CHFM Certified Health Care Facility Manager (CHFM) Questions and Answers
The annual utility bill at a hospital is $1.2M for a 500,000 sq. ft. facility. The current construction project will add 100,000 sq. ft. to the facility. What is the anticipated annual utility budget after the construction project is completed?
Where a required fire alarm system is out of service for more than 4 hours in a 24-hour period, which of the following is required according to NFPA Life Safety Codes?
Notify the authority having jurisdiction.
Provide an approved fire watch for all parties left unprotected by the shutdown.
Notify the building administrator.
Notify the fire alarm service company for repair.
Which of the following should be considered when determining the simple payback of an energy-saving alternative?
The following information is available:

Which building has the best overall building condition?

(Base Bid / Alternate A / Alternate B)
Company A: $18,000 / $2,000 / Not available
Company B: $20,000 / $3,000 / Included
Company C: $19,000 / $4,000 / $500
Company D: $19,000 / $4,000 / $1,000
Which company has the LOWEST cost if alternate B is chosen?
In which type of boiler do the gases of combustion pass through tubes surrounded by water?
As part of developing a HVA, which of the following elements should be considered?
events affecting demand for hospital services
cost of addressing the events
consequences of the events
likelihood of the events occurring
The occupants of a building wing complain of nausea, dizziness, or drowsiness. Which of the following is the most likely cause?
Which section of the National Electrical Code addresses the installation of electrical wiring within healthcare facilities?
When a motor malfunctions on an air handler, what is the first step to be taken in the replacement of the motor?
According to OSHA, which of the following is required as part of a lockout/tagout program?
When storing oil or petroleum products over 1,320 gallons above ground or 42,000 gallons underground, a Spill Prevention, Control, and Countermeasure (SPCC) program is required in accordance with
Which of the following methods could be used to reduce the cost of a service contract without reducing the scope of service?
Implement an in-house first response program.
Increase the frequency of house calls.
Finance the cost of the contract.
Extend the length of the contract.
Medical gases normally found in a patient room include
oxygen.
medical air.
nitrogen.
vacuum.
In order to ensure a safe environment for patients, what department must be involved during the planning of all construction projects?
The occupants of a building wing complain of nausea, dizziness, or drowsiness. Which of the following is the most likely cause?
Which of the following are used to establish a salary range for a new job category?
market salary analysis
candidate qualifications
review of internal equity
job description
A construction project in a cafeteria should not start until which of the following is present?
At the end of an 8-hour electrical shutdown, after the maintenance work is completed but before the cabinets are closed up or the system re-energized, a final inspection should be completed by individuals who have
A primary-secondary chilled water system typically has variable volume pumping on the
A justification for having an institutional standard for a ball valve instead of a gate valve is that ball valves
Which of the following types of injuries is most likely to occur during an MRI scanning process?
Which of the following building fire alarm system components is required to be tested quarterly?
A facility manager has to prepare a labor budget for an upcoming addition of a new patient wing. Budgetary needs will include:
— Two carpenters at $40 per hour for 20 hours a week for project work for 78 weeks
— Two carpenters at $40 per hour for 20 hours a week for maintenance work for 78 weeks
— One laborer at $20 per hour for 40 hours a week for project work for 78 weeks
— One supervisor at $45 per hour for 10 hours a week for project work for 104 weeks
— One supervisor at $45 per hour for 10 hours a week for maintenance work for 104 weeks
What is the correct budget assignment, without any benefits?