Which of the following best describes the appraisal costs in the cost of quality'
Refer lo SCENARIO 2 - You are writing the Master Test Plan for Project 2 and must include a section documenting project risks that you believe could impact testing along with how, as Test Manager, you propose to manage each risk.
Which one of the following is the MOST appropriate entry for the Master Test Plan for RISK 4 "The user interface software for the sound systems will be delivered late into testing-?
SELECT ONE OPTION
The teams are two days away from the end of the current iteration. The rate at which users have been reporting defects has been trending upward in the last few weeks and so far during this latest iteration has shown another increase.
The scrum master of the team responsible for most defects has asked you for ideas about how to perform the next retrospective in order to learn the appropriate lessons.
You have suggested that they should provide the retrospective meeting with a breakdown, by nature and severity, of the defects relevant to that team.
Assuming that this is done, which next three steps of the retrospective will be MOST effective?
Your test team has created a custom automation tool that will be used for an upcoming release. Now that the tool has been coded, what
should be the next step? [1]
You are interviewing a candidate for the position of test analyst. At one stage of the interview, you are looking specifically for skills in the area of professional competence. Which of the following skills would demonstrate this?
Which two items are MOST relevant for inclusion in your tool selection plan for functional test automation in Agile?
You are working on a project that is having problems with regressions. With each release of software given to the test team. 50% of the defects found are actually regressions. To combat this you have decided to implement test automation. You have given your automation team the following goal
'Implement lest automation to automate 90% of the manual regression tests before the product release date.’’
Which of the following is likely an issue with this goal being defined as "SMART?
You are writing a system test level plan and are defining the test activities that must take place during test implementation. There is an established project risk register in place, with product risks addressing all new features to be developed. Three time-boxed cycles of system test execution are planned, and all the new features will be delivered in the first cycle.
The project test strategy states that the stakeholders require an overall view of the product quality for these features. This should be achieved by planning to test each product risk, to some degree, during the first cycle of test execution.
Which risk-based mitigation approach should be adopted during test implementation, to BEST meet the stakeholders' requirement?
Which of the following should be considered the biggest risk to the schedule when trying to implement formal scripted test cases early in the SDLC for a system with a
large GUI front end? [2]
You are a new lest manager in an organization You have been asked to assess the defect process to determine if there are any efficiency improvements that could be made that would reduce the cost of quality You have started digging through the defect Information What information would be most helpful for this investigation?
Which classification information would be most useful to capture for newly identified defects? [2]
You have been asked to implement formal reviews at your company. From the list below, what are the correct characteristics of a formal review?
a. Entry and exit criteria have been defined.
b. Checklists created to be used by all reviewers.
c. Consistency with current project plan is checked.
d. Metrics on effectiveness will be gathered.
e. The review will be moderated by a lead auditor.
Which is a typical test task that would demonstrate the professional and methodological competence of a tester?
As test manager, you need to determine if there are likely to be new security risks arising from proposed changes to an in-house purchasing application. You invite a security testing consultant, who is external to the organisation, to assess the changes and provide you with their written report of perceived security risks.
Which risk identification technique are you using?
Your test process is fully integrated into the software development lifecycle. You are at which TMMi level? [1]
Which of the following is NOT true when following the V-Model lifecycle to organise and plan testing activities? SELECT ONE OPTION
Your Project Manager has challenged you to come up with a process improvement strategy using the IDEAL model.
Which step within the process defines the success criteria? [2]
Which statement about defining process improvement actions using defect report information is TRUE?
Refer to SCENARIO 2 It has been agreed that the following test planning documents will be produced;
• A single overarching document outlining the general testing methodology for the whole programme of work
• A subordinate test plan for each of the three projects
• A separate test plan for performance testing within each project
Which one of the following options BEST describes the type of test management document that will meet the programme requirements?
Mary is an external IT auditor. She is conducting a review of the system-level testing done by Greg's functional testing team.
Which of the following items from Mary's assessment summary should concern Greg the most? [2]
Assume that you are working for a company that has maintained and tested a car parking permit system for many years. The system holds the name and address of permit holders and automatically writes to the permit holder with a form to renew or cancel their permit each year.
The test plan states the following:
"since the system is considered a stable system. Boundary Value Analysis is the only test case design technique that needs to be applied during testing"
Consider the following change that was detailed in the Requirements Specification for a replacement to an existing parameter held within the system;
• The specified renewal date for each permit must be not be after 31 st January 2020. Which one of the following is a valid test condition that satisfies both the requirement and the test plan?
SELECT ONE OPTION
Your company has adopted an Agile methodology. Defect reports are not raised for all bugs found during the testing of individual stories, but continue to be raised in some circumstances, e.g., when the fix cannot be made immediately, or would involve another team. The teams would like better data to use for assessing the quality of their work. The list below shows five items that are currently not captured on defect reports.
Which TWO of these items will be MOST useful for assessing the quality of a product increment?
Which of the following is likely to occur if reviewers do not have an adequate level of technicalknowledge? [1]
In relation to cost of quality, which of the following would be classified as a cost of detection? SELECT ONE OPTION
Your last project was released three months ago and used a risk-based approach. In production, a number of serious failures in low risk areas have occurred.
What is the most important lesson to be learned from this information? [2]
Which of the following is required to apply an experience-based testing approach''
An old stock control system is being decommissioned and replaced with a new system that has been running successfully in the live environment for the last few months. The stakeholders would like to -
• retain historical information held in the database to comply with their data retention policy (which requires order information to be retained for 7 years)
• query the historical information by running pre-written SQL queries.
• all commands must be invoked by keyboard as one of the end users is unable to use a mouse
The pre-written SQL queries will be designed, developed and tested by the developers who are decommissioning the system and writing the data migration routine.
As the system to be decommissioned is integrated to other systems that will remain operational, the stakeholders have requested that testing incorporates all systems that are part of the stock control suite.
The stakeholders and project manager have identified the following risks, in priority order -
• 1st - Data has not been successfully migrated to an archived data store, resulting in the inability to query past stock levels and re-order details.
• 2nd - Historical data for the last 7 years is unavailable, resulting in the failure to meet the data retention policy.
• 3rd - Failure of existing systems within the stock control suite, adversely affecting the operational running of the business
The risks are to form the basis of the test objectives. Which three of the following test activities, work products and/or resources achieves the test objectives?
a. Use of the live database to test the data migration does not corrupt or lose data
b. A test plan detailing the test approach for ST. SIT & OT test levels
c. Accessibility testing of the pre-defined SQL queries
d. Security and Penetration testing of the archived database
e Performance testing of the data migration exercise to ensure it completes in the time specified by the stakeholders
f. Functional testing of the pre-defined SQL queries
g. Regression testing of the end to end process for maintaining specified stock levels.
You have replaced informal code reviews with technical reviews for the most complex and critical components, in an attempt to reduce the high number of defects being found during component and integration test levels. The project manager is concerned about the costs of implementing formal reviews and has asked you to measure whether they actually provide a return on investment.
Which three of the following metrics would be MOST effective in helping you to achieve this?
a. Identification of defect clusters across components
b. Number of lines of code reviewed
c. Number of defects found during reviews d Root cause for each defect detected
e Post-review cost of detection and internal failure per defect
f. Type of review
g. Effort to conduct the review including rework
Which three of the following would be considered a good mix of technical and interpersonal skills (hard and soft), for a test team leader?
a. Ability to compliment a developer.
b. Presenting information regarding a test project progress to stakeholders
c. Using a configuration management tool.
d. Ability to read a development coding language
e. Assessing a failure and documenting it correctly.
Which of the following is MOST likely to influence the choice of test levels for a project?
'Safe as Houses' is a company that specialises in home security software, including alarm systems, surveillance cameras and other forms of deterrence.
It is currently developing the software for a device which simulates an active television, producing sound and light images that suggest someone is home watching the television. 'Safe as Houses' recently won a lucrative contract to supply the software to Smart Alarms', who will be manufacturing the hardware devices Sound will be created using actual television and film archives, licensed through a third-party supplier, 'Silver Sound Ltd'. A user interface will be developed in house to allow the customer to choose sound tracks.
The software will be delivered as a programme of work, consisting of three projects. Project 1 will develop the software for the light images. Project 2 will develop the sound system and Project 3 will integrate the two using hardware prototypes supplied from 'Smart Alarms'. The programme will conclude with 'Smart Alarms' performing User Acceptance testing in usability labs.
The 'Safe as Houses' test team has experience in testing alarm and surveillance systems but lacks experience in testing light imagery software. The organisational test policy includes the following objectives:
1 Exploratory testing should be used to augment more formal, structured testing within constraints of time and budget
2. Test automation tools should be purchased and employed to maximise the breadth and efficiency of regression testing
The Programme risk register currently includes the following risks:
RISK1 Working prototypes will be delivered late to the integration test environments
RISK 2 A delay in signing the contract with 'Silver Sound Ltd' will impact the programme schedule
RISK 3 Inexperience in testing light imagery software will cause major defects to be missed RISK 4 The user interface software for the sound systems will be delivered late into testing
Refer to SCENARIO 2 - The IT Director for 'Safe as Houses' is recruiting a Programme Test Manager and has been provided with a skills matrix for four prospective candidates. The matrix shows the skill level (5 being highest. 1 lowest) for each candidate:
Consider which of these skills are key for a Programme Test manager in this scenario. Based on these, which candidate would be the most suitable?
SELECT ONE OPTION
Your current project is delivering a warehouse management system for use in distribution centres, you are writing a test plan to address acceptance testing. You need to determine which stakeholders would be interested in receiving regular reports covering the progress of test execution against agreed schedule and budget. Which roles would be MOST interested in these reports?
There is a debate in your organization about who can close a defect report The developers think they should be able to reject and close defects without any further steps The testers are not happy with this approach as they are afraid the rejections may go undetected and the developers may close something without understanding the real problem
How can this problem be rectified7
At what testing level do the test management activities Include coordinating with end users7
In what environment are you most likely to see multiple defect management systems used in one project?
Your team has been assigned to lest a new product that is tightly integrated with existing systems The integrations include data transfers and transformations You have access to the architectural design documents and the integration specifications and some of your testers are former developers.
Given this information, what is the most appropriate test approach?
You have decided to help your team improve their skills. One of their assignments is to mentor a junior member of the team Which competency should you expect the mentor to develop during this exercise?
Your manager has decided that your team of manual testers should all become test automation engineers Your team is much stronger in analysis than In technical testing so you are concerned about their ability to adapt. What tool capabilities could help with this transition?
You have been looking at the actual vs expected defects in one high risk area of the software The actual is much higher than the expected value What should you do?
You are working with a development team who have a CI/CD pipeline implemented. They want to integrate your team's existing test automation into the pipeline to augment their unit tests so they will have continuous testing. They have already determined that this is technically possible with the tool you are using but with require some changes to the test automation framework to integrate the results reporting
What will your team need to make this happen?
Your team has been assigned to a new project You have a mix of manual testers and automation engineers but everyone is currently doing manual testing. The development learn has alreadydecided to use DevOps as its approach but they have never used it before and are happy to take your input Unfortunately, about 50% of the development is completed already In the testing your team is doing they are finding that about 40% of the defects they catch are actually regressions caused by other changes
Given this information what should you do to help mitigate risk'?
Which of the Mowing should be used to understand the context of testing within an organization?
Which of the following Is the common set of information to be produced in a test estimate''
It the lest manager must repeatedly step in to resolve conflicts within the team what phase is the team in and what competencies are required from the test manager?
You have been seeing a high number of rejections of defect reports The developers are complaining that they do not understand what the problem is. even though they have been supplied with screenshots. You have checked a number of the 'problem' defect reports and have not found any information that is missing. The descriptions are very detailed and include all the necessary information in a long descriptive paragraph.
What change should you recommend that should help with the developer s problems?
Your team has been assigned to test a loyalty card program for a supermarket chain. Because this is a highly competitive market significant investment has been made to determine the shortcomings of the products offered by competitors While the feature sets are mostly the same, there is a wide variance In usability and performance and the users perceptions of these quality characteristics
Given only this information what test approach would be most appropriate?
Which of the following Is considered a heavyweight risk-based testing technique'
In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''
You feel that your team has become lazy when applying good software testing techniques You have given each of them a challenge to take a different business rule and build a full decision tableand then collapse that table You will then assess the results For this assessment, what competencies are you validating?
One of your team members is struggling to identify the requirements to be tested for a project The requirements documents are not conventional but you have determined that the data is there. If they do some digging to find it Given this information in what competence area does this person need to improve?
You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving
You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?
You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?
You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.
Given this information what should you conclude?
Your defect opened trend is converging to the closed trend but there is still a gap. What does that gap represent?
You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?
Which of the following defect statistics will provide input to be used for improvement in the defect reporting process?