Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

Note! SAP has retired the C_TS412_1909 Exam and replaced it with the C_TS412_2021 Exam. Contact us through Live Chat or email us for more information.

C_TS412_1909 SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Questions 4

Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

Options:

A.

Schedule Manager

B.

Project Builder

C.

Project planning board

D.

Easy Cost Planning

Buy Now
Questions 5

What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question

Options:

A.

Location

B.

Material

C.

Production version

D.

Resource

Buy Now
Questions 6

Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.

Note : there are 3 correct answers for this question.

Options:

A.

Display of production orders assigned to WBS element.

B.

Display of plant maintenance orders for activities.

C.

Display of project cost plan.

D.

Display of project -relevant purchase order.

E.

Using specific color management for Gantt Chart.

Buy Now
Questions 7

A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question

Options:

A.

Resource reports

B.

Cost element reports

C.

Structure information system reports

D.

Hierarchical reports

Buy Now
Questions 8

Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

Options:

A.

Network profile

B.

Project profile

C.

Parameters for the network type

D.

Network type

Buy Now
Questions 9

Revenues & Payment

A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

Options:

A.

Settle the WBS element to the highest billing element before you do the result analysis.

B.

Split the project intdifferent project according to each company code.

C.

Change the project structure so that it correspond better to the company's organization structure.

D.

Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

Buy Now
Questions 10

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Options:

A.

Float time can be negative

B.

Activities with the time constraint "Must start on" always have a negative float time

C.

The float time of WBS elements is calculated by extrapolation

D.

By default, critical activities have a float time, which is less than or equal to zero

E.

The maximum size of a free float is as large as the total float of an activity

Buy Now
Questions 11

You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

Options:

A.

The person responsible for the work center

B.

The person responsible for the superior WBS element

C.

The MRP controller for the network

D.

The person responsible for the network activity

Buy Now
Questions 12

When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

Options:

A.

Service specification

B.

Overall limit (maximum value of all unplanned services)

C.

Service purchase order number

D.

Material master within service specification

E.

Vendor

Buy Now
Questions 13

Which organizational structures are required for network activities? Note: There are 3 correct answers to this question

Options:

A.

Controlling area

B.

Plant

C.

Sales organization

D.

Company code

E.

Operating concern

Buy Now
Questions 14

Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

Options:

A.

In the project profile

B.

In the project version

C.

In the project type

D.

In the project definition of a standard WBS

E.

In the operative WBS element

Buy Now
Questions 15

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

Options:

A.

Scheduling and capacity category

B.

Scheduling and distribution key

C.

Control key of an activity

D.

Capacity planner group in the network header

Buy Now
Questions 16

Which object is used to allocate the costs from a claim to the project structure?

Options:

A.

Network activity

B.

Internal order

C.

Claim

D.

WBS element

Buy Now
Exam Code: C_TS412_1909
Exam Name: SAP Certified Application Associate - SAP S/4HANA Project Systems
Last Update: Jul 17, 2025
Questions: 112