Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

IDPX Interior Design Professional Exam Questions and Answers

Questions 4

Changes made to the contract documents during the bid (tender) process are documented in a(n)

Options:

A.

Bulletin

B.

Addendum

C.

Change order

Buy Now
Questions 5

Earthquakes and the loads caused by winds are examples of

Options:

A.

Live loads

B.

Dead loads

C.

Static loads

D.

Dynamic loads

Buy Now
Questions 6

A storage area has been approved as an accessory occupancy within a retail store. The means of egress requirements are based on which occupancy type?

Options:

A.

Storage (S)

B.

Business (B)

C.

Mercantile (M)

Buy Now
Questions 7

While on site, the designer notices that the glazing subcontractor is installing the storefront system in the wrong finish. What should the designer do?

Options:

A.

Report the discrepancy in a memo to the contractor and client

B.

Reach out to the glazing supplier to find out which finish was ordered

C.

Explain the issue at the next owner, architect, contractor (OAC) meeting

D.

Tell the subcontractor to stop their work and explain the issue to the contractor

Buy Now
Questions 8

Which wall assembly would produce the highest STC rating?

Options:

A.

2x4 studs at 16" [406 mm] OC, 2 layers of 5/8" [15 mm] gypsum board on each side, full batt insulation

B.

2-1/2" [64 mm] metal studs at 16" [406 mm] OC, 1/2" [13 mm] gypsum board on each side, full batt insulation

C.

3-1/2" [89 mm] metal studs at 16" [406 mm] OC, 5/8" [15 mm] gypsum board on each side, full batt insulation

Buy Now
Questions 9

The role of the project manager includes

Options:

A.

selecting a project team, establishing and overseeing the budget, and coordinating withconsultants

B.

preparing preliminary designs, coordinating with consultants, and developing proposals and contracts

C.

serving as the primary client contact, developing proposals and contracts, and producing project specifications

D.

establishing and overseeing the budget, producing schematic designs, and serving as the primary client contact

Buy Now
Questions 10

A designer is hired to update a community clubhouse in a private residential subdivision. During the pre-design phase, the designer interviews stakeholders to gather information about the use of the clubhouse. Who is the MOST important stakeholder?

Options:

A.

HOA

B.

residents

C.

building manager

Buy Now
Questions 11

When reviewing the general contractor’s pay application, the designer should approve the amount for

Options:

A.

Utilities and property taxes

B.

Subcontractors’ travel expenses

C.

Delivered materials stored on-site

Buy Now
Questions 12

Which of the following should be installed at regular intervals to avoid cracking of a GWB ceiling from building structural movement?

Options:

A.

J mold

B.

U channel

C.

Control joint

D.

Elastic sealant

Buy Now
Questions 13

Who should be consulted when specifying materials and finishes to ensure maintenance adherence?

Options:

A.

Tenant

B.

Facility manager

C.

General contractor

Buy Now
Questions 14

What should be evaluated by the design team in advance of a project kickoff with clients and stakeholders?

Options:

A.

Cost analysis and value engineering

B.

Site availability and schedule impacts

C.

System performance and subcontractor availability

Buy Now
Questions 15

Which item causes the MOST issues when planning for systems workstations in an office space?

Options:

A.

The workstation cost is too expensive for the client’s budget

B.

The thickness of the panels was not considered when maintaining clearances

C.

The height of the panels is too low to reduce sound from traveling between workstations

D.

The electrical outlets are not maintained at the correct height to accommodate equipment

Buy Now
Questions 16

Referencing the table below, which two spaces could be combined as part of the space needs program?

Space

Days in Use

Hours of Use

Banquet

Friday to Sunday

10am to 10pm

Classroom

Monday to Friday

8am to 12pm

Art Gallery

Wednesday to Sunday

11am to 7pm

Exhibition Hall

Friday to Tuesday

5pm to 10pm

Options:

A.

art gallery and banquet

B.

classroom and art gallery

C.

banquet and exhibition hall

D.

exhibition hall and classroom

Buy Now
Questions 17

What are the PRIMARY components of sustainability?

Options:

A.

global, wellness, and universal

B.

LEED, SMaRT, and Green Globes

C.

eco-friendly, non-toxic, and organic

D.

environmental, social, and economic

Buy Now
Questions 18

What spaces are typically grouped together in a multistory building’s service core?

Options:

A.

lobby, elevator, corridors, stairs

B.

stairs, elevator, toilet rooms, supply closet

C.

kitchen, toilet rooms, loading docks, laundry

D.

janitors closets, electrical closets, data rooms, HVAC

Buy Now
Questions 19

When the owner/contractor agreement is executed, which documents specifically form the contract documents?

Options:

A.

drawings, specifications, instruction to bidders

B.

drawings, specifications, addenda

C.

specifications, addenda, bid (tender) solicitation

D.

addenda, bid (tender) solicitation, instruction to bidders

Buy Now
Questions 20

What rating is used to determine a material’s sound absorption?

Options:

A.

CAC

B.

STC

C.

NRC

D.

UL (CSA)

Buy Now
Questions 21

Which of the following factors in daylighting design determines the depth of light penetration into the space?

Options:

A.

window height

B.

shading device

C.

glazing material

D.

reflective surface

Buy Now
Questions 22

Which of the following is part of an active system for fire protection?

Options:

A.

Area of refuge

B.

Means of egress

C.

Protected stairwells

D.

Pre-action sprinklers

Buy Now
Questions 23

The design for a new corporate office has wood wall panels with aluminum reveals. What sequence below will result in the MOST efficient installation?

Options:

A.

Installation of panels then reveals

B.

Installation of base then wood wall panels

C.

Installation of inner wall blocking then reveals

D.

Installation of reveals then inner wall blocking

Buy Now
Questions 24

Administration, marketing, and management expenses in a design firm are examples of

Options:

A.

Indirect labor

B.

Billable hours

C.

Direct materials

D.

Facility overhead

Buy Now
Questions 25

The purpose of shop drawings is to

Options:

A.

Analyze the fabrication method

B.

Approve completeness of the details

C.

Check conformance with the design intent

Buy Now
Questions 26

What is the PRIMARY benefit for incorporating a design firm?

Options:

A.

Limit liability of the principals

B.

Shelter company’s profits from taxes

C.

Enhance company availability to credit

D.

Protect company from negligence suits

Buy Now
Questions 27

What would be included as part of a fire separation (fire assembly)?

Options:

A.

Dampers

B.

Operable window

C.

Low flame-spread rating

D.

Flame retardant wallcovering

Buy Now
Questions 28

The PRIMARY reason for the submittal process during Contract Administration is for the designer to

Options:

A.

Confirm the quantity of material to be ordered

B.

Alter product specifications prior to the final order

C.

Check for conformance with the contract documents

D.

Verify that the dimensions conform to the site conditions

Buy Now
Questions 29

A project is running behind schedule and over budget. What should the designer do FIRST?

Options:

A.

Review and determine budget cuts with the client

B.

Simplify installation methods to save both cost and time

C.

Contact the client to discuss the problem as soon as possible

D.

Rank construction priorities and complete the critical path elements first

Buy Now
Questions 30

With regard to electrical systems, one responsibility of an interior designer is to provide the

Options:

A.

Quantity of junction boxes for light fixtures

B.

Quantity of conduit for wiring under carpet

C.

Location of electrical panel and circuit breakers

D.

Location of power required for built-in equipment

Buy Now
Questions 31

What modification would increase the available time for occupants to exit a space during a fire?

Options:

A.

Change the ceiling type

B.

Install a sprinkler system

C.

Increase the number of exits

D.

Specify finishes with higher flame-spread rating

Buy Now
Questions 32

A designer has a contract with a client to provide complete contract documents for a tenant build-out. Specifying FF&E is beyond the scope of the contract. The designer makes some general FF&E recommendations to show a systems furniture layout as required by the local code officials. The furniture comes in over the client’s previously undisclosed budget. What should the designer do?

Options:

A.

Suggest that the client purchase directly from the manufacturer

B.

Meet with the client and furniture provider to resolve the problems

C.

Research alternate furniture options to bring the budget back in line

D.

Let the client and the furniture provider work out the budget problems

Buy Now
Questions 33

Which of the following would allow for ease of reconfiguration of power and data for open office environments?

Options:

A.

access flooring

B.

poke-through system

C.

cellular floor systems

D.

underfloor steel ducts

Buy Now
Questions 34

The MOST appropriate use for low voltage wiring is

Options:

A.

receptacle circuits and switching

B.

thermostat and communication wiring

C.

appliance circuits and equipment wiring

D.

television circuits and audiovisual wiring

Buy Now
Questions 35

A designer who is working on a non-profit community center in a historic building has met individually with the project’s benefactor, the community center’s board, the center’s director and staff, local community members, the municipality’s historic preservation committee, and the retained contractor. Which of the following is the designer’s GREATEST challenge?

Options:

A.

Balancing the various stakeholders’ preferences

B.

Working with the contractor towards a unique design

C.

Balancing material and finishes that have historical significance

D.

Working with the community towards a concept that will use the space as desired

Buy Now
Questions 36

Which of the following installations would require a structural engineer to be involved?

Options:

A.

A wall-mounted furniture workstation

B.

A demountable partition wall

C.

A non-load-bearing interior wall

D.

An operable partition wall

Buy Now
Questions 37

During construction, the general contractor notices conflicting information between the construction drawings and the specifications. The FIRST step the contractor should take is to

Options:

A.

issue a change order

B.

make an interpretation

C.

notify the owner of the discrepancy

D.

notify the designer of the discrepancy

Buy Now
Questions 38

In new construction, when would be the appropriate time to schedule an on-site review of wall blocking for an artwork package?

Options:

A.

when the artwork arrives on site

B.

before gypsum board is installed

C.

during a preconstruction meeting

D.

before electrical systems are installed

Buy Now
Questions 39

When developing a design, which BEST unifies the project and provides specific direction for the design?

Options:

A.

Feasibility studies

B.

Concept statement

C.

Space allocation studies

D.

Programming and research

Buy Now
Questions 40

An interior designer was contacted by their client shortly after occupancy and move-in, complaining that lights in private offices and some spaces were turning off automatically after a few minutes. What is the BEST next step?

Options:

A.

Inform the client that they can disconnect the occupancy sensors

B.

Reconfigure the spaces with issues to better improve occupancy sensor line-of-sight

C.

Have the occupancy sensors replaced with manual switches at the owner’s expense

D.

Contact the installer to check that the occupancy sensors are set to the maximum time limit

Buy Now
Questions 41

A new hospital includes a cafeteria and a 60-person conference room. Which occupancy classifications would apply?

Options:

A.

assembly and business

B.

assembly and industrial

C.

institutional and business

D.

institutional and assembly

Buy Now
Questions 42

Where open risers are permitted in a commercial space, what is the MAXIMUM clear space between risers?

Options:

A.

3" [76 mm]

B.

4" [102 mm]

C.

7" [178 mm]

D.

11" [279 mm]

Buy Now
Questions 43

A designer is planning an office remodel where the tenant is relocating their existing microwaves. After project completion, the tenant is disappointed to discover the outlets for the microwaves were installed at the incorrect height. What could the designer have done to prevent this?

Options:

A.

Coordinated the outlet heights with the electrical drawings

B.

Requested an appliance submittal from the general contractor

C.

Scheduled a site walk with the electrical contractor during installation

D.

Verified the equipment specifications with the microwave manufacturer

Buy Now
Questions 44

Which consultant should be contacted to correct omissions on the drawing shown below?

IDPX Question 44

Options:

A.

Electrical

B.

Plumbing

C.

Structural

D.

Fire protection

Buy Now
Questions 45

The installation of which material has the lowest VOC emissions?

Options:

A.

epoxy paint

B.

ceramic tile

C.

vinyl wallcovering

Buy Now
Questions 46

The office manager for a client signed a contract for design services. However, the owner refuses to pay the design fee because the office manager did not have the authority to sign the contract. This is an issue of

Options:

A.

mutual assent

B.

breach of contract

C.

contractual capacity

D.

designer responsible disclaimer

Buy Now
Questions 47

While visiting a job site, it is observed that the junction boxes for wall sconces are mounted at thewrong height. What should be done?

Options:

A.

Tell the electrical contractor on-site to move them and follow up with written documentation

B.

Issue a proposal request to the general contractor to verify the cost for having them relocated

C.

Notify the general contractor’s superintendent on-site and follow up with written documentation

D.

Wait until construction has been completed and then note the problem on the punch (deficiency) list

Buy Now
Questions 48

What floor finish would BEST support a passive solar design strategy in a hot arid climate?

Options:

A.

vinyl

B.

wood

C.

carpet

D.

concrete

Buy Now
Questions 49

In an existing non-sprinklered multi-tenant building, a client will be converting a suite from a bank into a restaurant serving more than 49 persons. What fire rating is REQUIRED between the new tenant and the existing adjacent insurance office?

Options:

A.

0

B.

1

C.

2

D.

3

Buy Now
Questions 50

How are the actual riser and tread dimensions for a set of stairs determined?

Options:

A.

Divide floor opening by desired tread dimension

B.

Divide floor opening by desired riser dimension

C.

Divide floor-to-floor height by minimum riser dimension

D.

Divide floor-to-floor height by maximum riser dimension

Buy Now
Questions 51

What is the MOST effective construction method to help mitigate impact noise from high heels on ahard floor surface?

Options:

A.

Higher NRC in the ceiling material

B.

Framed-in upholstered wall panel system

C.

Resilient underlayment in the floor assembly

D.

Blanket insulation between joists and trusses

Buy Now
Questions 52

Plumbing traps are an essential feature of sanitary drains because they prevent

Options:

A.

the backflow of wastewater

B.

the backflow of sewer gases

C.

the contamination of water supply with wastewater

D.

the contamination of water supply with sewer gases

Buy Now
Exam Code: IDPX
Exam Name: Interior Design Professional Exam
Last Update: Sep 11, 2025
Questions: 175

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99