CCM Certified Contract Manager Questions and Answers

Questions 4

If a FIDIC Red, Yellow, or Silver Book (edition 2017) is applied, in which of the following two cases is the Contractor required to submit a revised programme?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor shall revise the Programme only by request from the Engineer or the Employer (in case of FIDIC Silver Book).

B.

To accurately reflect the actual progress of the Works, but only if any Programme ceases to reflect actual progress with at least 42 days.

C.

To accurately reflect the actual progress of the Works, whenever any Programme ceases to reflect actual progress or is otherwise inconsistent with the Contractor's obligations.

D.

Upon a request from the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) notifying it that the Programme fails to comply with the Contract, to a specified extent, or no longer reflects actual progress or is otherwise inconsistent with the Contractor's obligations.

Buy Now
Questions 5

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer's prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer's prior approval or not. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 6

Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?

(Choose all correct answers — multiple possibilities)

Options:

A.

The Employer is bound by the Certificate issued by the Engineer, and must make payment in full, except for any compensation arising from any claim which the Employer may have against the Contractor.

B.

The Employer is not bound by the Certificate issued by the Engineer.

C.

The Employer is bound by the Certificate issued by the Engineer and must make payment in full, irrespective of any entitlement to compensation arising from any claim which the Employer may have against the Contractor.

D.

If the Employer considers itself entitled to claim against the Contractor, notice and particulars must first be submitted under Sub-Clause 2.5. The Employer's entitlement is then to be agreed or determined by the Engineer, and then, incorporated as a deduction in a Payment Certificate.

Buy Now
Questions 7

Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

Options:

A.

Letter of Acceptance

B.

Letter of Intent

C.

Memorandum of understanding

D.

Letter of Intent & Memorandum of understanding

Buy Now
Questions 8

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

Options:

A.

The Contractor submits a Value Engineering proposal, in which it proposed to change the colour of the outdoor paint. The Engineer approved the proposal.

B.

The Engineer instructs a change in slopes of stairs to the parking lot with an Instruction in accordance with Sub-Clause 3.3.

C.

The Engineer requests a proposal regarding a change in type of windows and doors of the business centre.

D.

The Employer verbally instructs a change in the layout of the rooftop restaurant. The Engineer issued an Instruction describing the required change with revised design drawings.

Buy Now
Questions 9

Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor's Proposal. Which two of the following statements are true in this respect, after it has been submitted?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor is entitled to change the design by optimising the design, without approval of the Employer/Engineer.

B.

The Contractor is not allowed to make any changes regarding the design to optimise the design, unless approved by the Engineer/Employer.

C.

The Contractor may submit a proposal for Value Engineering.

D.

The Contractor is not allowed to submit a proposal for Value Engineering, as any value engineering should already have taken place before submitting its design proposal.

Buy Now
Questions 10

Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 11

Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 12

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

Options:

A.

A prolonged suspension for more than 1 year has affected the whole of the Works.

B.

The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.

C.

The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

D.

The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer's obligations under the Contract.

Buy Now
Questions 13

Which two statements reflect an INCORRECT application of a Golden Principle?

Options:

A.

Any deletions of General Conditions (GC) must be replaced with Particular Conditions (PC) that cover the same scope, and do not leave any roles, duties, obligations, rights, and risk allocation undefined.

B.

When applying the FIDIC Red Book or Yellow Book, the Commencement Date shall be within 60 days after the Contractor receives the Letter of Acceptance, in lieu of 42 days.

C.

The Contractor's right to suspend work (or reduce the rate of work) effective after giving not less than 3 months (in lieu of 21 days) notice to the Employer.

D.

Deleting all the clauses in the General Conditions that refer to the DAAB/DAB.

Buy Now
Questions 14

In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?

Options:

A.

When the works are simple and of short duration.

B.

When there is a limited number of capable experienced contractors available and ready to take part in the procurement.

C.

In case of large scale works, where there are several companies likely to have an interest in submitting an offer.

D.

If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.

Buy Now
Questions 15

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.

B.

Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.

C.

The appointment of the Contractor's Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.

D.

Receipt of a statement and supporting documents.

Buy Now
Questions 16

Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.

Options:

A.

Provisions of the General Conditions are deleted and replaced in the Particular Conditions solely by the words "not used".

B.

All deletions of a General Conditions are replaced with new Particular Conditions that cover the same scope.

C.

Clarifications to the meaning of tender documents together with answers to tenderers' inquiries made during the tender period by the Employer should be e-mailed in a Excel table in both PDF and XLS file format.

D.

The clarifications to the Contract given during the tender period are never to be attached to the Contract, as such clarifications are reflected by amending the Particular Conditions.

Buy Now
Questions 17

Towards the end of implementing a varied work (initiated originally by the Contractor as a "Value Engineering Proposal", relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]

Choose all of the correct answers (multiple possibilities).

Options:

A.

Since the design was approved by the Engineer, the Contractor might not be found responsible for such discrepancy, hence, to be fully compensated.

B.

In this situation, the whole of the varied works should be removed, and the original technical content reinstated.

C.

The Contractor shall immediately rectify, ensuring, that the varied work fully complies with the prevailing standards.

D.

In case it is necessary, the Contractor shall prepare designs for works subject to the Value Engineering, hence, it is up to the Contractor to ensure that the works are fit for the purposes, including that the designs are correct, regardless of any approval or "no-objection" of the Engineer.

Buy Now
Questions 18

The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If the advance payment is not completely repaid before Time for Completion.

B.

If advance payment is not completely repaid before the Performance Certificate is issued.

C.

If the advance payment is not completely repaid before the Taking-Over Certificate is issued.

D.

If the advance payment is not completely repaid before termination of the Contract.

Buy Now
Questions 19

The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.

Options:

A.

True

B.

False

Buy Now
Questions 20

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?

Choose all of the correct answers (multiple possibilities)

Options:

A.

All internationally recognized holiday periods.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

Only the delivery dates of Plant and Materials which have not been delivered on Site yet.

Buy Now
Questions 21

You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".

For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.

In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.

As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.

In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?

Options:

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirement only.

C.

The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both Claims.

Buy Now
Questions 22

Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?

Options:

A.

If the Contract Price is to be adjusted for rises and falls in the cost of labour, the Contractor is entitled to compensation in such a way that all rises and falls in the costs are compensated fully.

B.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. This can result in lower adjustments of the Contract Price than the actual changes in the costs of labour and/or Goods.

C.

If Particular Conditions provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8, it can only apply to rises or falls in the costs of labour and Goods.

D.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. Only the Base Date can be taken as the date from which the adjustment should be calculated from.

Buy Now
Questions 23

You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer's claim on Delay Damages. You have asked Y to consider whether the Contractor's delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor's payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?

Options:

A.

Both you and Y are both correct.

B.

You are correct, Y is wrong.

C.

You are wrong, Y is correct.

D.

Both you and Y are wrong.

Buy Now
Questions 24

Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?

Options:

A.

The Letter of Tender may be worded by the Contractor (at its discretion) so as to allow for the alternative of the Contract to become effective when the Employer issues a Letter of Acceptance.

B.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

C.

The Contract is administered by the Engineer who is appointed by the Employer. If disputes arise, they are referred to a Dispute Adjudication Board (DAB) for its decisions.

D.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

Buy Now
Questions 25

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

Options:

A.

True

B.

False

Buy Now
Questions 26

A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.

Options:

A.

The Employer should check on the Appendix to Tender, Employer's Requirements and / or Particular Conditions. There could very well be specific requirements regarding the language in those. If that is not the case, the language of the Contract determined in Sub-Clause 1.4 and the language of the Operation and Maintained Manuals should in this case be English.

B.

If French is indeed an official second language of the region where the Plant is built, the Contractor is entitled to deliver the documents in French. The usability in terms of language is not described in Sub-Clause 5.7, so the Employer should accept the Operation and Mantained Manuals in French.

C.

Golden Principle no. 1 states: The duties, rights, obligations, roles and responsibilities of all the Contract Participants must be generally as implied in the General Conditions, and appropriate to the requirements of the project. In this case this means it is appropriate that the Operation and Maintenance Manuals are in French, as the maintenance is based in France.

D.

As the Contract is written in the English language, Sub-Clause 1.4 dictates that the Operation and Maintenance Manuals should be written in English as well.

Buy Now
Questions 27

Regarding the FIDIC Red Book (edition 1999), which two statements are true?

Options:

A.

In emergency situations notices can also be submitted verbally (rather than (also) in writing).

B.

A notice is to be signed by the Engineer, Contractor's Representative or Employer's Authorised Representative.

C.

A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.

D.

Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.

Buy Now
Questions 28

You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

Options:

A.

Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.

B.

Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.

C.

Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.

D.

None of the above.

Buy Now
Questions 29

In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:

"In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction."

What GP(s) is/are breached?

Options:

A.

GP1 only

B.

GP3 only

C.

GP1 and GP3

D.

GP1, GP2 and GP3

Buy Now
Questions 30

Applying FIDIC Silver Book (edition 1999), which one of the following elements shallnotform part of the time Programme/revised programme?

Options:

A.

The intended order of the works.

B.

The sequence and timing of inspections and tests.

C.

The remedial work (if any) instructed under Sub-Clause 7.6.

D.

Review periods under Sub-Clause 5.2.