An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?
The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.
What should the junior team member do?
The team is considering committing to 44 story points for the upcoming sprint. Based on the
velocity chart, what advice should the scrum master offer the team?
Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.
What should the agile practitioner do?
What should a Scrum Master do when an agile team member is behind on their tasks?
Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?
DRAG DROP
All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)
A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?
A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.
What should the product owner have the customer review and approve?
On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders' requirements.
Which of the following could help resolve the incomplete work?
Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?
A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.
What should the agile practitioner do?
When a team member encounters an issue in an agile environment, what should they do?
A customer has given a project team several requests for new features on a product. The customer is upset that the requests have been placed in the backlog and are not currently being worked on by the team.
What should the team do next?
A technical problem arises that will likely impact the stories planned for delivery in the current sprint.
What should the Scrum Master do?
A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.
How should the scrum master help the team to resolve the issue?
An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.
Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).
The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?
A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?
A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.
What behavior would indicate the team is not working well together?
A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.
What should the product owner do?
In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?
The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.
What should the coach do to help the team?
An organization is shifting to an agile delivery methodology. An agile project manager has been assigned to the transformation project.
What should the agile project manager do to ensure a high level of adoption?
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.
How should the scrum master proceed?
During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration's remaining scope?
The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.
Which two actions should the product owner take first? (Choose two.)
A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.
What steps should the project leader take to improve knowledge sharing?
During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?
An agile team often fails to deliver its sprint goal. At a sprint retrospective, the more experienced team members complain that the less experienced team members are working too slowly. This creates tension in the team.
What should the scrum master do to remove this tension?
A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?
A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.
What strategy should be used to deliver it successfully?
An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?
During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.
What is the agile project manager trying to show?
What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?
All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)
Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.
How should this situation be handled?
During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.
What should the agile practitioner do?
An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.
What should the team do?
The product owner is very concerned about work not being completed and tested before a hard release date.
What can the agile team do to mitigate this risk?
A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.
What should the Scrum Master do?
At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.
How should this situation have been prevented?
An agile project leader notices that the team's velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.
What can happen as a result?
A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.
Which action should the scrum master take?
Conversation transcript between the customer and the product owner (PO):
Customer: I am requesting a calendar feature for scheduling and reminding of upcoming releases that we can manage. We also need the calendar to indicate quarterly metrics deadlines, code freeze dates for financial close, and things like that.
PO: My understanding is that this is for tracking project deadlines. Would you need to see the project deadlines on your phone calendar?
Customer: Yes. I need to see a single snapshot on my phone. So, is it possible for me to connect my phone to this calendar app?
PO: Let me write up the requirements and get the development team on board with the deadlines. What phone do you own?
Customer: I own an Android phone, but I also need integration with the Apple phones.
Identify three minimum viable product (MVP) items. (Refer to Conversation transcript between the customer and the product owner (PO). Choose three.)
An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.
Who is responsible for protecting against distractions?
In a project, the customer asks for a requirement that clearly deviates from the contract terms.
How should the contractor react?
As user stories are developed, what should be done to record and update acceptance criteria?
An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.
What should the agile practitioner do?
Midway through a sprint, the Scrum Master identifies that reassigning a certain task could help the team meet its sprint goals.
What should the Scrum Master do next?
A company is planning to launch a new service to improve the customer checkout experience.
What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?
A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.
What should the team do to improve its speed of delivery?
A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.
What should the team do to improve its speed of delivery?
An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?
A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?
An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: "I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles."
What is the agile lead attempting to highlight?
During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.
What should the agile practitioner do?
A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.
How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?
A project team realizes that an important task on the iteration backlog will take more time than originally estimated.
What should the project team do?
What should the project manager do to share this project's knowledge and learning with wider organizational business groups?
A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.
What should the project manager do to make sure team members are following up on risks?
A project team identifies a number of technical challenges with features in the next sprint.
What should they do?
During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.
How should the project manager explain this to the customer and save time in the meeting?
The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.
What should the agile practitioner do?
How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)
During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.
What should the product owner do to help the team?
The project lead of a newly created Agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.
What should the project lead do to address the gaps and develop a high-performing team?
An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?
During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)
A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.
What should the team do?
The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.
How should the Agile Leader address this?
A project team for a local government is transitioning from a predictive development life cycle to an iterative development life cycle. The project sponsor has informed the team lead that the subject matter expert (SME) for the financial functions of the solution is overallocated, so the team needs to convert the previously gathered requirements into user stories.
What should the agile lead do?
A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.
What should the agile project leader do?
A Scrum team is refining product backlog items for the next sprint in a project. The product owner does not agree with the changes.
Can the product owner reject changes to a product backlog?
An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours, which affects team performance.
What should the agile coach do to mitigate this issue?
A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time.
What type of behavior does this describe?
During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.
How should the agile practitioner handle the recommendation?
A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.
How should the team address this issue?
When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?
A client has provided their requirements and deadline to the project team. The requirements are confusing, and the team is frustrated.
What should the team's servant leader do?
During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.
How can the project team achieve this?
A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project
deliverables could not be completed on time.
How should the project team improve during their retrospective for future implementations?
As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.
Which two actions should the scrum master take? (Choose two.)
After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.
What should the agile practitioner do?
The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.
How can the team improve their collaboration?
An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness.
Which method of communication would be most effective?
During the fourth sprint retrospective for an IT project, the team members develop a series of actions to improve problem solving in the next sprint. However, many team members are concerned that these actions will not be implemented, since there was no follow-up from the last retrospective meeting.
What should the Scrum Master do to improve team commitment to the recommendations from the retrospective meeting?
The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
The vice president (VP) of an organization has been asked by the chief information officer (CIO) to have their teams to embrace an agile approach to projects. The VP, however, often insists teams use a more predictive approach to project management which allows the project managers to do what they like.
How should an agile team member coach the VP and teams be more effective?
The product owner working on an agile software development project has brought all the Scrum team members together for the first sprint planning meeting. The team has read the user stories and has provided estimates to complete these user stories. The product owner plans to empower the team to get the work done.
What is this an example of?
What should an agile practitioner do to ensure that the end product meets business requirements?
Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?
While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments.
What should the agile coach do?
A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.
How should the team lead address this?
Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.
Which of the following activities should be performed next?
A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.
What should the project lead do to accommodate this request?
A global organization is migrating its IT infrastructure from traditional, physical assets to cloud-based assets. Agile concepts are new to the organization because it currently uses a predictive approach.
What should an Agile Coach do to facilitate a culture change to an Agile approach?
An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.
What should the agile team do?
A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.
Is this agile strategy appropriate?
Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed.
How should the agile leader reduce this conflict?
Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date.
What should the agile practitioner do?
An agile team is planning the next iteration for a product release that has accumulated technical debt. What should the team do?
What is a specific development practice that has been effective in implementing disciplined DevOps?
A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?
A Kanban team is struggling to prioritize and determine which tasks to handle first according to value.
What should the team do to improve this situation?
A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?
An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.
What is the sponsor looking at?
A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).
What should the team tell the sponsor at this point in the planning process?