Big Black Friday Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

CDT Construction Documents Technologist Questions and Answers

Questions 4

Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?

Options:

A.

Warranty of title

B.

Implied warranty of merchantability

C.

Purchase warranty

D.

Extended warranty

Buy Now
Questions 5

Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?

Options:

A.

Conformed set

B.

Record set

C.

Change order log

D.

Request for information documents

Buy Now
Questions 6

Who is responsible for job site security?

Options:

A.

Owner

B.

Architect/engineer

C.

Contractor

D.

Construction manager

Buy Now
Questions 7

Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?

Options:

A.

Contractor

B.

Material supplier

C.

Owner

D.

Subcontractor

Buy Now
Questions 8

In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?

Options:

A.

Construction documentation

B.

Design

C.

Project conception

D.

Programming

Buy Now
Questions 9

During design, in a design-build delivery method, what is the design-builder responsible for delivering to the owner?

Options:

A.

Submittals

B.

Record documents

C.

Geotechnical reports

D.

Construction documents

Buy Now
Questions 10

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

Options:

A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Buy Now
Questions 11

What project scheduling technique involves setting the target date of building occupancy and then working backwards to establish preceding milestone dates?

Options:

A.

Methods technique

B.

Critical path method

C.

Front end loading

D.

Schedule of values

Buy Now
Questions 12

What is the procedure for guarding against defects and deficiencies before and during the execution of the work?

Options:

A.

Quality assurance

B.

Quality control

C.

Quality management

D.

Quality monitoring

Buy Now
Questions 13

There are over 3,500 different grades of steel. The amount of carbon, level of impurities, and additional elements all contribute to what grade steel is classified as in building projects. Therefore, which of the following is the method of specification writing used to limit lengthy descriptions of materials?

Options:

A.

American National Standards Institute (ANSI)

B.

Descriptive

C.

Performance

D.

Reference standard

Buy Now
Questions 14

Which of the following is a format that standardizes the way text is arranged in specification pages so that it is best suited for easy reading and rapid reference?

Options:

A.

SectionFormat®

B.

PageFormat

C.

MasterFormat®

D.

UniFormat®

Buy Now
Questions 15

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?

Options:

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Buy Now
Questions 16

The general principle to which architects and engineers have a duty to clients and society at large to practice is defined as "taking the same course of action as another reasonable and prudent architect or engineer in the same geographic area would have taken under the same circumstances" is known by what term?

Options:

A.

Professional standard of care

B.

Due diligence

C.

Performance based requirement

D.

Spearin doctrine

Buy Now
Questions 17

What determines the responsibilities of the participants on the project team?

Options:

A.

Size of the project

B.

Nature of the project

C.

Cost of construction

D.

Project delivery type

Buy Now
Questions 18

Which entity maintains project record documents?

Options:

A.

Architect/engineer (A/E)

B.

Contractor

C.

Owner

D.

Owner or A/E

Buy Now
Questions 19

Which of the following is NOT a method of specifying?

Options:

A.

Perspective

B.

Proprietary

C.

Performance

D.

Reference standard

Buy Now
Questions 20

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Buy Now
Questions 21

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Buy Now
Questions 22

What does the Integrated Project Delivery (IPD) process involve?

Options:

A.

A collaborative, integrated, and productive team composed of key project participants

B.

Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members

C.

Responsibility silos for greater efficiencies, leading to project success

D.

Segregat knowledge gathered as needed with paper-based communications to team members

Buy Now
Questions 23

Which of the following statements best describes stakeholder and participant interest in a project?

Options:

A.

Participants have direct interest in the project while stakeholders have indirect interest

B.

Stakeholders have direct interest in the project while participants have indirect interest

C.

Both stakeholders and participants have direct interest in the project

D.

Both stakeholders and participants have indirect interest in the project

Buy Now
Questions 24

Which party is usually required to maintain record drawings during the project according to the Project Delivery Practice Guide?

Options:

A.

Architect

B.

Contractor

C.

Owner

D.

Authority having jurisdiction

Buy Now
Questions 25

The three types of commissioning include systems and equipment commissioning, building envelope commissioning, and what other process?

Options:

A.

Mechanical commissioning

B.

Facility commissioning

C.

Process commissioning

D.

Total project commissioning

Buy Now
Questions 26

What is Leadership in Energy and Environmental Design® (LEED®)?

Options:

A.

A set of sustainable standards with measurable recognized categories for a project

B.

A formula for determining a sustainable classification

C.

A system of prioritizing sustainable projects

D.

Standardized structure for organizing sustainable information

Buy Now
Questions 27

When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?

Options:

A.

An addendum is issued to all the bidders

B.

The proposer of the substitution is notified in writing

C.

The architect/engineer accepts the substitution during the pre-bid meeting

D.

Specifications are revised and reissued to include the substitution

Buy Now
Questions 28

Peer reviews or internal reviews of completed documents are examples of what?

Options:

A.

Quality control

B.

Commissioning

C.

Quality assurance

D.

Construction administration

Buy Now
Questions 29

Which of the following is NOT included in Divisions 02–49 of a project manual?

Options:

A.

General requirements

B.

Finishes

C.

Concrete

D.

Utilities

Buy Now
Questions 30

What governs Division 01 specifications and general requirements?

Options:

A.

Part I general

B.

Divisions 02-49

C.

The general conditions of the construction contract

D.

The construction drawings

Buy Now
Questions 31

The architect/engineer reviews submittals for which of the following reasons?

Options:

A.

To correct or change the design

B.

To monitor design conformance

C.

To review installation procedures

D.

To review substitution requests

Buy Now
Questions 32

An architect/engineer (A/E) is reviewing a claim from a contractor asking for more money and time on the project. The A/E plans to reject this claim based on documentation supplied by the contractor indicating what reason?

Options:

A.

There was active interference by the owner.

B.

There were conditions beyond the control of the contractor or owner.

C.

The A/E modified the contract documents.

D.

There is defective work needing repair.

Buy Now
Questions 33

Which of the following is LEAST important to log when documenting the decision-making process?

Options:

A.

Date, time, and location of the meeting

B.

List of attendees and who they represent

C.

Length of time each attendee spent speaking

D.

Action items with responsibilities assigned and date to accomplish

Buy Now
Questions 34

Which of the following is a scaled view?

Options:

A.

Perspective

B.

Foundation plan

C.

Riser diagram

D.

Isometric

Buy Now
Questions 35

To avoid miscommunication problems during construction, which best practice should the design professional use?

Options:

A.

Develop a good working relationship for verbally addressing problems as they arise

B.

Mark emails and electronic communications as "Urgent!" to ensure they are read right away

C.

Distribute meeting minutes to all attendees and concerned parties documenting key decisions and action items resulting from the meeting

D.

Leave detailed voicemail messages describing everything that needs to be done so there is a record of the direction

Buy Now
Questions 36

Which party has the ultimate authority to approve a change order?

Options:

A.

Architect/engineer

B.

Contractor

C.

Owner

D.

Construction manager

Buy Now
Exam Code: CDT
Exam Name: Construction Documents Technologist
Last Update: Nov 23, 2025
Questions: 120

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99