Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Questions 4

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

Options:

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.

B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.

C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.

D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.

Buy Now
Questions 5

An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project ' s way. What role is the agile coach advising to the project manager to take on?

Options:

A.

Scrum master

B.

People manager

C.

Servant leader

D.

Squad leader

Buy Now
Questions 6

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?

Options:

A.

Foster stronger communication by hosting cross-organizational meetings between the two teams.

B.

Suggest merging the teams to avoid misunderstandings.

C.

Create stories from full technical specifications to avoid ambiguity.

D.

Co-locate the teams to encourage osmotic communication.

Buy Now
Questions 7

In a Scrum team, who should be responsible for the budget and release plans?

Options:

A.

The Scrum Master assigns someone on the team to handle the budget, and the Product Owner is responsible for release plans

B.

The finance department is responsible for the budget, and the Product Owner is responsible for release plans

C.

The Scrum team as a whole, as they are self-organizing and share accountability

D.

The Product Owner is responsible for both the budget and the release plans

Buy Now
Questions 8

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.

What should the Scrum Master do?

Options:

A.

Dismiss the team member

B.

Discuss the situation with the functional manager

C.

Report the functional manager to the project sponsor

D.

Demand that the functional manager respect the project charter

Buy Now
Questions 9

A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.

How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?

Options:

A.

The team needs to see the product owner ' s body language and facial expressions to understand what they really want.

B.

An in-person meeting helps ensure the product owner will consider their feedback carefully and not ask for any unneeded rework.

C.

It typically takes more time and resources to set up and test a virtual communications tool than to meet in person.

D.

The team will be able to better address the product owner ' s needs if they can have a conversation and ask questions.

Buy Now
Questions 10

A software team is developing a product in an environment with increased uncertainty. Although there is a clear vision of the goals to be achieved, the product owner is not fully certain about how some of the product features should work.

How should the product owner address this situation?

Options:

A.

Improve the product testing and quality assurance skills among the team

B.

Facilitate more product planning sessions with the software team.

C.

Consider moving to a more predictive product development approach.

D.

Develop a prototype of the product to obtain feedback from users.

Buy Now
Questions 11

A member of the development team displays disrespectful behavior and continuously argues with colleagues. This is negatively impacting team morale.

Which action should the scrum master take to resolve this situation?

Options:

A.

Mitigate the new conflicts that appear and rely on the self-organization of the team.

B.

Escalate the issue to senior management to make a decision.

C.

Follow the organization ' s policies to remove the team member to boost team engagement.

D.

Attend daily coordination meetings and retrospectives with the agile coach.

Buy Now
Questions 12

To help the team gain confidence, what should the agile practitioner suggest?

Options:

A.

Develop a spike

B.

Create an Ishikawa diagram

C.

Perform a pre-mortem analysis

D.

Complete a variance and trend analysis

Buy Now
Questions 13

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?

Options:

A.

Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.

B.

Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.

C.

Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.

D.

Implement a spike to enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working.

Buy Now
Questions 14

A team retrospective was going well until the team lead introduced the " define the next experiment " topic; then the discussion became an argument. A new team member feels strongly that the approach used on their previous team would improve this team ' s efficiency and effectiveness. The team lead is adamant that they remain with the current approach and the discussion dissolves into a circular argument.

Options:

A.

Remind the group that all input is welcome but dissension is not productive and suggest the group move on to another task more agreeable to everyone.

B.

Restate both stances, ask for details of both approaches, and create a chart of similarities and differences.

C.

Construct an Ishikawa diagram for each approach, and use the 5 Whys technique to determine the effectiveness of each approach.

D.

Interject and request this experiment be postponed for 2 months, so the new team member has time to observe the current approach.

Buy Now
Questions 15

There is a throughput of 200 tickets in a customer service line. The tickets are raised by employees, with each 8-hour shift averaging 50 tickets in progress.

What is the cycle time to resolve a ticket?

Options:

A.

0.25 hour

B.

1 hour

C.

2 hours

D.

4 hours

Buy Now
Questions 16

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?

Options:

A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.

B.

They can provide an anticipated date with the assumption that conditions will be ideal.

C.

They can provide a broad range but cannot realistically set a target release date until the team ' s velocity stabilizes.

D.

They will send an update when all of the stories are estimated and prioritized in the backlog.

Buy Now
Questions 17

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.

What should the agile practitioner do?

Options:

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team ' s estimated velocity.

Buy Now
Questions 18

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

Options:

A.

Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.

B.

Ask the Scrum Master to extend the sprint ' s duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand-ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager.

Buy Now
Questions 19

PMI-ACP Question 19

In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)

Options:

A.

Implementing a systematic approach to automate integration, testing, and deployment activities

B.

Increasing the frequency of stakeholder meetings to gather feedback on feature priorities

C.

Leveraging regular reviews, feedback loops, and lessons learned to adjust at key milestones

D.

Organizing training sessions for end users to ensure effective utilization of the planning tool

Buy Now
Questions 20

A scrum team is experiencing lengthy discussions leading to no concrete actions during their scrum events. The scrum master determines that these inefficient meetings are producing waste.

What should the scrum master do to make the meetings more efficient?

Options:

A.

Issue fixed agendas and a decision log for all scrum events to ensure that only relevant agenda points are discussed and decisions are appropriately captured.

B.

Remind the team of the purpose of each scrum event, and implement a policy that long conversations deviating from the scope of each event will be stopped.

C.

Ask the product owner to conduct these discussions in individual meetings with the team members.

D.

Remind the team that staying on topic during meetings is part of being a self-managing team.

Buy Now
Questions 21

What should the Scrum Master mention at the next retrospective?

Options:

A.

Solutions to project problems that were built into the last sprint

B.

Problems that arose

C.

Solutions that saved the organization the most time and money

D.

Problems that were solved

Buy Now
Questions 22

What should the agile coach do?

Options:

A.

Start the hiring process for a new, equally skilled database administrator as a replacement.

B.

Move this database administrator to another team so that team members learn database-related tasks.

C.

Add another database administrator to balance the workload and aid with knowledge retention.

D.

Obtain agreement from the team that, on upcoming sprints, the database administrator will act only in an advisory capacity.

Buy Now
Questions 23

During refinement, the team tester has a question about part of the acceptance criteria for a given user story. Who should clarify the acceptance criteria?

Options:

A.

The sponsor, since they understand the business value.

B.

The Scrum Master, since they coordinate with the team and define the acceptance criteria.

C.

The Product Owner, since their vision is the basis for the acceptance criteria.

D.

The developer, since they write the code that would be tested.

Buy Now
Questions 24

Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do?

Options:

A.

Ask the agile practitioner to help write the user stories.

B.

Ask the agile team to facilitate a story-writing workshop.

C.

Ask subject matter experts (SMEs) to help write the user stories.

D.

Ask the agile practitioner to facilitate a story-writing workshop.

Buy Now
Questions 25

How should an agile project leader interact with the Product Owner?

Options:

A.

Conduct regular one-on-one meetings to review development features and trace them back to the product roadmap

B.

Ensure that they attend regular sprint meetings to provide product-feature feedback

C.

Share any new versions of the project plan with them including updated statuses for tasks and project milestones

D.

Schedule meetings where they can provide team direction regarding new-feature priorities and upcoming sprints

Buy Now
Questions 26

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Buy Now
Questions 27

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

Options:

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Buy Now
Questions 28

Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.

What should the agile coach do?

Options:

A.

Incorporate quality assurance in the planning stage of product development.

B.

Schedule a dedicated meeting with the product owner to tackle this roadblock.

C.

Conduct a brainstorming exercise to get to the root of the issue and devise action plans.

D.

Conduct a retrospective meeting at the end of the current iteration to identity necessary improvements.

Buy Now
Questions 29

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

Options:

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Buy Now
Questions 30

After completing the release plan, the team realizes that the project is very likely to have a negative ROI.

What should the team do?

Options:

A.

Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI

B.

Replace some team members to reduce the release costs and minimize a negative ROI

C.

Perform a root-cause analysis to remove waste from the delivery process and increase the ROI

D.

Communicate the risk of a negative ROI to the stakeholders, and update the release plan

Buy Now
Questions 31

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

Options:

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Buy Now
Questions 32

During a retrospective, a team member claims that a specific set of documentation that is continuously updated during iterations is not being used by any stakeholder.

What should the team do?

Options:

A.

Continue updating the documentation but initiate an analysis to identify its value and act on the findings.

B.

Stop updating the documentation since no one is using it.

C.

Continue updating the documentation since it is clearly required by the process.

D.

Stop updating the documentation and initiate an analysis to identify its value and act on the findings.

Buy Now
Questions 33

An executive sponsor of a new Scrum team actively attends Scrum ceremonies.

How does this benefit the team?

Options:

A.

It helps the team to focus on and meet sprint goals.

B.

It reminds the team about who sponsors the project.

C.

It provides high-level project updates to the sponsor.

D.

It helps to quickly resolve issues using the sponsor ' s influence.

Buy Now
Questions 34

What is the proper agile approach to handle this?

Options:

A.

Hold frequent retrospectives and share the responsibility for making changes

B.

Understand that this is the nature of innovative business and strive to work harder

C.

Collect team member feedback and discuss them privately with the product owner

D.

Conduct a team-building exercise to increase trust among the team members

Buy Now
Questions 35

An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.

What should the agile practitioner do?

Options:

A.

Create an issue on the backlog to investigate the root cause and assign a team resource to resolve the issue immediately.

B.

Request increased velocity from the development team to clear off some defects and stay on track with the current iteration ' s work.

C.

Ask the team to determine how to adapt to this increase in the next retrospective.

D.

Stop work on in-progress user stories to clear defects from the product owner and increase velocity on defect resolution.

Buy Now
Questions 36

What should the customer do?

Options:

A.

Expand the Scrum Master ' s role to other projects, while allowing them to support the current project.

B.

Release the Scrum Master, since the team is adequately skilled with agile practices.

C.

Expand the product owner ' s role to serve as the Scrum Master, while providing additional product knowledge.

D.

Increase the functional manager ' s role to act as the Scrum Master, while providing additional information about functional areas.

Buy Now
Questions 37

An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.

Who is responsible for protecting against distractions?

Options:

A.

Product owner

B.

Project manager

C.

Agile leader

D.

Developers

Buy Now
Questions 38

In companies where decision-making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?

Options:

A.

A formalized agile approach offers controlled flexibility in dealing with unknown variables in a manner that adds business value.

B.

Agile is focused only on digital transformation project management, whereas a predictive approach focuses on traditional " brick and mortar " projects.

C.

The agile formal change management system is better able to deal with unknown variables.

D.

Agile is relatively new; therefore, it is inherently more aligned with data-analytic-based efforts.

Buy Now
Questions 39

PMI-ACP Question 39

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).

At the end of which sprint will the minimum viable product (MVP) be completed?

Options:

A.

7

B.

8

C.

9

D.

10

Buy Now
Questions 40

On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders ' requirements.

Which of the following could help resolve the incomplete work?

Options:

A.

Conduct a spike so that the team can focus on defect repair without the distraction of new work items.

B.

Create a burndown chart to ensure the team understands the variance between the current and target velocity.

C.

Work with the Product Owner to reduce the complexity of the work so that the team can improve quality.

D.

Work with the team to ensure that acceptance criteria is being properly defined and understood.

Buy Now
Questions 41

What should a Scrum Master do when one team member falls behind in their tasks?

Options:

A.

Move the task to another team member who has spare capacity in the sprint

B.

Ask the team for suggestions

C.

Privately offer the team member encouragement to meet task commitments

D.

Notify the product owner

Buy Now
Questions 42

What should the agile coach do to develop members into a high-performance team?

Options:

A.

Teach the team how to work comfortably in chaos.

B.

Provide strong facilitation and conflict-resolution guidance.

C.

Allow the team to resolve issues on their own.

D.

Observe each team member and advise them on team relationships.

Buy Now
Questions 43

Two agile teams from different company sites need to work and collaborate on the same project. What is the first action the agile project manager should take in order to ensure a smooth collaboration between the two teams?

Options:

A.

Organize onsite backlog-refinement workshops to ensure common understanding.

B.

Set up weekly meetings where all team members will participate.

C.

Call an onsite meeting where ground rules will be discussed and agreed upon.

D.

Ask the product owner to prepare an onsite team-building activity.

Buy Now
Questions 44

What should the agile practitioner do?

Options:

A.

Work with the agile team and product owner to agree on the definition of done

B.

Ask the project sponsor to determine whether the product is completed

C.

Plan another review after the product has been tested

D.

Add testing to the backlog, and have the product owner reprioritize

Buy Now
Questions 45

Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?

PMI-ACP Question 45

Options:

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with that work

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

Buy Now
Questions 46

In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?

Options:

A.

" Inspect and adapt " are two of the three pillars in Scrum. The roles in Scrum are divided among the product owner, scrum master, and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed.

B.

Scrum is a collaboration framework that encourages the Scrum team - the product owner, scrum master, and development team - to collaborate in a way that fosters fast value creation with respect for each team member ' s opinions and individual preferences.

C.

The product owner is responsible for the product backlog and long-term plans, the scrum master is responsible for the Scrum process, and the development team is responsible for the sprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation.

D.

The product owner is responsible for the product and sprint backlog. The scrum master follows up on progress, and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with.

Buy Now
Questions 47

What should the agile practitioner do?

Options:

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration ' s test-automation levels and reduce redundancy

Buy Now
Questions 48

A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?

Options:

A.

Establish and keep an active risk register that includes mitigation strategies and a cost-benefit analysis.

B.

Establish and keep an active risk register based on qualitative risk analysis and expected losses.

C.

Have each development team post the highest risk development items on the information radiator.

D.

Avoid risk by splitting development teams into two locations to ensure knowledge continuity.

Buy Now
Questions 49

A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?

Options:

A.

Assign agile roles within the team and conduct training for each role to provide understanding of the agile methodology.

B.

Organize training and development workshops to help all stakeholders to form a shared understanding of agile practices.

C.

Plan a transformation to agile delivery methods for senior leadership before starting project implementation.

D.

Apply only agile methods and practices for specific deliverables of the work and assign this work to experienced agile team members.

Buy Now
Questions 50

An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?

Options:

A.

Report this as a blocker and ask senior management to provide the right subject matter experts (SMEs) until all the outstanding issues can be dosed.

B.

Identify the key business stakeholders and invite them to day-long sessions until all the dependencies and outstanding issues can be closed.

C.

Identify the key dependencies that need to be resolved in order of priority level so the user stories can meet the definition of ready (DoR) criteria.

D.

Report this as a blocker and ensure the product owner is able to deprioritize the issues so the user stories can meet the definition of ready (DoR) criteria.

Buy Now
Questions 51

When working on a new product, what should an agile team do to ensure alignment with external stakeholders?

Options:

A.

Hold a kick-off meeting to assign roles.

B.

Review the project vision statement.

C.

Ask the product owner for a detailed product-specification document.

D.

Work with the Scrum Master to ensure that agile principles are followed.

Buy Now
Questions 52

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

Options:

A.

Notify the product owner and begin resolution.

B.

Communicate the issue to the team in the next stand-up meeting.

C.

Immediately begin resolution, and communicate it to the team during the retrospective.

D.

Work on the next activity, and communicate it to the team during the retrospective.

Buy Now
Questions 53

What should the team have done to prevent this?

Options:

A.

Reprioritized requirements prior to committing to iteration work

B.

Ensured that requirements remained stable during the iteration cycle

C.

Had stakeholders focus on items created after the product backlog was initially built

D.

Worked on features rather than a set of components

Buy Now
Questions 54

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team ' s agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration

Buy Now
Questions 55

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options:

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and Product Owner decide and reprioritize based on value

C.

Recommend canceling the current iteration and plan the change request into the next iteration

D.

Recommend that the Product Owner add this change request as a user story to the backlog for the current iteration

Buy Now
Questions 56

An agile project team has team members with varying technical skills. Due to recent events that adversely impacted customer satisfaction, management mandated that Kaizen should be given more focus to ensure the quality in product delivery.

Kaizen is a prime concept of which agile practices?

Options:

A.

Standup meetings. Extreme Programming (XP), relative estimating

B.

Build quality in, visualize workflow, fail fast

C.

Standup meetings, retrospective meetings, continuous improvement

D.

Collaborate, regular builds, inspections

Buy Now
Questions 57

A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?

Options:

A.

Discuss the issue to reduce the backlog based on decreased productivity of the team.

B.

Collect updates from each team member before the meeting and share them with all members.

C.

Ask the team member to update daily progress on the information radiators.

D.

Change the team velocity to show positive progress in shared information radiators.

Buy Now
Questions 58

A project ' s Product Owner asks the Scrum Master to facilitate the estimation activity. The Scrum Master then meets with the team and the Product Owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

Options:

A.

Lessons learned

B.

Wideband Delphi

C.

Formal point counting

D.

Planning poker

Buy Now
Questions 59

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options:

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Buy Now
Questions 60

What should an agile practitioner do to ensure that the end product meets business requirements?

Options:

A.

Invite the team to iteration review meetings

B.

Obtain agreement from the product owner on business requirements

C.

Request that regular reports are sent to stakeholders

D.

Confirm managers and stakeholders are invited to product review meetings

Buy Now
Questions 61

One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective.

How should the product owner respond?

Options:

A.

Stakeholders have the opportunity to add features to the sprint.

B.

Team members determine if there are any impediments preventing them from meeting the sprint goal.

C.

The product owner explains which product backlog items have been done and which have not.

D.

Team members identify ways to improve and make plans to implement these improvements.

Buy Now
Questions 62

An agile facilitator is helping a team. The team is taking too long in each daily coordination meeting, and the facilitator is beginning to view the time as unproductive.

What should the agile facilitator do to help the team?

Options:

A.

Reduce the number of participants in the daily coordination meeting so only one representative for each user story or area of expertise can participate each day.

B.

Change the structure of the daily coordination meetings so team members only comment on the blockers they face during the day.

C.

Let team members decide how to execute the meeting because they are self-organized and should know what works for them.

D.

Pay attention to the comments of each team member during the meeting and intervene every time they deviate from the objective of the meeting.

Buy Now
Questions 63

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature ' s story points to their burndown chart?

Options:

A.

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.

No, because the product owner has not reviewed the release implementation checklist for potential issues.

Buy Now
Questions 64

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

Options:

A.

The team should have reviewed the definition of done prior to the iteration review.

B.

The testers should have ensured that test cases accurately reflected the product owner ' s expectations.

C.

The team should have conducted more demonstrations with the product owner during the iteration.

D.

The product owner should have provided clearer explanations during the planning meeting.

Buy Now
Questions 65

A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.

What should the agile project leader do?

Options:

A.

Add more resources to projects to ensure work sharing.

B.

Encourage the resource to undergo time management training.

C.

Ask management to ensure that the resource is available to only one project at a time.

D.

Allow the resource to continue switching between projects to deliver high customer value.

Buy Now
Questions 66

While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments.

What should the agile coach do?

Options:

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation

Buy Now
Questions 67

An agile team is planning the next iteration for a product release that has accumulated technical debt. What should the team do?

Options:

A.

Add code cleanup activities to the product backlog and request prioritization by the product owner

B.

Add code cleanup activities to the next iteration and request clarification from the product owner

C.

Add code cleanup activities to the next iteration and ask the product owner to end the current iteration

D.

Add code cleanup activities to the next release backlog and request documentation from the product owner

Buy Now
Questions 68

A team member has made a mistake on a project.

How should the Scrum Master address the mistake?

Options:

A.

Encourage all team members to follow existing processes.

B.

Require team members to complete a peer review of work and deliverables.

C.

Facilitate a retrospective to identify areas of improvement.

D.

Reward those who have the lowest occurrences of mistakes.

Buy Now
Questions 69

Options:

A.

Add new security features to the backlog and prioritize.

B.

Execute a spike to research security features for the project.

C.

Ask questions to determine where and how the product owner wants to use the product.

D.

Ask questions to determine if the product owner can define the desired level of security.

Buy Now
Questions 70

How could the project leader have avoided this?

Options:

A.

Led by example by encouraging the team to engage in consensus-driven decision making

B.

Iterated the need for agile teams to make quick decisions, then followed up with that team member

C.

Empowered a team member to facilitate decision making then made a final decision on behalf of the team

D.

Refrained from participating in the team ' s decision-making process, except to document and communicate results

Buy Now
Questions 71

During backlog refinement, a team routinely creates tests to demonstrate to the customer that each acceptance criterion has been met. Most acceptance tests results are observable or demonstrable, but testing for one requirement is providing a challenge to the team. The requirement states that the home button should be recognizable and the team is unsure how to test this.

What should the team lead do?

Options:

A.

Determine if the home button is present and if it is shaped like a house, it is recognizable.

B.

Record the product owner ' s opinion on how they will know if the button is recognizable.

C.

Skip creating a specific test for Ibis particular requirement because it is too abstract

D.

Consult the design team as subject matter experts (SMEs) for criteria on what makes a button recognizable.

Buy Now
Questions 72

How can an agile team working on a new product ensure alignment with external stakeholders?

Options:

A.

Ask the product owner to provide a detailed product specification document

B.

Conduct story-mapping exercises to clarify deliverables and release priorities

C.

Hold a kick-off meeting to assign roles and responsibilities

D.

Work with the scrum master and stakeholders to ensure agile principles are followed

Buy Now
Questions 73

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.

How should the team lead address this?

Options:

A.

Inform management and suggest that additional resources may be required

B.

Discuss the issue with the team in the daily stand-up meetings

C.

Meet personally with the stressed team member to brainstorm ways to better manage their time

D.

Begin tracking the stressed team member ' s tasks in a separate backlog for additional analysis and reporting

Buy Now
Questions 74

An agile project leader notices that the team ' s velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.

What can happen as a result?

Options:

A.

The team will be unable to understand the iteration ' s status

B.

The team will be unable to judge the project design ' s validity

C.

The team cannot give accurate updates to management

D.

Team collaboration cannot be measured effectively

Buy Now
Questions 75

PMI-ACP Question 75

Answer Options:

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team ' s velocity is constant.

Buy Now
Questions 76

Options:

A.

Keep sprints short.

B.

Invite the stakeholder to the daily stand-ups.

C.

Ask the stakeholder for estimates for each user story.

D.

Schedule more demos during each sprint.

Buy Now
Questions 77

A business analyst has been assigned to optimize a process to deliver healthcare services to patients in a clinic. In creating a value stream map, what will the business analyst’s key observations include?

Options:

A.

Process breakdowns and workflow

B.

Wait times and cycle times

C.

Process maps and story points

D.

Activity sequences and earned value (EV)

Buy Now
Questions 78

An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success?

Options:

A.

Address this impediment by obtaining suitable training for the team.

B.

Address the risks resulting from complexity within sprint zero.

C.

Facilitate team brainstorming of the risks resulting from complexity for the risk register.

D.

Motivate the team to try new technical approaches.

Buy Now
Questions 79

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

Options:

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Buy Now
Questions 80

What should the project leader suggest?

Options:

A.

Develop and document a detailed architectural design; peer review with the development team and implement/test

B.

Develop the functional requirements of the solution first before any non-functional requirement, as they provide more customer value

C.

Discuss the integration requirement with the product owner and negotiate it to be lower on the backlog to focus on the minimal marketable feature

D.

Develop and test the implementation approach and demonstrate it at the next sprint review to collect feedback

Buy Now
Questions 81

What is the project leader trying to create?

Options:

A.

A safe space for team members to learn to trust one another, leading to collaborative relationships.

B.

A safe space for team members to learn to be vulnerable, leading to high performance relationships.

C.

A safe space for team members to learn to share, leading to collaborative relationships.

D.

A safe space for team members to learn about each other ' s weaknesses and strengths.

Buy Now
Questions 82

How should the team resolve this?

Options:

A.

Refer to the values of the agile framework and the team

B.

Review the signed customer contract

C.

Check the sprint priority list

D.

Submit the problem to the product owner

Buy Now
Questions 83

A senior executive contacted an agile lead about starting an agile project to solve a problem for the human resources (HR) department of a company. The project idea is not clear and no backlog has been developed.

How should the agile lead start the project?

Options:

A.

More work is needed to refine the idea and there is no backlog to start working on, so there is no way to help the manager.

B.

Identify the persona that needs help and conduct a workshop applying the empathy map technique about that persona.

C.

Review how similar problems have been resolved in other companies and see if a solution is available on the market.

D.

Start working on a list of user stones to create a backlog and suggest a product owner be assigned to the project.

Buy Now
Questions 84

An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.

How should the agile practitioner improve the team’s productivity?

Options:

A.

Work with the team to ensure that both the product and iteration backlogs are up to date.

B.

Work with the team to ensure that the release backlog is in sync with the product backlog.

C.

Work with the team to ensure that the iteration and release backlogs are kept up to date.

D.

Work with the team to ensure that the product backlog is always kept up to date.

Buy Now
Questions 85

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities.

How should the stakeholders ensure their objectives are met by product delivery?

Options:

A.

Provide feedback for completed user stories.

B.

Define how the features will be implemented.

C.

Tell the team which features to include in the backlog.

D.

Write acceptance criteria for the user stories.

Buy Now
Questions 86

What should the team do?

Options:

A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories

B.

Create a triage step on the Kanban board to pre-identify risky stories

C.

Set a policy to break down stories larger than a specified complexity, then adjust the WIP

D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large

Buy Now
Questions 87

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?

Options:

A.

Include security concerns on the agenda for every meeting.

B.

Request that a security expert be added to the team.

C.

Add security as a non-functional requirement to the risk register, and review regularly.

D.

Ensure that planning and prioritizing includes consideration of security requirements.

Buy Now
Questions 88

During sprint planning, the product owner wants the team to prioritize and deliver a number of features that have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.

What should the project leader do?

Options:

A.

Encourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies

B.

Encourage the team to continue with the current plan, do what they can, and carry forward the work not done to the next iteration

C.

Ensure the team captures the technical dependencies as issues within the backlog and prioritize based on value optimization

D.

Ensure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization

Buy Now
Questions 89

What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Buy Now
Questions 90

An agile project was underway for two months and delivered the expected value to the stakeholders. However, during a sprint review, a team member complained that the product owner constantly changes requirements and the member feels that this is blocking the team’s performance.

How can the scrum master handle this situation?

Options:

A.

Work with the product owner to include fewer features in the next sprint planning.

B.

Hire more team members to elevate the team ' s velocity to increase performance.

C.

Tell the team members that changes are natural and welcome if the project is delivering value.

D.

Schedule more meetings with the team and the product owner to refine the backlog constantly.

Buy Now
Questions 91

What can an agile team use to prioritize stories?

Options:

A.

Planning poker technique

B.

Weighted average calculation

C.

Risk-value quadrant

D.

INVEST scale

Buy Now
Questions 92

All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)

Options:

A.

Due to frequent context switching, the daily 15-minute touchpoints last an hour even/ day, reducing the team ' s time to finish activities for the demonstrations.

B.

A developer is unable to work on their tasks within an iteration, because senior management is constantly pulling them into production incident analyses.

C.

The development team needed to urgently set up all the test data the previous week; however, due to a glitch in the system this will not be available until before the demonstration.

D.

The offshore testing team is pulled away at the last minute from a high-profile initiative and testing cannot be resumed until a new testing team is assigned.

E.

Performance issues in the testing environment, leading to a 2-day delay in implementing the code.

F.

The team has started working on the iteration, but the requirements artifacts are under review by the product owner.

Buy Now
Questions 93

A seven-member agile team ' s composition varies considerably in age, gender, culture, personality type, and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?

Options:

A.

Networking

B.

Social awareness

C.

Communication

D.

Leadership

Buy Now
Questions 94

An agile team had unexpected technical problems in a project and was not able to complete the deliverables on time. During the retrospective meeting, the team openly discussed the causes for these issues and what can be done to avoid similar situations in the future.

What agile values and principles did the team demonstrate?

Options:

A.

The team is being proactive by discussing how to better balance demands and capacity and make sure they have the right competencies.

B.

The team shows respect for one another by listening to everyone ' s opinions and valuing human interaction during face-to-face meetings.

C.

The team is providing one another with fast feedback to find those responsible for any mistakes so they can be avoided in the future.

D.

The team eliminates potential waste by discussing who should be responsible for future risk management by actively applying the pi an-do-check-act (PDCA) method.

Buy Now
Questions 95

A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?

Options:

A.

To produce a fast return on investment

B.

To reduce risk as quickly as possible

C.

To gain competitive advantage as soon as possible

D.

To maintain visibility with project stakeholders

Buy Now
Questions 96

How should the agile practitioner address this?

Options:

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the Kanban board and assign it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

Buy Now
Questions 97

What agile tools can help the team address these issues?

Options:

A.

Information radiators and wireframes

B.

Information radiators and story maps

C.

Process flows and personas

D.

Personas and extreme characters

Buy Now
Questions 98

A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.

How should the project manager handle a review with the team member?

Options:

A.

Talk to the team member about project deliverables and how poor performance is unacceptable.

B.

Discuss performance with the team member on the project deliverables and provide constructive feedback.C Inform the learn member that this project is complex and consider moving them to another project

C.

Extend support to the team member as this is the first project in which the team member underperformed.

Buy Now
Questions 99

Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed.

How should the agile leader reduce this conflict?

Options:

A.

Facilitate team agreement on the definition of done (DoD) during the chartering process.

B.

Motivate the team during Tuckman ' s " storming " phase.

C.

Ensure the product owner is grooming the backlog so user stories are clearly written.

D.

Ensure epics are broken down into smaller user stories for clarity.

Buy Now
Questions 100

A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.

What should the scrum master do?

Options:

A.

Review the release plan with the product owner and invite the stakeholders to a series of release reviews.

B.

Review the metrics and the process to determine where the overhead could be further reduced to speed up delivery.

C.

Explain to the product owner why the sprint reviews are now replaced by release reviews as inspect and adapt is a key principle in Scrum.

D.

Explain to the product owner that getting feedback early and often from stakeholders is important so necessary changes can be made quickly.

Buy Now
Questions 101

PMI-ACP Question 101

A product owner is working on a special agile project for the automobile industry. The project team is responsible for all of the issues related to vehicle electronic control units. The team has observed a significant backlog of items in the “In progress ' column (Refer to the kanban board). This accumulation is causing delays in task completion and impacting overall project timelines. The team operates in a dynamic environment where requirements frequently change, and stakeholders demand quick turnarounds.

What should the project team adopt to address this issue and improve task flow, considering all the demands?

Options:

A.

Increase the number of items allowed in the ' In progress " column to accommodate the high volume of tasks and provide flexibility.

B.

Limit the work in progress (WIP) and implement strict policies to encourage team members to focus on completing existing tasks before starting new ones, ensuring a balanced workload.

C.

Move tasks to the ' Done " column regardless of their completion status to give the appearance of progress and alleviate the pressure of the backlog.

D.

Add more team members with varying levels of expertise to handle the increased workload, aiming to accelerate task completion and reduce the backlog in the ' In progress " column.

Buy Now
Questions 102

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

Options:

A.

Work with team members to resolve the issue.

B.

Escalate the issue to the product owner.

C.

Allow team members to resolve the issue.

D.

Escalate the issue to senior management.

Buy Now
Questions 103

PMI-ACP Question 103

A scrum master is overseeing the launch of a chatbot for the service desk. Complaints come up post-release about edge case responses to queries. After analyzing the issues, the business decision was made to take the chatbot offline, resulting in workflow disruptions and risking the reputation.

How could this situation have been avoided? (Refer to Testing Protocol Table)

Options:

A.

Conduct user acceptance testing to ensure the chatbot meets stakeholder needs and expectations.

B.

Perform integration testing to minimize any bugs between the chatbot components.

C.

Perform functional testing to verify the chatbot performs the reguired functions.

D.

Conduct regression testing to ensure all previously functioning chatbot features continue to work after updates.

Buy Now
Questions 104

During team meetings, the team often struggles with making decisions about their technical approach.

What should be done to improve the quality and timeliness of decisions?

Options:

A.

Work with the team to improve collaboration by fostering group decision-making and conflict resolution techniques.

B.

Promote team discussion but give the Product Owner the ultimate decision-making authority.

C.

Assign individual team members as decision owners for each key decision to avoid conflict.

D.

Identify team members that demonstrate servant leadership qualities to facilitate discussion and make decisions.

Buy Now
Questions 105

During an iteration, an urgent customer request for support reaches the team. If they work on it, the team ' s commitments in this iteration are at risk.

What should the team do next?

Options:

A.

Work overtime to meet the customer request and the iteration commitments.

B.

Ask another team that is less busy to handle the situation.

C.

Work with the product owner to assess the impact for reprioritization.

D.

Work on the customer request in the next iteration as a top priority.

Buy Now
Questions 106

An agile team is working on the first sprint, and has already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

Options:

A.

Communicate the importance of the business need to the team and refine the product backlog.

B.

Ask the team to discuss the changes to the features with the customer.

C.

Meet with the agile team lead to prioritize the requirements.

D.

Discuss and prioritize the requirements with the team.

Buy Now
Questions 107

A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.

What should the product owner do?

Options:

A.

Schedule regular meetings with the scrum team to write, groom, and size user stories

B.

Focus on stories based on the highest number of story points to first address those items with the highest value

C.

Seek regular input from project stakeholders, and reflect this input in the backlog’s priorities

D.

Schedule in-person monthly meetings with key stakeholders to review the project’s progress

Buy Now
Questions 108

During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)

PMI-ACP Question 108

Options:

A.

Prioritize the stakeholder feedback, considering the impact on strategic objectives and current workload, and discuss these priorities with the team in the next sprint planning meeting to collaboratively decide on the next steps.

B.

Implement the changes in the current sprint, reallocating resources and adjusting the sprint goals to accommodate the feedback immediately, regardless of the current workload and potential impact on ongoing tasks.

C.

Update the product backlog immediately without consulting the team, ensuring that the most critical feedback is addressed as soon as possible, even if it disrupts the current workflow.

D.

Disregard the feedback until the next product release, focusing solely on the current sprint commitments to avoid any disruption and maintain the current workflow, even if it means delaying potentially valuable changes.

Buy Now
Questions 109

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

Options:

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

Buy Now
Questions 110

During agile training, an aspiring scrum master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.

How should the agile trainer respond?

Options:

A.

The Kanban approach relies on storyboards.

B.

The Kanban approach focuses on adaptive, simultaneous workflows.

C.

There are no work-in-process limits in the Kanban approach.

D.

Kanban teams employ a pull system.

Buy Now
Questions 111

A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.

What should the team lead do next?

Options:

A.

Negotiate with the project director to reduce the types of tests for which they need details to reduce the impact of this request.

B.

Escalate this as an issue to the executive project sponsor for a decision because it will impact the ability of the team to deliver the product on time.

C.

Ask the test manager to provide a detailed estimate of the time required to write the plan for the solution and their capacity for the remainder of the week.

D.

Ask the team to put their work on hold and collaborate on the documentation because it can be completed quicker if everyone shares the work.

Buy Now
Questions 112

What should the team do to effectively manage this?

Options:

A.

Rework the iteration scope to accommodate these requirements.

B.

Add these requirements into the product backlog for future consideration.

C.

Raise the discovery of these requirements as an issue, and escalate to management.

D.

Immediately start working on these requirements.

Buy Now
Questions 113

A software project is being implemented by a small, colocated team. What should the project manager do to keep the team focused and engaged with the high level of requirements?

Options:

A.

Arrange afternoon touchpoints where the team can discuss what they have done during the day

B.

Request that the project sponsor is present during daily standups to increase commitment from the team.

C.

Send out daily activity tasks to each member of the team, mitigating the risk of tasks being forgotten.

D.

Make use of a kanban board so that the team will have a clear view of the work in progress (WIP) for the release.

Buy Now
Questions 114

On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders ' business needs. Which option supports this idea?

Options:

A.

A project charter should be established and reviewed throughout the project life cycle to ensure the accurate documentation of stakeholders ' interests and expectations.

B.

A product backlog should be created to list the project requirements from all of the project stakeholders.

C.

An Agile Manifesto should be created to document the project stakeholders, their desired outcomes, and identified risks.

D.

A user story should be created for all key stakeholders to list their individual business objectives and needs.

Buy Now
Questions 115

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: " I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles. "

What is the agile lead attempting to highlight?

Options:

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.

Conflict is not productive and team members should resolve issues by themselves.

C.

Better decision-making, because the team is encouraged to join in constructive conflict.

D.

Leaders should incentivize conflict because it is inevitable in the workplace.

Buy Now
Questions 116

What should the agile team do?

Options:

A.

Discuss the efficiency at the next iteration retrospective

B.

Review the process value stream to determine potential improvements

C.

Review the value the customer receives from the user story to determine backlog priority

D.

Discuss the performance of the solution at the next sprint review

Buy Now
Questions 117

What should the team do?

Options:

A.

Re-estimate the sprint ' s completed stories to increase and adjust the sprint ' s velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Buy Now
Questions 118

What can the project team do to assist in achieving the organizational goal?

Options:

A.

Maintain and review a lessons learned repository to improve delivery of future projects.

B.

Ask each team member to post corrective action to the backlog.

C.

Engage the project management office (PMO) to take responsibility for identifying lessons learned on projects.

D.

Perform a root cause analysis to identify alternative approaches for performing the next project.

Buy Now
Questions 119

The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.

How should the Agile Leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Buy Now
Questions 120

What should the agile project manager have done to avoid this?

Options:

A.

Invited end customers to attend the stand-ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Buy Now
Questions 121

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team ' s target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Buy Now
Questions 122

Over the last two sprints, a number of potential problems have threatened the team ' s ability to hit the targeted release date.

What should the agile practitioner do?

Options:

A.

Deal with the issues in a retrospective if they ever come up again.

B.

Create a task board to track issues when they appear.

C.

Identify and monitor issues through a risk burndown chart.

D.

Create an issue log as an information radiator and monitor.

Buy Now
Questions 123

A new Agile team is forming to address a high-priority project. Team members are dispersed over a wide geographic area. The Scrum Master and the team are currently defining their working agreement.

What should be part of the working agreement for a dispersed team?

Options:

A.

Identify support needed from external vendors to assist dispersed team members.

B.

Meet face to face at regular intervals to enhance shared understanding.

C.

Designate one person to communicate with all team members working at different locations.

D.

Define what project work can be done by dispersed team members.

Buy Now
Questions 124

A project manager is managing a large complex project with cross-functional teams using an adaptive approach. Frequent communication among the team leads of these cross-functional teams is crucial for the project to stay on track and deliver value according to the project plan.

Which agile communication practice should the project manager implement to ensure the cross-functional teams interact frequently?

Options:

A.

Empower each cross-functional team lead to manage their team ' s issues and impediments.

B.

Post the daily coordination meetings and discuss impediments raised by the teams.

C.

Ask the project management office (PMO) to work on the communications management plan for the cross-functional teams.

D.

Set up additional meetings to handle additional communications if necessary.

Buy Now
Questions 125

Iterations last between a couple of weeks to a couple of months, with a preference for the shorter time. What is the goal for each iteration?

Options:

A.

Complete the assigned tasks.

B.

Deliver working software frequently.

C.

Demonstrate the software to the customer.

D.

Provide a high-level timeline.

Buy Now
Questions 126

More details for a story are required before the upcoming sprint planning meeting.

What should the Scrum Master do?

Options:

A.

Email the product owner requesting detailed story specifications and wait for a response

B.

Gather the details from the team members before sprint planning

C.

Schedule a story grooming session with the product owner before sprint planning

D.

Conduct a planning poker session with the team

Buy Now
Questions 127

A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team.

What is the agile project leader doing?

Options:

A.

Practicing the servant leadership style of working with an agile team

B.

Building a collaborative teamwork culture

C.

Following a participatory decision-making model

D.

Adopting the practice of receiving feedback that will facilitate team improvement

Buy Now
Questions 128

What should the agile team do?

Options:

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Buy Now
Questions 129

During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?

Options:

A.

Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting.

B.

Create a spike story to determine what needs to be done to use the new interface.

C.

Lower the epic ' s priority so that it can be deferred, and analyze it during backlog refinement meetings.

D.

Move the work to the vendor, since they have better knowledge of interface implementation.

Buy Now
Questions 130

What is a benefit of this meeting?

Options:

A.

The team will learn how its contribution will create product value

B.

It will enable team acceptance of client priorities

C.

It will enable the team to see the entire project in one glance

D.

It will enable the team to ask any questions to the customer upfront

Buy Now
Questions 131

An agile team is preparing a release plan for a project. What information will the team need to complete this plan?

Options:

A.

Amount of work needed to complete a single user story

B.

Amount of work that can be accomplished by each team member

C.

Amount of work that can be accomplished in an iteration

D.

Amount of work that can be accomplished by the entire team

Buy Now
Questions 132

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Buy Now
Questions 133

The coach on a new agile team notices that one team member is influencing most of the team ' s decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team ' s velocity drops.

Buy Now
Questions 134

After conducting the second retrospective with project stakeholders, the customer expresses frustration. The customer wants a more predictable roadmap for the delivery of features and functionalities.

How should the project manager respond to the customer?

Options:

A.

Explain to the customer that an agile approach requires re-prioritization at the beginning of each sprint, so it is not possible to provide a roadmap.

B.

Ask the customer to develop a roadmap the team can follow for future delivery.

C.

Work with the customer to understand which user stories will deliver the best business value, re-prioritize the backlog, and share it with the customer to provide release plans.

D.

Work with the product owner to develop a tentative roadmap for the customer but explain that it is always subject to change.

Buy Now
Questions 135

What should the agile practitioner do?

Options:

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner ' s manager that the work items provide insufficient detail.

Buy Now
Questions 136

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.

What should the servant leader do?

Options:

A.

Coach the company director on agile approaches and good practices.

B.

Ask the product owner to speak to the director because their visits are delaying the project.

C.

Ask the director and team member to leave the room so they can have a private conversation.

D.

Coach the team member on how to report progress to directors and executives.

Buy Now
Questions 137

What is the risk of using Agile in a distributed team?

Options:

A.

Frequent integration of work produced

B.

Lack of shared knowledge of user stories

C.

Need for more locations to learn Agile

D.

Unclear team structure

Buy Now
Questions 138

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project ' s total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Buy Now
Questions 139

During a sprint review, the Product Owner identifies a required improvement for a feature’s user interface (UI) delivered during the sprint.

What should the Product Owner do next?

Options:

A.

Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer

B.

Create a user story for this new improvement and prioritize it for the next sprint

C.

Document it as a requirement creep

D.

Ask the team to take on additional story points to improve the UI

Buy Now
Questions 140

An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours, which affects team performance.

What should the agile coach do to mitigate this issue?

Options:

A.

Speak with the functional managers and come to an agreement that will resolve the issue

B.

Explain to functional managers that too much control will inversely impact team morale

C.

Meet with the team to discuss the issue and identify specific actions to reduce or eliminate the issue

D.

Inform the team there will be penalties to anyone who visits that business during working hours

Buy Now
Questions 141

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

Options:

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Buy Now
Questions 142

A stakeholder complains about the amount of changes that are being introduced to a project. What should the product owner do?

Options:

A.

Escalate the complaint to the scrum master

B.

Suggest implementing a more rigorous change governance

C.

Coach the stakeholder on agile principles

D.

Agree to limit scope changes going forward to control costs

Buy Now
Questions 143

How should the agile team lead respond?

Options:

A.

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.

Work with the team to create a vision from the stakeholder ' s supplied requirements.

D.

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Buy Now
Questions 144

What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team ' s incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: May 10, 2026
Questions: 481

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99