MSP-Practitioner MSP Practitioner, 5th edition Exam Questions and Answers
The programme is in the ‘design the outcomes’ process. The programme team is reviewing the programme brief and a revised version of the vision statement that has been prepared and validated in a workshop with key stakeholders.
What action should the programme manager and BCM take FIRST?
The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.
Is this an appropriate application of the ‘plan progressive delivery' process, and why?
The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
Three items of information have been recorded in the documents to support the 'decisions' theme. In which document should they be recorded?

The programme is in the 'identify the programme' process. The CEngO is concerned that the engineering department will not be able to deliver the proposed Engineering Department Work at the same time as supporting the research into new smart meters and water leak detection equipment. The programme board believes that the engineering department will be able to manage, if the programme is planned optimally.
Which role is MOST LIKELY to approve the programme board's recommendation?
At the start of the programme, the programme manager listed some design-related actions to be completed. Which role is MOST focused on each task?

It has been agreed with the sponsoring group that a risk review should be held before any of the new customer processes and web-based portal services are used by call centre staff to consider any risks before transition. This risk review needs to be documented appropriately.
Which role should approve the inclusion of this risk review in the relevant programme control document?
The Customer Processes Project has reported that the work to develop the integrated billing and accounting services is progressing according to plan. However, when the system was tested, the system performance was very slow and there are errors that were not previously identified. The programme manager is concerned about the possible impact of this inaccurate reporting.
Which type of data gathering should be improved, and why?
During Tranche 1, the Call Centre Manager had played an active role in the programme as a BCM. However, at the end of the tranche, it was decided that they were not required during Tranche 2. In addition, the CTO was appointed as a new BCM for Tranche 2.
Which principle is being applied by the ‘organization’ theme, and why?
The programme is in the middle of Tranche 2 and a new SRO has been appointed. In order to understand the current status of the programme, the SRO has asked for a health check to be carried out. The health check was not in the assurance plan, and there is no budget available to pay for an external auditor. As a result, the programme manager has agreed with the SRO that a senior member of the portfolio office, who is acting as the programme office lead, should complete the health check instead.
How well does this action by the programme manager apply the ‘assurance' theme, and why?
Which activity from the Smart Meter Programme should be delivered using a continual improvement approach?
The programme manager has produced a rough estimate of costs based on the recently completed roll-out of smart metered services to electricity and gas customers.
Is this an appropriate application of the ‘identify the programme' process, and why?
The ‘identify the programme’ process has started. The programme manager organized a meeting to discuss the work being planned for the ‘design the outcomes’ process. It was agreed that the Call Centre Manager and the CEngO should be included in future planning meetings.
Which theme is being applied?
There is a risk that the utilities market is changing, with green energy solutions becoming more attractive to customers. As UU does not currently offer this type of green energy, the benefits gained from cross-selling electricity and gas to current water customers may be overestimated.
Which activity is relevant in the ‘plan’ phase of the Plan-Do-Check-Act (PDCA) cycle?
The Training Project has included some interactive games in the training materials. This is to help engineering staff members share ideas and experiences during the training of how to apply the new processes. However, the CEngO thinks that the engineering staff members will find this approach rather childish as they are very experienced and normally work independently. As a result, the CEngO has asked for the games to be removed from the training materials.
Is the CEngO's request an appropriate application of the 'knowledge' theme, and why?
The programme is now in the ‘close the programme’ process. All the planned training from the Training Project has been completed. However, it is too early to tell how much impact the training will have on service to customers. This will need to be monitored during normal business operation.
Which theme is MOST relevant to this situation?
The programme is in the ‘deliver the capabilities’ process. When the Call Centre Rationalization Project is complete, it will be important to inform all staff and customers. This is because there will be new contact details for the new single call centre with longer opening hours. The programme manager has planned for both internal and external announcements to publicize this.
Which theme is MOST relevant to these planned activities?
When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?
The programme is in the ‘plan progressive delivery' process. The programme manager has recommended that the funds for the HR Work should come from a different source to the funding for the project work.
During which activity is the SRO responsible for providing formal approval for this recommendation?
The programme is in the ‘design the outcomes’ process. One risk to the programme is that new and improved meter technology may be developed during implementation. This risk has been assessed as high probability and high impact and is therefore a high priority. The initial delivery approach proposes a phased roll-out of the meters so that the programme can exploit any new technology that emerges. The CTO has been appointed as the owner of this risk.
Is this appointment an appropriate application of the identify and prioritize risks’ activity, and why?
In delivering the capability, which role is responsible for aligning projects with programme objectives?
The programme is in the ‘deliver the capabilities’ process in Tranche 3. Engineering staff have been installing the new water meters. As a result, fewer staff than planned have attended the first few training courses, delivered as part of the Training Project. If this trend continues, realization of the reduced costs could be delayed. The programme manager has asked the CEngO to schedule this routine work so that the engineers can attend training courses in the future.
Which theme is MOST relevant to this situation, and why?