead do?

Options:

A.

Explain that the testable acceptance criteria are included in each story and it is necessary for the expert to collaborate with the developers, testers, and product owner for common understanding of the solution.

B.

Agree, and ask the developers to explain to the testers how the solution should perform for quality assurance. The testers will demonstrate to the stakeholders how the system should perform to gain acceptance.

C.

Agree, because the developers can copy and paste the requirements and include the technical specifications and performance criteria while writing the stories to save time.

D.

Explain to the project sponsor that the user stories should be assigned to the analysts, because they helped write the requirements and better understand them.

Buy Now
Questions 99

A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.

What should the agile project leader do?

Options:

A.

Add more resources to projects to ensure work sharing.

B.

Encourage the resource to undergo time management training.

C.

Ask management to ensure that the resource is available to only one project at a time.

D.

Allow the resource to continue switching between projects to deliver high customer value.

Buy Now
Questions 100

A Scrum team is refining product backlog items for the next sprint in a project. The product owner does not agree with the changes.

Can the product owner reject changes to a product backlog?

Options:

A.

Yes, the product owner is part of a Scrum team and can reject any changes on the product backlog.

B.

Yes, because the product owner is the decision maker for product backlog changes.

C.

No. because this action will create disruption in the Scrum team.

D.

No. because only members of the Scrum team can reject or approve changes.

Buy Now
Questions 101

An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours, which affects team performance.

What should the agile coach do to mitigate this issue?

Options:

A.

Speak with the functional managers and come to an agreement that will resolve the issue

B.

Explain to functional managers that too much control will inversely impact team morale

C.

Meet with the team to discuss the issue and identify specific actions to reduce or eliminate the issue

D.

Inform the team there will be penalties to anyone who visits that business during working hours

Buy Now
Questions 102

A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time.

What type of behavior does this describe?

Options:

A.

Synchronous

B.

Collaborative

C.

Passive-aggressive

D.

Random

Buy Now
Questions 103

During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.

How should the agile practitioner handle the recommendation?

Options:

A.

Record the suggestion to be considered for future projects.

B.

Invite the team to evaluate the suggestion and measure the effectiveness of the implementation.

C.

Let the product owner consider the proposal and decide whether to adopt the suggested practice.

D.

Let the team's senior members decide whether to adopt the suggested practice.

Buy Now
Questions 104

A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.

How should the team address this issue?

Options:

A.

The team member that is complaining should talk individually with the scrum master to remove impediments.

B.

They should ask for more details about the impediments and then resolve them when the team has more time to investigate.

C.

The team member that is complaining should address the impediments in daily scrum, communicating them directly.

D.

Team members should state that they need to prioritize their work instead of responding to daily emails about impediments.

Buy Now
Questions 105

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

Options:

A.

High-risk and high-value

B.

High-risk and low-value

C.

Low-risk and low-value

D.

Low-risk and high-value

Buy Now
Questions 106

A client has provided their requirements and deadline to the project team. The requirements are confusing, and the team is frustrated.

What should the team's servant leader do?

Options:

A.

Try to motivate the team by recounting examples of their past successes.

B.

Ask the team to find user stories from similar projects for this customer.

C.

Ask the team to restate the requirements and review them with the client.

D.

Ask the team to develop user stories and build deliverables based on the requirements.

Buy Now
Questions 107

During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.

How can the project team achieve this?

Options:

A.

Use a successful platform on which several object-oriented products have been developed in the past.

B.

Create a quick mock-up of the product to serve as a visual tool and adjust it until consensus is reached.

C.

Include brief exploratory iterations, proof-of-concept (POC). to reduce project risk at the beginning of every project cycle.

D.

Deliver an iteration planning diagram, allowing a 2-week refactoring period at the end of the project.

Buy Now
Questions 108

A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project

deliverables could not be completed on time.

How should the project team improve during their retrospective for future implementations?

Options:

A.

Use the scrum or team board and daily scrum meetings to track and manage issues and optimize deliverables.

B.

Encourage team members to become general specialists to reduce bottlenecks and create a cross-functional team.

C.

Empower teams and encourage emerging leadership to produce effective solutions to manage complexity.

D.

Define the roles of the individual or group and define the what, how, why, when, and where to do each task.

Buy Now
Questions 109

As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.

Which two actions should the scrum master take? (Choose two.)

Options:

A.

Proactively engage the resource managers to lead the team and provide the required support.

B.

Request the enterprise coach and human resources support the team with the transition.

C.

Document the pros and cons and review with stakeholders to determine the dependencies.

D.

Protect the team from disruptions and seek an exemption for status quo.

E.

Assess the impacts of the change and brainstorm potential solutions.

Buy Now
Questions 110

What should the agile practitioner do?

Options:

A.

Defer starting the design of item B until the second iteration is being planned

B.

Proceed with the design of item B, since it will hasten the second iteration

C.

Escalate the issue to the customer, and obtain their approval before starting the design of item B

D.

Log the issue in the risk register, and request change control board (CCB) approval

Buy Now
Questions 111

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.

What should the agile practitioner do?

Options:

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team's estimated velocity.

Buy Now
Questions 112

What is the proper agile approach to handle this?

Options:

A.

Hold frequent retrospectives and share the responsibility for making changes

B.

Understand that this is the nature of innovative business and strive to work harder

C.

Collect team member feedback and discuss them privately with the product owner

D.

Conduct a team-building exercise to increase trust among the team members

Buy Now
Questions 113

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

Options:

A.

Set clear expectations and allow everyone to contribute.

B.

Prepare the project vision statement and then present it to the team.

C.

Ask senior management to address the situation.

D.

Seek assistance from the scrum master to mediate the conflict.

Buy Now
Questions 114

An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness.

Which method of communication would be most effective?

Options:

A.

Interactive communication

B.

Pull communication

C.

Interpersonal communication

D.

Push communication

Buy Now
Questions 115

During the fourth sprint retrospective for an IT project, the team members develop a series of actions to improve problem solving in the next sprint. However, many team members are concerned that these actions will not be implemented, since there was no follow-up from the last retrospective meeting.

What should the Scrum Master do to improve team commitment to the recommendations from the retrospective meeting?

Options:

A.

Lead the team and help them to constantly improve the processes in the project.

B.

Be aggressive when working with the team to identify the root cause of the problems.

C.

Ensure each team member follows through all the improvement actions.

D.

Perform as a servant leader and let the team resolve the impediments of the project themselves.

Buy Now
Questions 116

The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.

What is the estimated project conclusion?

Options:

A.

Twelve months

B.

Three months

C.

Six months

D.

Two months

Buy Now
Questions 117

The vice president (VP) of an organization has been asked by the chief information officer (CIO) to have their teams to embrace an agile approach to projects. The VP, however, often insists teams use a more predictive approach to project management which allows the project managers to do what they like.

How should an agile team member coach the VP and teams be more effective?

Options:

A.

Coach the chief information officer (CIO) on implementation of agile benefits and expectations.

B.

Coach the teams on implementation of agile benefits and expectations.

C.

Coach the managers on implementation of agile benefits and expectations.

D.

ICoach the vice president (VP) on implementation of agile benefits and expectations.

Buy Now
Questions 118

The product owner working on an agile software development project has brought all the Scrum team members together for the first sprint planning meeting. The team has read the user stories and has provided estimates to complete these user stories. The product owner plans to empower the team to get the work done.

What is this an example of?

Options:

A.

Emotional intelligence

B.

Two-way communication

C.

Bipartisan agreement

D.

Reciprocal communication

Buy Now
Questions 119

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Buy Now
Questions 120

What should an agile practitioner do to ensure that the end product meets business requirements?

Options:

A.

Invite the team to iteration review meetings

B.

Obtain agreement from the product owner on business requirements

C.

Request that regular reports are sent to stakeholders

D.

Confirm managers and stakeholders are invited to product review meetings

Buy Now
Questions 121

Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

Options:

A.

Assign story B more than 8 story points to provide a better estimate

B.

Add points to story B’s iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A, B, and C

Buy Now
Questions 122

While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments.

What should the agile coach do?

Options:

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation

Buy Now
Questions 123

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.

How should the team lead address this?

Options:

A.

Inform management and suggest that additional resources may be required

B.

Discuss the issue with the team in the daily stand-up meetings

C.

Meet personally with the stressed team member to brainstorm ways to better manage their time

D.

Begin tracking the stressed team member's tasks in a separate backlog for additional analysis and reporting

Buy Now
Questions 124

Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.

Which of the following activities should be performed next?

Options:

A.

The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed.

B.

The team should perform a spike to conduct research on their technical solutions and prove their viability.

C.

The team should consolidate small stories into larger ones so that there are less work items to be estimated.

D.

The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort.

Buy Now
Questions 125

What should the product owner do?

Options:

A.

Accept responsibility for the product's delay.

B.

Ensure that the project sponsor's priorities are in the product backlog.

C.

Negotiate with the project sponsor for increased funding.

D.

Empower the project sponsor to manage the product backlog.

Buy Now
Questions 126

A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.

What should the project lead do to accommodate this request?

Options:

A.

Review the burn up chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

B.

Review the burn down chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

C.

Ensure the team focus on completing the current items in the backlog and do not accept any request for changes.

D.

Work with the product owner to launch a minimum viable product (MVP) and focus on completing only this portion of work by the new deadline.

Buy Now
Questions 127

A global organization is migrating its IT infrastructure from traditional, physical assets to cloud-based assets. Agile concepts are new to the organization because it currently uses a predictive approach.

What should an Agile Coach do to facilitate a culture change to an Agile approach?

Options:

A.

Develop and distribute a high-level summary of how Agile offers greater benefit than predictive to mid-level managers and let them decide if it should be distributed to lower-level workers.

B.

Develop and distribute a high-level summary of competing vendors' product alignment and Agile project execution to the Product Owner for approval.

C.

Develop and distribute a high-level summary of how Agile offers greater benefits than predictive to all members of the organization.

D.

Develop and distribute a high-level summary of how Agile offers greater benefits than predictive to the organization's executive directors, and if executive directors agree with the summary, distribute it organization-wide.

Buy Now
Questions 128

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master's estimation

B.

Identify a set of user stories based on the team's velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion

Buy Now
Questions 129

What should the team do?

Options:

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Buy Now
Questions 130

A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.

Is this agile strategy appropriate?

Options:

A.

Yes, this is a case of sequential development where working in parallel is an accepted strategy in agile to gain time.

B.

Yes, this is a case of hybrid development where a product is divided into components and agile is used for component development and integration.

C.

No, dividing the development team into three separate teams will diminish communication and result in delays.

D.

No the feedback loops are being altered, which can result in big failures and delays

Buy Now
Questions 131

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after all spikes are executed

Buy Now
Questions 132

What should the product owner have done differently?

Options:

A.

Demonstrated only the completed stories and seek stakeholder feedback

B.

Presented the budget situation and review the cost variance

C.

Reviewed the test results to gain confidence from the stakeholders

D.

Presented a demo of all the stories including the work in progress stories

Buy Now
Questions 133

Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed.

How should the agile leader reduce this conflict?

Options:

A.

Facilitate team agreement on the definition of done (DoD) during the chartering process.

B.

Motivate the team during Tuckman's "storming" phase.

C.

Ensure the product owner is grooming the backlog so user stories are clearly written.

D.

Ensure epics are broken down into smaller user stories for clarity.

Buy Now
Questions 134

Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date.

What should the agile practitioner do?

Options:

A.

Deal with the issues in a retrospective if they ever come up again.

B.

Create a task board to track issues when they appear.

C.

Identify and monitor issues through a risk burndown chart.

D.

Create an issue log as an information radiator and monitor.

Buy Now
Questions 135

What should the agile practitioner do?

Options:

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner's manager that the work items provide insufficient detail.

Buy Now
Questions 136

An agile team is planning the next iteration for a product release that has accumulated technical debt. What should the team do?

Options:

A.

Add code cleanup activities to the product backlog and request prioritization by the product owner

B.

Add code cleanup activities to the next iteration and request clarification from the product owner

C.

Add code cleanup activities to the next iteration and ask the product owner to end the current iteration

D.

Add code cleanup activities to the next release backlog and request documentation from the product owner

Buy Now
Questions 137

What should be proposed to the team?

Options:

A.

Have other team developers attend training to learn database skills.

B.

Monitor the retrospectives of two additional sprints before taking action.

C.

Plan fewer stories for the sprint to reduce the database engineers' workload.

D.

Ask the Scrum Master to work with the product owner to remove backlog stories that have database dependency.

Buy Now
Questions 138

What is a specific development practice that has been effective in implementing disciplined DevOps?

Options:

A.

Put the client first.

B.

Create a safe environment.

C.

Practice continuous delivery.

D.

Manage risk.

Buy Now
Questions 139

A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?

Options:

A.

Have the development team follow the product owner's direction

B.

Openly challenge the product owner in an effort to poke holes in their approach

C.

Facilitate a conversation about the user story between the development team and the product owner

D.

Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Buy Now
Questions 140

A Kanban team is struggling to prioritize and determine which tasks to handle first according to value.

What should the team do to improve this situation?

Options:

A.

Involve their product owner.

B.

Review their work in progress (WIP) limits.

C.

Use class of service.

D.

Measure their lead time.

Buy Now
Questions 141

A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?

Options:

A.

Create a time-boxed spike story to reduce the technical risk of the feature.

B.

Commence an iteration 0 for the customer and the team to investigate the feature.

C.

Facilitate the decomposition of the feature epic into more manageable user stories.

D.

Facilitate a just-in-time exploration of the functionality by the customer and the team.

Buy Now
Questions 142

What should the Scrum Master do?

Options:

A.

Ask the product owner how upper management's comments can be redirected.

B.

Direct the developer team to ignore the phone calls and emails.

C.

Ask the product owner to enter the requests into the product backlog as high priority.

D.

Personally respond to upper management's phone calls and emails.

Buy Now
Questions 143

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

Options:

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

Buy Now
Questions 144

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?

Options:

A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.

B.

They can provide an anticipated date with the assumption that conditions will be ideal.

C.

They can provide a broad range but cannot realistically set a target release date until the team's velocity stabilizes.

D.

They will send an update when all of the stories are estimated and prioritized in the backlog.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Oct 15, 2025
Questions: 476

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99