PgMP Program Management Professional (PgMP) Questions and Answers

Questions 4

You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?

Options:

A.

Audit reports

B.

Program management plan

C.

Program performance reports

D.

Program issues register updates

Buy Now
Questions 5

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, how many pennies is the program losing per dollar invested in the program work?

Options:

A.

17

B.

11

C.

15

D.

14

Buy Now
Questions 6

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Options:

A.

Project Management Information System

B.

Integrated Change Control

C.

Scope Verification

D.

Configuration Management System

Buy Now
Questions 7

A program manager learns that their company’s organizational strategy has changed. This change impacts one component project of a program, misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete.

What should the program manager do next?

Options:

A.

Immediately submit a component project closure request to the program sponsor so that resources can be reallocated to strategically aligned component projects.

B.

Assess the impact of closure on other component projects, and generate a recommendation for submission to the program governance board.

C.

Recommend that the component project manager complete work activity to deliver benefits to the organization.

D.

Update the benefits management plan to reflect the impact of the change on the program and its intended benefits.

Buy Now
Questions 8

You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Options:

A.

EV/AC

B.

EV/PV

C.

BAC/CPI

D.

EAC-AC

Buy Now
Questions 9

A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.

What activity should the program manager perform next?

Options:

A.

Program delivery management

B.

Resource interdependency management

C.

Program performance monitoring and controlling

D.

Benefits sustainment and program transition

Buy Now
Questions 10

A program management team is invited to a company’s annual strategy planning session. The CEO discusses the mission and vision of the organization, and how the strategic plan will create opportunities to fulfill them.

How can the program manager use the company’s vision to establish a program?

Options:

A.

Define the program and component projects to enable the fulfillment of strategic goals.

B.

Set the priority matrix, and map the projects’ priorities that will be included in the program.

C.

Define the program roadmap, and highlight the individual projects’ benefits.

D.

Identify program benefits that will enable the fulfillment of strategic goals.

Buy Now
Questions 11

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff.

What should the program manager do to ensure communications on the component projects are consistent?

Options:

A.

Request a more experienced project manager to work on project B.

B.

Create a program communications management plan across all component projects.

C.

Direct all projects to use project A's communications management plan as a template.

D.

Rework the communications management plans for all projects to be consistent.

Buy Now
Questions 12

Who prepares the statement of work (SOW) for external projects?

Options:

A.

Customer

B.

Project management team

C.

Project Manager

D.

Chief Financial Officer (CFO)

Buy Now
Questions 13

You are the program manager for your organization. Your program is about to being initiated and management is asking you for a document that will define all of the required resources, skills, and competencies you'll need in your program. What document defines the skills and competencies for a program?

Options:

A.

Staffing management plan

B.

Staffing pool description

C.

Program resources requirements plan

D.

Human resources management plan

Buy Now
Questions 14

While setting up a program’s infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program’s components.

What should the team also prepare, if not already provided by the organization’s assets?

Options:

A.

Breakdowns such as the program work breakdown structure (PWBS), component project milestones, and budgets that transform top-level planning into fragments relevant to the components

B.

Industry standards that provide guidance to the component project managers on how to adapt their detailed planning to the program’s master plan

C.

Documents that enable level-adequate aggregation and consolidation of component/program information and forecasting

D.

Files, filing structures, and templates for knowledge repositories that contain centrally stored and commonly maintained program data

Buy Now
Questions 15

You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

Options:

A.

Contract administration

B.

Resource management

C.

Resource control

D.

Procurement management

Buy Now
Questions 16

A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review.

What is the other part of the review?

Options:

A.

Tracking and reporting on benefits management plan

B.

Identifying factors influencing delivery of benefits

C.

Demonstrating that other stage gate requirements have been met

D.

Gathering additional stakeholders' requirements

Buy Now
Questions 17

In a program's definition phase, a program manager in country A is assigned to expand a restaurant chain into country B. The program manager creates the program team by identifying the required project management resources.

Which of the following represents an initial step needed to evaluate available resources that are aligned with the program's needs?

Options:

A.

Completing an assessment of skills and competencies

B.

Obtaining resource availability information from the functional managers

C.

Identifying program resource requirements

D.

Creating a program resource management plan

Buy Now
Questions 18

During the selection of source process, you assign certain points towards various categories to judge the vendors. Which type of source selection process is it?

Options:

A.

Benefit-cost analysis

B.

Screening system

C.

Weighting system

D.

Preferred vendor list

Buy Now
Questions 19

You are the program manager for your organization. You have proposed a program that will cost $750,000

and will last for four years. Management is concerned with the cost of the program in relation to the return your

program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?

Options:

A.

$750,000

B.

$795,000

C.

$750,001

D.

$946,857

Buy Now
Questions 20

A program will generate revenue for several years after it ends. The program manager and the operations manager, who are accountable for managing the benefits after program closure, are in disagreement. The operations manager is concerned that information necessary for managing the processes and benefits after program closure will be unavailable. The program manager expresses that managing the benefits after program closure is not within the scope and must be managed through the scope management plan.

What should the program sponsor do?

Options:

A.

Direct the operations manager to allocate a resource to the program to ensure that knowledge transfer and process development occur before closure.

B.

Direct the operations manager to allocate the necessary resources to establish proper plans for accepting the benefits and processes after program closure.

C.

Direct the program manager to develop the necessary plans to ensure benefits can be transitioned and sustained after program closure.

D.

Direct the program manager to assess the impact of this change and follow the established change management process.

Buy Now
Questions 21

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

Options:

A.

.99

B.

-$2,500

C.

$2,500

D.

1.02

Buy Now
Questions 22

Which one of the following is not an output of the direct and manage program execution process?

Options:

A.

Results of program work

B.

Program budget

C.

Change requests

D.

Request to terminate the program

Buy Now
Questions 23

You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end- of-phase review management is completing on your project?

Options:

A.

Quality control

B.

Kill point

C.

Phase review

D.

Audit

Buy Now
Questions 24

In a transformational program, all projects are on track and delivering their objectives. However, stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance. Stakeholders fear that the program will fail to provide the service required.

To assure positive performance in the current environment, the program manager should do which of the following?

Options:

A.

Ensure the new processes will perform better than the current processes.

B.

Ask the program steering committee to endorse the new processes and current program schedule and deliverables.

C.

Meet with stakeholders to ensure they understand that the expectations for the new processes are superior to the current processes.

D.

Discuss concerns with stakeholders and mitigate them by changing the processes that will be delivered.

Buy Now
Questions 25

Tom is the program manager for his organization. He has to balance the resources he'll be using in the program with the demand for operations to use the same resources. What program document can Tom reference to determine the availability of certain program resources, such as application developers, engineers, and technical writers?

Options:

A.

Staffing management plan

B.

Resource calendar

C.

Functional management plan

D.

The resource pool description

Buy Now
Questions 26

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.

In what phase is the risk management plan created?

Options:

A.

Program definition

B.

Program execution management

C.

Program delivery

D.

Program risk management planning

Buy Now
Questions 27

A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified.

Key stakeholders for the program should include which of the following?

Options:

A.

Potential customers, government regulatory agencies, and competitors

B.

Project management office (PMO), third-party contractors, and agents

C.

Local car dealers, factory workers, and corporate officers

D.

Vice president of logistics, potential customers, and corporate executives

Buy Now
Questions 28

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.

What should the program manager do next?

Options:

A.

Escalate the issue to the stakeholder’s supervisor

B.

Escalate the issue to the program governance board, as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks

Buy Now
Questions 29

A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company’s headquarters. Five regional sales departments are located at different locations around the world.

At this stage of the program, what is the first step?

Options:

A.

Develop a program work breakdown structure

B.

Identify and quantify business benefits of the program

C.

Determine and prioritize the various components of the program

D.

Prepare a program organization chart covering both sales and production

Buy Now
Questions 30

As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

Options:

A.

The project management lifecycle and the project lifecycle are the same thing.

B.

The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work.

C.

The project management lifecycle is unique to each project while the project lifecycle is universal to all projects.

D.

The project management lifecycle is universal to all projects and the project lifecycle is unique to each project.

Buy Now
Questions 31

Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has a cost variance of a positive $56,000. While Tom is pleased, the new management is not. Why is a positive cost variance not necessarily good news?

Options:

A.

A poor cost estimate prevented the organization from adding things to the program scope.

B.

Tom has overestimated the cost of the program.

C.

A poor cost estimate could affect the organization's decisions to invest the funds elsewhere .

D.

Tom has forgot to include deliverables in the program.

Buy Now
Questions 32

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?

Options:

A.

Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.

B.

Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.

C.

Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.

D.

Add the lack of skilled resources to facilitate the large number of change requests to the issue log.

Buy Now
Questions 33

Which of the following shows the ratio between a task's budgeted and actual costs?

Options:

A.

To-Complete Performance Index (TCPI)

B.

Schedule Variance (SV)

C.

Schedule Performance Index (SPI)

D.

Cost Performance Index (CPI)

Buy Now
Questions 34

A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country’s branches by the end of the fiscal year. Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support

the regulation, as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured.

What should the program manager do to address the risk?

Options:

A.

Build a coalition with local companies that can influence the government to renegotiate the imposed deadline.

B.

Create fine and closure scenarios to assess the impact on the program and create a contingency plan.

C.

Generate a delivery incentive contract with the selected fiscal expert to ensure on-time delivery of the revised financial statements.

D.

Assess the risk, incorporate it in the program’s risk management plan, and meet with the steering committee.

Buy Now
Questions 35

You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule

beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

Options:

A.

Avoidance

B.

Mitigation

C.

Transference

D.

Workaround

Buy Now
Questions 36

A program is in its last year of execution. The program manager will receive a performance bonus if executive leadership and the program steering committee determine that the program is a success.

How can the program manager justify receiving a performance bonus upon program closure?

Options:

A.

Update the business case analysis document indicating how each goal was attained.

B.

Prepare a financial framework to show effective financial management and alignment with profit metrics.

C.

Provide a report using the benefits management plan to demonstrate overall benefits realization.

D.

Conduct a customer satisfaction survey to show program success.

Buy Now
Questions 37

A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next?

Options:

A.

Define the program architecture and assign the benefits realization to the component projects.

B.

Complete the program setup to establish a firm foundation of support and approval for the program.

C.

Analyze lessons learned and historical information to validate the program’s expected outcomes.

D.

Continue to develop the high-level program road map.

Buy Now
Questions 38

You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?

Options:

A.

Parkinson's Law

B.

Law of Diminishing Returns

C.

80/20 Law

D.

Pareto's Law

Buy Now
Questions 39

A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project.

What should the program manager do next?

Options:

A.

Reassess the project manager’s credentials

B.

Assign a different project manager

C.

Review the skill requirements of the project

D.

Apply the competence assessment techniques to resolve the issue

Buy Now
Questions 40

You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

Options:

A.

Monitor and Control Program Scope

B.

Monitor and Control Project Performance

C.

Monitor and Control Program Schedule

D.

Manage Program Issues

Buy Now
Questions 41

Program manager B leaves the program and program manager A takes over the program responsibilities. Program manager A wants to ensure that all expected benefits of the program are realized.

What is used to assess the program cost/benefit justification?

Options:

A.

Program charter

B.

Benefits management plan

C.

Program business case

D.

Program scope statement

Buy Now
Questions 42

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.

What technique could the program manager use to gain more input from this project manager?

Options:

A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member.

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions.

D.

Create an online message board so team members can see and respond to everyone’s ideas.

Buy Now
Questions 43

A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations. The high-level scope of this transformation encompasses three main areas:

1.The technology area--assessing which technology/tooling should be retained for the target data center.

2.The policies and procedure area--aimed at establishing a common set of processes supporting the new way of delivering services.

3.The HR area--assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions.

You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase.

Which document should be present in your business case?

Options:

A.

A detailed plan showing dependencies among the constituent projects

B.

A comprehensive analysis of the different compensation packages offered in the 16 countries

C.

An inventory detailing all physical and logical components in place and the employees in scope

D.

A cost/benefit analysis of the different scenarios, presenting their respective contributions

Buy Now
Questions 44

You are the project manager of a construction project. You have to close a phase of the project. Which is the only technique (or tool) available in the Close Project or Phase process?

Options:

A.

Change control meetings

B.

Project management information system

C.

Expert judgment

D.

Observations

Buy Now
Questions 45

You are a program manager for an environmental program. The program involves installation of windmill across the country. During execution of the project, a stakeholder raises a change request to add an additional module with the existing installation. The program governance board has approved the change request. Which of the following is true regarding this scenario?

Options:

A.

The new Program Master Schedule is created containing the approved changes.

B.

Separate project is made to ensure that the approved changes are included in the program.

C.

Project charter is upgraded to include the approved changes in the program.

D.

The Program Master Schedule is updated to reflect the changes.

Buy Now
Questions 46

A program manager is concerned that a program will be unable to achieve its intended benefits.

How should the program manager handle this concern?

Options:

A.

Meet with the program management office (PMO) to review critical program success factors.

B.

Meet with the component project managers to reallocate resources within the program.

C.

Meet with the program stakeholders to determine if a reduction in program scope is acceptable.

D.

Meet with the component project managers to perform risk analysis.

Buy Now
Questions 47

In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

Options:

A.

Quality control

B.

Process improvement

C.

Scope verification

D.

Quality assurance

Buy Now
Questions 48

A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.

What should the program manager do NEXT?

Options:

A.

Consider the option to close out the key project

B.

Evaluate the program and re-baseline the objectives

C.

Assess the benefits and impact to the program

D.

Amend the risk register with the key project changes

Buy Now
Questions 49

The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program.

What should the program manager do next?

Options:

A.

Accept what the program sponsor requires and implement the changes.

B.

Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor the best option.

C.

Respond to the program sponsor if the program sponsor asks about it a second time.

D.

Present the risks and benefits of the changes to the program sponsor.

Buy Now
Questions 50

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Options:

A.

Resource breakdown structure

B.

Resource management chart

C.

Stakeholder analysis chart

D.

RACI chart

Buy Now
Questions 51

Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status?

Options:

A.

Change register

B.

Integrated change control

C.

Program Management Information System

D.

Change log

Buy Now
Questions 52

An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

Options:

A.

Accept the assignment, identify the skill gaps, and request training.

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified.

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager.

D.

Reject the assignment because of fear of failure and resulting negative career impact.

Buy Now
Questions 53

Which of the following statements are true regarding the Monitoring and Controlling Program Risks process? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Risk Monitoring and Control is an ongoing process for the life of the program.

B.

Planned risk responses should be continuously monitored for new and changing risks.

C.

Monitoring reduces the impact of risk by identifying, analyzing, reporting, and managing risks on a continuous basis.

D.

It is the process of selecting the most suitable response to reduce the threats to the program objectives.

Buy Now
Questions 54

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.

To ensure the realization of long-term benefits, what should the program manager use?

Options:

A.

Benefits register

B.

Benefits sustainment plan

C.

Benefits management plan

D.

Benefits transition plan

Buy Now
Questions 55

A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.

What should the program manager do next?

Options:

A.

Modify the program schedule to accommodate the risk.

B.

Incorporate the project risk into the program risk response strategy.

C.

Instruct the project manager to escalate the risk to the program sponsor.

D.

Ask the road construction project manager to manage the risk at the project level.

Buy Now
Questions 56

Which one of the following is NOT a component of the risk monitoring and controlling process?

Options:

A.

Executing risk response plans

B.

Completing quantitative risk analysis

C.

Tracking identified risks

D.

Determining if new risks have developed

Buy Now
Questions 57

Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?

Options:

A.

Risk management plan

B.

Risk register

C.

Activity list

D.

Activity list and attributes

Buy Now
Questions 58

You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any QUESTION NO:s the vendors may have about the project. What is this meeting called?

Options:

A.

Sales meeting

B.

Select sellers process

C.

Bidder conference

D.

Negotiations

Buy Now
Questions 59

A critical program for a company fails to delivers its intended benefits. The CEO and program sponsor are both held accountable and, ultimately, their employment is terminated by the board of directors.

What should the program manager do before formally closing the program?

Options:

A.

Update the benefits register.

B.

Establish a program management information system (PMIS).

C.

Share lessons learned with all program team members.

D.

Transfer all program documentation to the deputy program manager.

Buy Now
Questions 60

You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?

Options:

A.

59,340

B.

15,351

C.

861

D.

74,691

Buy Now
Questions 61

You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?

Options:

A.

Program governance

B.

Project management assets

C.

Enterprise environmental factors

D.

Organizational process assets

Buy Now
Questions 62

A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete.

What should the program manager do to understand the financial environment?

Options:

A.

Map costs to the expected benefits realization.

B.

Establish intermediate budget based on historical information.

C.

Establish program financial framework.

D.

Obtain intermediate funding from the executive sponsor.

Buy Now
Questions 63

What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?

Options:

A.

Sensitivity analysis

B.

Stakeholder analysis

C.

Monte Carlo simulation

D.

Force field analysis

Buy Now
Questions 64

You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?

Options:

A.

You must ensure that the project sponsor closes the project.

B.

You must ensure that that the projects within the program have been closed at the project level.

C.

You must close the project before operations closes the project.

D.

You must ensure that the program management team closes the project for the project manager.

Buy Now
Questions 65

Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

Options:

A.

Program charter

B.

Program risk register

C.

Program issue register

D.

Program scope statement

Buy Now
Questions 66

Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

Options:

A.

Net present value

B.

Future value

C.

Present value

D.

Cost-Benefit ratio

Buy Now
Questions 67

You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are telling Beth about the five process groups of project management and how they map to the progression of the project. Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?

Options:

A.

Monitoring and Controlling

B.

Planning

C.

Executing

D.

Procurement