Which of the following product risks would be most effectively addressed just by static testing? 3 credits
The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits
Which of the following would be the TWO most appropriate examples of entry criteria documented in the system integration test plan? 2 credits
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
In addition to introducing the new team member, you have decided to raise motivation. Which of the measures listed below would be the best measure to take in order to increase the motivation of the team? 2 credits
Which of the following team roles would be most appropriate to enhance the team and why? 2 credits
You are considering involving users during test execution. In general, what is the main reason for involving users during test execution? 1 credit
Based on the information given in the scenario, identify how the team could be improved most effectively? 2 credits
A number of options have been suggested for the level of independence to be employed for the testing on the next project, and are shown below.
i. External test specialists perform non-functional testing.
ii. Testing is outsourced.
iii. Testing is carried out by the developer.
iv. A separate test team carries out the testing.
v. Testing is performed by the business.
vi. Testing is performed by a different developer.
Which of the following orders the above in a correct order of independence? 1 credit
Which of the following is a project risk mitigation step you might take as test manager? 1 credit
Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
Which test management control option is most appropriate to adopt under these circumstances? 2 credits
Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit
You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations? 3 credits
Which of the following is a consideration when deploying test execution tools? [K1]
During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below. 1 credit
Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement? 1 credit
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)
Part of the testing strategy indicates that you are going to be using systematic test design techniques. Your manager has asked that you present the main advantages of using these techniques at the next board meeting. Identify THREE main benefits of using systematic test design techniques within this company. 2 credits (for 2 out of 3 correct 1 credit)
You have been asked to write a testing strategy for the company. Which statement best explains how risk can be addressed within the testing strategy? 1 credit
In addition to risk, identify TWO other components of a testing strategy. 1 credit
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit
As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria? 1 credit
What would be a test approach regarding the test design techniques to be applied that would fit an item with the highest risk? 2 credits
A system is being enhanced to simplify screen navigation for users.
Which of the following does NOT reflect structural testing?
Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV. Defect trend (number of defects found per test run over time
You have been given responsibility for the non-functional testing of a safety-critical monitoring & diagnostics package in the medical area. Which of the following would you least expect to see addressed in the test plan? 1 credit
A test log is one of the documents that need to be produced in this domain in order to provide evidence of testing. However, the level of detail of test logs can vary. Which of the following is NOT an influencing factor for the level of detail of the test logs being produced? 1 credit
Select THREE issues from the options provided that should at least be raised. 1 credit
Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit
Why might a RAD approach be a better option for the test manager rather than a sequential development? 2 credits
A test assessment has been carried out using the selected model as a reference framework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change. Which of the following would be the most important selection criterion for defining the priority of the recommendations? 2 credits
Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2 credits
Model characteristics:
Which THREE of the below mentioned characteristics relate to TMMi? 1 credit