Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

PfMP Portfolio Management Professional (PfMP) Questions and Answers

Questions 4

What can you tell about the following portfolio status, having CPI weight = 80% and SPI weight = 20%

Larger image

Options:

A.

Work is not performing well and outside of range

B.

Work is not preforming well but within range

C.

Work is progressing as planned and within range

D.

Work is progressing as planned but outside range

Buy Now
Questions 5

Roadmaps may be prepared to show different elements, and at the beginning they may not provide details of the various components. As a high-level plan at the portfolio level, the roadmap:

Options:

A.

Identifies internal and external dependencies

B.

Serves as a master schedule to show the timing of approved components

C.

Contains all the details of program and project roadmaps

D.

Serves to identify issues

Buy Now
Questions 6

Portfolio Reports are widely used as inputs and outputs to multiple processes throughout the Portfolio Life Cycle. Which of the following is NOT part of portfolio reports?

Options:

A.

None of the options

B.

Updates in resources, risks/issues, value/benefits, performance, and financials

C.

Governance Recommendations

D.

Feedback report to organizational strategy planning

Buy Now
Questions 7

One key artifact to review as the portfolio communications management plan is prepared is the:

Options:

A.

Portfolio management plan as it shows all elements in it have communications requirements

B.

Portfolio performance plan as it sets forth needed reports and their frequency

C.

Portfolio strategic plan since it shows the need for strategic alignment

D.

Portfolio benefits realization plan to determine reports on progress in benefit realization, transition, and sustainment

Buy Now
Questions 8

Assume you are new to your organization and you were hired specifically to help implement portfolio management in your new manufacturing company. Having worked in portfolio management for the past five years, you know it is a major culture change. It is definitely a challenge at your new company because:

Options:

A.

The organization basically has many operational activities, and only a few projects are under way

B.

The organization lacks a defined strategy

C.

The few projects that are under way are not interdependent

D.

Operational activities have continued without any major changes for years

Buy Now
Questions 9

As a portfolio manager, you realize the importance of communication for the success of a portfolio. You are now developing the portfolio management plan and are looking for the portfolio current risks status including high risks. Which of the following contains what you are looking for?

Options:

A.

Portfolio Management Plan

B.

Portfolio Reports

C.

Portfolio Charter

D.

Portfolio Process Assets

Buy Now
Questions 10

As part of the strategic alignment, you Identify prioritization criteria (e.g., legislative, dependencies, ROI, stakeholder expectations, strategic fit) using information gathering and analysis techniques in order to

Options:

A.

Create portfolio scenarios

B.

Understand the strategic priorities

C.

Create a basis for decision making

D.

Provide a guiding framework to operationalize the organizational strategic goals and objectives

Buy Now
Questions 11

The portfolio management process ensures the components are aligned to goals. However, it is driven by:

Options:

A.

Viability

B.

Value and benefits

C.

Organizational strategy and objectives

D.

Interdependencies and resource constraints

Buy Now
Questions 12

You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and demand is a recurring activity in the portfolio life cycle and results in changes in resource utilization and resource efficiency. What you use to perform this?

Options:

A.

Elicitation techniques, Value Scoring & Measurement Analysis, Benefits Realization Analysis

B.

Elicitation techniques, Communication Requirements Analysis, Stakeholder analysis

C.

Elicitation techniques, Capability & Capacity Analysis, PMIS

D.

Scenario Analysis, Capability & Capacity Analysis, Quantitative & Qualitative Analysis

Buy Now
Questions 13

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. You have just finalized managing the strategic change and you are expected to present the following documents:

Options:

A.

Portfolio Strategic Plan update, Portfolio Roadmap update, Portfolio Charter update, Portfolio Process Assets update, Portfolio update

B.

Portfolio Strategic Plan update, Portfolio Management Plan update, Portfolio Roadmap update, Portfolio Charter update, Portfolio Process Assets update, Portfolio update

C.

Portfolio Strategic Plan update, Portfolio Roadmap update, Portfolio Charter update, Portfolio Process Assets update, Organizational Process Assets update

D.

Portfolio Strategic Plan update, Portfolio Roadmap update, Portfolio Charter update, Organizational Process Assets update, Portfolio Management Plan update

Buy Now
Questions 14

During the portfolio lifecycle, components will be authorized, initiated, executed and closed accordingly. For authorizing the portfolio, as a program manager you will use which of the Which of the following tools and techniques?

Options:

A.

PMIS, Authorization techniques, Scenario Analysis

B.

PMIS, Authorization techniques

C.

Authorization techniques, Scenario Analysis

D.

PMIS, Authorization techniques, Review Meetings

Buy Now
Questions 15

Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently in the process of monitoring the portfolio to ensure alignment with organizational strategy and objectives and make governance decisions. What do you expect as an outcome to this?

Options:

A.

Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Organizational Process Assets update

B.

Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Portfolio Process Assets update

C.

Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Organizational Process Assets update, Portfolio Process Assets update

Portfolio Updates, Portfolio Strategic Plan updates, Portfolio Reports, Organizational Process Assets update, Portfolio Process Assets update

Buy Now
Questions 16

As a portfolio manager you try to use all the information available to you in order to get the best out of the existing information and to better plan and manage the portfolio. The Enterprise Environmental Factors are important and referenced throughout the portfolio life cycle. Which of the following is correct regarding their purpose and focus?

Options:

A.

Forecasts how and when the portfolio will deliver value to the organization

B.

High-level prioritization mapping of the portfolio

C.

Organization’s overall governance processes

D.

Establish communication requirements

Buy Now
Questions 17

Based on the data in the following table, your organization should pursue which component:

Options:

A.

Component 5

B.

Component 3

C.

Component 2

D.

Component 1

Buy Now
Questions 18

In a portfolio you have a continuous interaction between the portfolio and its components. You have to follow a lot of processes and procedures in order to reach a satisfactory result. In your opinion as a portfolio manager, who guides the portfolio team to follow the processes, metrics, and other procedures in the portfolio?

Options:

A.

Company's CEO

B.

Portfolio Management Office

C.

Portfolio Sponsor

D.

Portfolio Manager

Buy Now
Questions 19

While aggregating data from component reports in order to present the portfolio status to the governance board on an upcoming review meeting, which of the following is the most important thing to do?

Options:

A.

Disseminating the status to related stakeholders mentioned in communication management plan before the review meeting

B.

Updating the portfolio communication management plan

C.

Disseminating the status to all stakeholders before the review meeting

D.

Perform Communication Requirements Analysis

Buy Now
Questions 20

Initiatives in the companies aim to deliver values. For a portfolio, the value is delivered through a mix of components with similar strategic goals and objectives. Multiple components can contribute in the realization of the same organizational value. While managing the portfolio value, how do you depict the relationships between components in achieving value?

Options:

A.

Cumulative distribution

B.

Cause and effect relationships between the portfolio components that are needed to deliver planned benefits

C.

Outcome probability analysis

D.

Set realistic targets in line with stakeholder risk tolerances

Buy Now
Questions 21

With the introduction of new legislation in your company, anyone now is entitled to medical services regardless of whether or not they are employed or have any pre-existing health conditions. Your insurance company's executives have been tracking this legislation as it means significant changes for your company; many employers who obtained insurance through your company may go elsewhere for lower costs. Recognizing this legislation may lead to a loss of revenue, your company decided to merge with another insurance firm to obtain greater market share. This merger, though, means some existing projects may not be needed, and the workforce will be reduced by 20 percent, Such a significant change will impact how components are categorized in your portfolio leading to:

Options:

A.

The need for a re-constituted oversight group

B.

Portfolio rebalancing

C.

A requirement to update the portfolio management plan

D.

A new portfolio prioritization model

Buy Now
Questions 22

Two functional managers within your portfolio are arguing about one scarce resource, and each one is claiming that the resource should be assigned to them. What should you do as a portfolio manager in order to solve this issue?

Options:

A.

Perform a capacity and capability analysis and tender the recommendation on resource allocation to the governance board

B.

Sit with the two functional managers privately and let them agree on a solution

C.

Perform a capacity and capability analysis in order to allocate the scarce resource

D.

Do prioritization analysis and allocate the resource accordingly

Buy Now
Questions 23

Following a major organizational restructuring, new portfolios are currently being initiated. You have been assigned the position of portfolio manager on one of the major portfolios and are currently in strategic management. You are currently performing cost-benefit analysis. What is part of this analysis?

Options:

A.

Qualifies estimated costs and benefits and lists quantitative considerations of alternative portfolio components

B.

Quantifies estimated costs and benefits and lists qualitative considerations of alternative portfolio components

C.

Quantitative considerations of alternative portfolio components

D.

Qualifying estimated costs and benefits

Buy Now
Questions 24

As a portfolio manager you need to continuously balance the need and requirements with the available resources to maintain a balanced portfolio and portfolio resources in order to optimize delivery. One of your key stakeholders came to you asking to skip the manage supply and demand process as you have already prioritized and allocated resources through the strategic management and the governance processes. As a portfolio manager you should

Options:

A.

Raise this to the steering committee for approval

B.

Skip the step as the stakeholder is correct and you can always re-do the process as part of managing a strategic change

C.

Continue work and ignore the stakeholder's request as this stakeholder is known to resist change and hates collaboration

D.

Continue your work and perform the manage supply and demand process

Buy Now
Questions 25

Your company acquired another company. The sponsor asked you to check the other company's current inventory of work and see what could be added to your current portfolio. You have a meeting coming up to show the sponsor the portfolio dependencies. Which document should you be showing him?

Options:

A.

Portfolio Roadmap

B.

Portfolio Charter

C.

Portfolio Management Plan

D.

Portfolio Strategic Plans of both, your portfolio and the ones of the other company

Buy Now
Questions 26

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. While planning for risk management, multiple investment choice tools are used as part of the quantitative and qualitative analyzes. Which of the following tools determine the effect of changing the portfolio?

Options:

A.

Budget Variability

B.

Market Payoff variability

C.

Performance variability

D.

Trade-Off Analysis

Buy Now
Questions 27

You have been newly appointed as a portfolio manager and found out that your predecessor did not develop a Portfolio Risk Management plan as he thought that it is not necessary in the case where he has a risk register. One of your first activities was to develop the missing plan. To do this, you needed to consult with stakeholders in order to fetch risk information in order to identify risks and plan risk management. Which of the following inputs to this process will help you in identifying which stakeholders to analyze?

Options:

A.

Portfolio Process Assets

B.

Portfolio Communication Management Plan

C.

Portfolio Risk Management Plan

D.

Elicitation technique

Buy Now
Questions 28

It is rare for organizational leaders to have an in-depth knowledge of all the work under way in the portfolio, but it is needed for portfolio decision making. If you were asked to prepare such an inventory, it would:

Options:

A.

Require one-on-one interviews to ensure all work being done was revealed

B.

Be helpful to have a statement in writing from the CEO to describe why the inventory is important

C.

Serve as the starting point for the portfolio

D.

Require assistance and support from the EPMO

Buy Now
Questions 29

In a portfolio you have a continuous interaction between the portfolio and its components. The approach is top down when it comes to offering guidelines and approaches and becomes bottom up when the components report status and progress to the portfolio. What is the relation between the portfolio and portfolio components when it comes to defining the performance measures and targets (metrics)?

Options:

A.

Portfolio metrics are not related to component metrics, each is used at its own level

B.

Metrics are defined at portfolio level and given as guidelines to components in order to define their own metrics

C.

Portfolio metrics used at the portfolio level are the same used at components level

D.

Metrics are defined at components level and rolled up to the portfolio level

Buy Now
Questions 30

Portfolio management processes are performed in an environment broader than a portfolio; therefore, an organization-level implementation team supported by executive management, a governing body, and portfolio managers join forces to implement organization-level portfolio management processes. After Defining roles and responsibilities for portfolio management process implementation, what should be the FIRST next step?

Options:

A.

Define and deploy detailed portfolio management processes and provide training to staff and stakeholders.

B.

Changing business processes

C.

Developing the Portfolio Strategic Plan

D.

Communicate the portfolio management implementation plan

Buy Now
Questions 31

Assume your automotive company is new to formal portfolio management. It has had for years a strategic plan and tries to be first to market for new and improved features on its vehicles each model year. You were hired as the portfolio manager to provide a more disciplined approach for determining new products to pursue as well as existing ones that should be terminated. So far, you have set up an approach, established categories for the various components, and determined a method to rank and score new proposals for consideration. Now you are working to set up practices to follow to optimize the portfolio. In doing so, it is important to note that:

Options:

A.

The criteria to optimize the portfolio may be the same as that used in the scoring model

B.

A portfolio management information system should be set up

C.

Future investment requirements are a key criterion to consider

D.

Compliance with organizational standards cannot be overlooked

Buy Now
Questions 32

As a portfolio manager you will use a variety of artifacts and documents that will help you better manage the portfolio and better communicate progress and status with stakeholders. The roadmap is considered the most used document in the portfolio and eases your work being able to present the status on a single graphical representation. Early on during the portfolio lifecycle, you prepare the roadmap. An output of this process is

Options:

A.

Portfolio update, Portfolio Charter update, Portfolio Roadmap

B.

Portfolio Roadmap

C.

Portfolio update, Portfolio Roadmap

D.

Portfolio Charter update, Portfolio Roadmap

Buy Now
Questions 33

Assume you are the portfolio manager for a legacy software company. For many years, your company was one of the top five leaders in software development, but as newer and more efficient software was invented, it began to lose market share. Your company then found its services were needed as legacy systems were converted, especially since Cloud computing now is so popular. But it has lost revenues increasingly over the years. To gain market share and provide greater portfolio value, the executive team decided it should:

Options:

A.

Focus on channel partnerships

B.

Hire people with competencies in Cloud computing and enter this market

C.

Recognize change takes time but retrain employees to enhance customer satisfaction

D.

Focus on supplier value by partnering agreements

Buy Now
Questions 34

In managing strategic change, the portfolio manager performs stakeholder analysis in order to consider the changing requirements. Which of the following options is referenced in this case to provide guidance on the communication required to ensure successful change?

Options:

A.

Portfolio Strategic Plan

B.

Portfolio Management Plan

C.

Portfolio Roadmap

D.

Portfolio Charter

Buy Now
Questions 35

Due to a strategic change, multiple components on your portfolio have been terminated, leaving you with limited remaining funds coming from the terminated components. What should be your best course of action?

Options:

A.

Since the funds are limited, you can leave them with you and use them as equity protection for low probability and high impact risks

B.

Return the funds to the organization

C.

Since the remaining budget is limited, the portfolio manager can directly assign it to ongoing components that need a little push

D.

Re-activate one of the terminated components because you have additional budget

Buy Now
Questions 36

Risks perspectives differ within the organization between executive management, operations management, portfolio management and project/program management. Which of the following are common risk concerns across the organization?

Options:

A.

Reporting and data accuracy

B.

Organizational Integrity

C.

Time, cost and scope commitments

D.

Issues with Product development

Buy Now
Questions 37

Organizations pass by a strategic planning cycle on regular basis in order to align existing strategies, remove strategies and add new ones. When it comes to the implementation, which of the following options represents the activities through which the organizational strategies are implemented?

Options:

A.

Portfolio Components

B.

Portfolio Strategic Management

C.

Portfolio Components and Ongoing Operations

D.

Ongoing Operations

Buy Now
Questions 38

Assume your pork producing company finds that there is an over-abundance of pork products and competitors in the marketplace even though it has had to implement Hazard Analysis and Critical Control Point (HACCP) processes that are a regulatory requirement. Profits are lower than ever before in the history of the company. Management is changing the company's strategy to also focus on seafood products. You have been asked to complete a gap analysis to:

Options:

A.

Determine resource capacity

B.

Assess risks with this change

C.

Compare the current portfolio mix with that with this change

D.

Determine any requirements that must be addressed before the change is implemented

Buy Now
Questions 39

Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. As part of managing risks, the portfolio manager applies multiple analyzes and uses tools to help dealing with risks. What does the portfolio manager use to visualize risks impact on portfolio strategic objectives such as profitability?

Options:

A.

Sensitivity Analysis

B.

Risk Breakdown Structure

C.

Efficient Frontier

D.

Probability and Impact matrix

Buy Now
Questions 40

A big strategic change occurred at the organization level and has impacted multiple portfolios in the organization including yours. The CEO has asked you to prepare a presentation to depict the impact of this change on portfolio resources. Which of the following should you present in this case?

Options:

A.

Communication matrix and communication calendar

B.

Resource Histograms

C.

Benefits Realization

D.

Efficient Frontier

Buy Now
Questions 41

A major strategic change has occurred and you are managing the change at portfolio level. You are currently performing gap analysis and you receive information on a stakeholder that is extremely unhappy with how the change will be handled in your portfolio. What should be your best course of action?

Options:

A.

Perform prioritization analysis in order to position the change with relations to other changes

B.

Check the Communication Strategy matrix and ignore the stakeholder if he lies in the lower quadrants

C.

Escalate the issue to steering committee before any further damage happens

D.

Perform Stakeholder Analysis

Buy Now
Questions 42

Consider you have the following efficient frontier graph with multiple portfolios on it. Which portfolio do you choose?

Larger image

Options:

A.

Portfolio D

B.

Portfolio B

C.

Portfolio C

D.

Portfolio A

Buy Now
Questions 43

Assume at this point as the portfolio manager in your mattress company, you are activating portfolio components, updating portfolio reports, and documenting the decisions made at the recent Portfolio Governance Committee meeting as the company moves into new markets. You are therefore:

Options:

A.

Communicating decisions to all stakeholders

B.

Maintaining a decision log from the Committee meeting

C.

Updating the portfolio strategic plan

D.

Authorizing the portfolio

Buy Now
Questions 44

A big strategic change occurred at the organization level and has impacted multiple portfolios in the organization including yours. The sponsor has asked you to analyze the change and update the needed documents. You managed this change and are currently updating the Portfolio Management Plan. Which of the following are part of this update

Options:

A.

Portfolio Organizational Structure

B.

Communication and Performance Management

C.

Stakeholder Engagement

D.

All of the options

Buy Now
Questions 45

Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. Risk is part of project, program and portfolio management and has a different exposure in each and every one. Multiple risks have already been spotted in your portfolio and you are now identifying, assessing and developing risk response plans for them, in addition to monitoring and controlling them. What are you looking for? You were finding this hard at first however you asked the help from a senior portfolio manager and he redirected you to use

Options:

A.

Weighted Ranking and scoring techniques, Portfolio Component inventory, Categorization

B.

Weighted Ranking and scoring techniques, Quantitative & Qualitative Analysis

C.

Capability & Capacity, Weighted Ranking and scoring techniques, Graphical Analytical methods, Quantitative & Qualitative Analysis

D.

Weighted Ranking and scoring techniques, Graphical Analytical Methods, Quantitative & Qualitative Analysis

Buy Now
Questions 46

The Portfolio Management Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Management Plan purpose and focus?

Options:

A.

Identifies recipients for information associated with the portfolio management process

B.

Articulates the options, preferences, and factors that will be considered in a specific portfolio

C.

Describes the approach and intent of management in identifying, approving, procuring, prioritizing, balancing, managing, and reporting a portfolio

D.

Shows how and when the portfolio resources will be planned, balanced, and allocated to the portfolio components

Buy Now
Questions 47

After three months, you have a list of all the program, project, and ongoing work being done in your 500-person Division of your State Government Agency. With this list, the next step is to:

Options:

A.

Determine the prioritization model to follow

B.

Convene a meeting of the Portfolio Review Board

C.

Assess gaps in meeting the Agency's strategic objectives

D.

Prepare a portfolio performance plan

Buy Now
Questions 48

A recent development in the market gave your competitors a leading edge. Your company's CEO and executive members want to focus on new developments and gain the market leadership once again. You wanted to show the new structure to the Portfolio stakeholders and strategies have changed. As a portfolio manager, your best course of action is to perform a

Options:

A.

Capability and Capacity Analysis

B.

Scenario Analysis

C.

Gap Analysis

D.

SWOT Analysis

Buy Now
Questions 49

You are the portfolio manager for a large and complex portfolio with a low risk appetite. You are currently planning for risk management, multiple investment choice tools are used as part of the quantitative and qualitative analyzes. Which of the following tools focuses on pricing and sales forecast?

Options:

A.

Market Payoff variability

B.

Trade-Off Analysis

C.

Market Requirement Variability

D.

Budget Variability

Buy Now
Questions 50

One of the major resources on your portfolio is needed by two of the components at the same time. This resource has high technical knowledge and is aware of all the business needs. Which of the following tools and techniques can you use in order to solve this issue?

Options:

A.

Sequencing Techniques

B.

Capability and Capacity Analysis

C.

Scenario Analysis

D.

Interdependency Analysis

Buy Now
Questions 51

You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust performance management plan. What is the expected result from developing this plan?

Options:

A.

Portfolio Management Plan updates, Portfolio updates, Portfolio Reports, Enterprise Environmental Factors updates

B.

Portfolio Management Plan updates, Portfolio Process Assets updates

C.

Portfolio Management Plan updates, Organizational Process Assets updates, Portfolio Process Assets updates, Portfolio updates

D.

Portfolio Management Plan updates, Organizational Process Assets updates, Portfolio Reports, Enterprise Environmental Factors updates

Buy Now
Questions 52

When it comes to change, one of your junior portfolio managers came to you requesting your help to deal with the overwhelming strategic changes. He wants your assistance in solving the issue of continuous changes in the organization's objectives. What should be your advice to him?

Options:

A.

Change is a normal thing when it comes to portfolios, and he should act upon each strategic change in a quick manner in order to re-align his portfolio

B.

Not all strategic changes impacting his portfolio need to be taken care of; he should prioritize the change and only accept the ones with high priorities

C.

Help him to align his portfolio and manage it correctly in order to decrease the number and scale of changes

D.

Inform him that this is abnormal and that he should re-do the planning for his portfolio; even if it takes time and resources, but it will help him a lot for the rest of the portfolio life cycle

Buy Now
Questions 53

You are managing a portfolio linked to multiple business units and you set clear accountabilities from the beginning to avoid delays and to enhance the decision making process. Roles and Responsibilities are recorded in multiple portfolio documents. Where are the portfolio component managers roles and responsibilities stored?

Options:

A.

Specifically the Communication Management Plan

B.

Strategic Plan

C.

Portfolio Management Plan

D.

Portfolio Process Assets

Buy Now
Questions 54

Processes in the portfolio management layer interact with each others. For example, Manage Portfolio Information interacts with Provide Portfolio Oversight in order to store decisions made during the portfolio review meetings. Where are these decisions stored?

Options:

A.

Portfolio Management Plan

B.

Portfolio

C.

Portfolio Reports

D.

Portfolio Process Assets

Buy Now
Questions 55

Due to market technological changes, your company got impacted and was urged to revise its portfolios. You are currently revising your portfolio to determine the required changes in the component mix. Which of the following options shows a clear path from the "as-is" to the "to-be" vision?

Options:

A.

Portfolio

B.

Portfolio Charter

C.

Portfolio Strategic Plan

D.

Portfolio Roadmap

Buy Now
Questions 56

Having worked in portfolio management before, you are pleased you were selected to implement it and be the portfolio manager for your motorcycle company, well known throughout the world. As it is a new function, you worked with the Enterprise Program Management Office to ensure you had a complete inventory of the work in progress. Now as you prepared your various portfolio management artifacts, and have a Portfolio Review Board meeting upcoming in two weeks, sponsors will be proposing new components. This means:

Options:

A.

A master schedule of resource allocation is needed

B.

The meeting also should focus on reviewing existing components to see if they are aligned with current strategy

C.

People throughout the organization should know about this meeting and its decisions

D.

The meeting should have a set agenda, and each member should be contacted before it to learn of key issues

Buy Now
Questions 57

Assume you are creating a roadmap for your portfolio and will present it to key stakeholders and then to the Portfolio Review Board. You realize you will be adding additional detail to it, but you also believe its graphical format will be useful. In developing it, you decide to reference prioritization, dependencies, and organizational areas so you should consult the:

Options:

A.

Organization's strategic plan

B.

Portfolio strategic plan

C.

Portfolio charter

D.

Portfolio management plan

Buy Now
Questions 58

When we talk about portfolios, programs and projects, it is inevitable to mention the business value which is the sum of tangible and intangible assets of an organization, also known as the net quantifiable benefit. When it comes to business value, at which level of the organization is the delivery of Business Value optimized?

Options:

A.

Portfolio

B.

Project

C.

Program

D.

Operational

Buy Now
Questions 59

All measurements in a Portfolio are done in correspondence to Key Performance Indicators (KPIs), and defining those KPIs is essential and should be done by highly capable personnel. Which of the following is true regarding who prepares KPIs and which party approves them?

Options:

A.

Portfolio Management team and Portfolio Manager

B.

Portfolio Manager and Steering Committee

C.

Governance team and Executives

D.

Portfolio Management Team does both

Buy Now
Questions 60

You are the portfolio manager for a large county that comprises much of a major city in your country. The city also has a portfolio manager, and often you meet to discuss proposed initiatives to see if there are any dependencies. In your county, you established an approach to evaluate portfolio components to make judgments regarding their alignment and priority. In doing so, which of the following was especially helpful:

Options:

A.

Portfolio strategic plan

B.

Portfolio management plan

C.

Portfolio roadmap

D.

Portfolio charter

Buy Now
Questions 61

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. Risk Categories, criteria and probability and impact are updated as a result of Developing the Risk Management Plan. These updates are recorded in which of the following?

Options:

A.

Portfolio Management Plan updates

B.

Portfolio Process Assets updates

C.

Organizational Process Assets updates

D.

Portfolio Reports

Buy Now
Questions 62

Working to prepare the communications plan, a best practice to follow is to use the roadmap. By doing so, it:

Options:

A.

Shows the overall portfolio timeline, useful for determining the frequency of reporting

B.

Provides information about interdependencies that may affect objectives

C.

Emphasizes milestones and the timing of key benefits

D.

Shows applicable constraints

Buy Now
Questions 63

While managing portfolio communications, the portfolio manager needs to account for the communication needs of the component teams in order for them to stay in the loop of the big picture. Which of the following can be of interest to this group of stakeholders?

Options:

A.

To know about the portfolio changes, risks and issues that may affect their components

B.

To be informed regularly of the portfolio progress so they can adjust their work accordingly

C.

To be informed of all portfolio changes so they can assess which changes affect their components

D.

To know about the portfolio changes, risks and issues that may affect their components, and to do interdependency management in order to cover any dependent component's issues

Buy Now
Questions 64

Calculate the composite index for the following portfolio having CPI weight = 80% and SPI weight = 20%

Larger image

Options:

A.

0.9

B.

1.5

C.

1

D.

1.1

Buy Now
Questions 65

In a portfolio, data is an abundant asset, and managing the information aiming for a better decision making is critical. For this you use a variety of Quantitative and Qualitative analysis methods. Considering that you are currently working to quantitatively measure component values, however a few components have intangible benefits and can not be measured using quantitative analysis. How do you plan to proceed?

Options:

A.

Subject Matter Experts

B.

Benefits Realization

C.

Using assumptions

D.

Scoring models

Buy Now
Questions 66

As you work to determine which of four possible components to optimize the portfolio, assume you are using the internal rate of return as the key crite rion to make your recommendation. Only one new component can be added based on financial constraints. Each of the four potential components has benefits that support the strategic plan. Based on the following data, you recommend:

Options:

A.

Project A

B.

Program A

C.

Program B

D.

Project B

Buy Now
Questions 67

Portfolio Governance is important in a portfolio to maintain correct alignment, monitor and control performance and status, reshuffle the mix of components as found necessary, etc. Governance management includes which of the following processes?

Options:

A.

Develop Portfolio Communication Plan

B.

Optimize Portfolio

C.

Develop Charter

D.

Manage Supply & Demand

Buy Now
Questions 68

The governance role in oversight is abundant during planning in order to agree on multiple roles and responsibilities including those of a portfolio manager. The agreements are recorded in the meeting minutes and included as updates to

Options:

A.

Portfolio

B.

Portfolio Management Plan

C.

Portfolio Reports

D.

Portfolio Process Assets

Buy Now
Questions 69

Stakeholders are an integral part of the portfolio. The portfolio manager will work with the stakeholders to plan, execute and eventually deliver and close the portfolio. While developing the performance management plan, the portfolio manager plans a series of sessions with key stakeholders to define Key Performance Indicators (KPIs). What are these sessions collectively referred to in a portfolio?

Options:

A.

Capability and Capacity Analysis

B.

Communication Methods

C.

Elicitation Techniques

D.

Communication Requirements Analysis

Buy Now
Questions 70

Assume you work for a technology company that is publically owned, and the value of its stock is tracked daily by the CFO and is reported to the portfolio manager. Quarterly meetings are held with stockholders as the company went public through an Initial public offering (IPO) last year. These stockholders:

Options:

A.

Have different communications requirements than other stakeholders

B.

Typically receive information as to the portfolio health before each meeting

C.

Want to attend all Portfolio Review Board meetings

D.

Are considered external stakeholders

Buy Now
Questions 71

As soon as you complete the portfolio risk management plan, and you have been working on it now with a team, you realize you need to update some organizational process assets such as:

Options:

A.

Risk checklists

B.

Risk register

C.

Lessons learned

D.

Risk interview guide

Buy Now
Questions 72

In your telecom company, a number of criteria must be considered as you develop your approach to prioritize components in the portfolio. Your management insists that to be competitive the products must be first to market or the window of opportunity is lost with the result being not only lost revenues but also lost productivity. Another criterion to consider is:

Options:

A.

External dependencies

B.

Goals and objectives

C.

Customers

D.

Regulatory compliance

Buy Now
Questions 73

You are mid-way through your portfolio and you are approaching a major milestone where multiple components will be authorized for execution and implementation. For informed decision making, as a portfolio manager, you will be communicating reports that will be viewed and analyzed, and used as critical information for taking a decision for the authorization of components. After passing through the authorization process, multiple reports are generated and others are updated. What type of reports is generated from this process?

Options:

A.

Performance

B.

Resources

C.

Value

D.

Resources, Assets and governance decisions

Buy Now
Questions 74

When developing the charter, you will use multiple inputs and documents of which the portfolio Strategic Plan is one. How is the strategic plan used in this case?

Options:

A.

It is not an input to this process

B.

The Portfolio Structure and Portfolio Manager's Authorizations are copied from the Portfolio Strategic Plan as is and incorporated in the Charter

C.

It is updated based on the output of the Develop portfolio charter process

D.

The prioritization model is used as a decision framework to structure the portfolio components

Buy Now
Exam Code: PfMP
Exam Name: Portfolio Management Professional (PfMP)
Last Update: May 3, 2024
Questions: 495

PDF + Testing Engine

$130

Testing Engine

$95

PDF (Q&A)

$80