Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

PMI-200 PMI Agile Certified Practitioner (PMI-ACP)® Questions and Answers

Questions 4

Team A is producing 61 points per iteration and Team B is producing 20 points per iteration. Team A has more senior engineers. A manager demands that Team B match Team A’s points in the next iteration. Based on this information, it is reasonable to tell the manager that:

Options:

A.

it is impossible to compare two separate teams on points alone.

B.

Team B’s points will match Team A if Team B gets more senior engineers.

C.

Team B must have help self-organizing so their points match Team A.

D.

Team B’s points will increase if the Product Owner becomes more involved.

Buy Now
Questions 5

What is used to provide a simple medium for gathering basic information about stories, recording high-level requirements, developing work estimates, and defining acceptance tests?

Options:

A.

Story card

B.

Burndown chart

C.

Retrospective

D.

Storyboard

Buy Now
Questions 6

Estimating costs for an Agile project starts with which of the following types of meetings?

Options:

A.

Project Retrospective

B.

Steering Committee

C.

Release Planning

D.

Sprint Planning

Buy Now
Questions 7

Which tool allows the Product Owner to focus on providing the greatest value and Return on Investment (ROI) to the organization?

Options:

A.

Burn up chart

B.

Product Backlog

C.

Affinity estimate

D.

Cost Benefit Analysis (CBA)

Buy Now
Questions 8

Which type of estimate refers to estimating a story based on its relationship to one or more other stories?

Options:

A.

Algorithmic

B.

Computational

C.

Triangulating

D.

Rules of Thumb

Buy Now
Questions 9

Which of the following best describes a core belief of Agile?

Options:

A.

The best customer feedback comes near the end of the project when there is working software to review.

B.

Project status can be gauged by frequently reviewing completed milestones as reflected in the plan.

C.

Working solutions are the most accurate way of seeing the progress of the effort.

D.

Unique skill sets are harnessed when team members play different roles on a project.

Buy Now
Questions 10

During iteration planning, the team is discussing the design for a user story. A team member states that a design document should be started since the system is complex in nature. Another team member responds that in Agile there is no documentation. How should the ScrumMaster respond?

Options:

A.

Agree that documentation should be avoided, since it slows the progress of the team.

B.

Explain that interactions are valued over documentation, but documentation is not forbidden.

C.

Ask the manager if the technical processes mandate that designs be documented.

D.

Ask the Product Owner if it is acceptable for the resources to spend time on documentation.

Buy Now
Questions 11

The three questions asked at every Daily Scrum should be: “What have you accomplished since the last Daily Scrum?”;”What are you planning to accomplish between now and the next Daily Scrum?”; and:

Options:

A.

What is preventing you from completing your work effectively?

B.

What is yourcurrent performance velocity?

C.

Are you on track to complete assigned story points?

D.

How many story pointswill you complete this sprint?

Buy Now
Questions 12

Which of the following is critical for the success of distributed Agile teams?

Options:

A.

Cost containment

B.

High volume of communication

C.

Shared knowledge

D.

Culture of collaboration

Buy Now
Questions 13

On a project using eXtreme Programming (XP), a customer test is a:

Options:

A.

Technique to determine if the software is easy for customer use.

B.

Tool for a customer to verify the business requirements.

C.

Technique to determine if a customer will use a software feature.

D.

Test for determining if a customer will purchase the product.

Buy Now
Questions 14

In a Lean Software Development environment, the Project Leader strives to eliminate:

Options:

A.

Work in Process (WIP) and bugs.

B.

Delays and building what is not needed.

C.

Defects and features with low value stream values.

D.

Poor requirements and changing scope.

Buy Now
Questions 15

A common estimation unit for Agile projects is:

Options:

A.

Lines of code.

B.

Function points

C.

Story points.

D.

Use-case points.

Buy Now
Questions 16

What key benefits might stakeholders realize from an Agile approach?

Options:

A.

The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet daily

B.

The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments

C.

Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting

D.

The team’s flexibility to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments

Buy Now
Questions 17

Which technique is used by a project team to estimate the amount of work that can be done per iteration?

Options:

A.

Velocity measurement

B.

Relative prioritization

C.

Planning Poker

D.

Release planning

Buy Now
Questions 18

The process of reviewing, testing, and accepting implemented features is called:

Options:

A.

Retrospective.

B.

Stakeholder review.

C.

Scope verification.

D.

Iteration planning.

Buy Now
Questions 19

For the best results in an Agile project, customers should:

Options:

A.

set priorities and identify product features.

B.

interview new team members for fit.

C.

approve development plans and tasks.

D.

set sprint and release schedules.

Buy Now
Questions 20

What is one of the benefits of incremental delivery?

Options:

A.

Value is delivered more quickly, as software can be released after every iteration.

B.

More customers can be handled simultaneously, as each regularly receives a delivery.

C.

Fewer bugs are introduced, as code is delivered to users more frequently.

D.

Costs are reduced, as less verification is required to regression test each iteration.

Buy Now
Questions 21

For a "caves and commonroom arrangement, the most appropriate prerequisite is that the people in the room must be working on:

Options:

A.

Whatever they choose.

B.

Individual projects.

C.

The same set of multiple projects,

D.

The same project.

Buy Now
Exam Code: PMI-200
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)®
Last Update: May 8, 2024
Questions: 145

PDF + Testing Engine

$130

Testing Engine

$95

PDF (Q&A)

$80