Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

BIM_MGT_101 Autodesk Certified Professional in BIM Management for Building Design Questions and Answers

Questions 4

During a model review, several linked files appear missing or unloadable in the federated coordination file. The files were present and working the day before, and no changes were made to the Revit host model itself.

As the BIM manager, what is the most appropriate step to troubleshoot the issue?

Options:

A.

Check that file paths to linked models were set as relative and validate that the folder structure remains unchanged.

B.

Ask the modelling team to rebind all linked models using absolute file paths.

C.

Remove the missing links and advise each team to reinsert their models before the next coordination meeting.

D.

Recreate the host model using a previous backup and manually reload each link.

Buy Now
Questions 5

Refer to the exhibit.

BIM_MGT_101 Question 5

Upon opening a model, the following warnings saying “Room Tag is outside of its Room” appear.

What action should the BIM manager ask the design team to take in order to identify any Room Tags that need a leader because the tag may be too big to fit within the room?

Options:

A.

Select Show to address each tag.

B.

Select Export to move the warnings outside the model.

C.

Select Close to exit the Warnings window.

D.

Select Delete Checked to resolve each tag.

Buy Now
Questions 6

A BIM manager is running clash detection for the first time on a large retail project during the Design Development phase. After copying all the models to the coordination space on Autodesk Forma, the matrix shows no clashes among any of the models.

How should the BIM manager proceed?

Options:

A.

Add sheets to the publish settings and rerun the clash.

B.

Verify the shared coordinates for each model and republish.

C.

Continue forward on the project because there are no coordination issues.

D.

Use the project as a case study for a firm-wide presentation.

Buy Now
Questions 7

The BIM manager is working on a mixed-use project in which consultants are on different platforms and delivery timelines. The client requires COBie-compliant data handover and weekly coordination uploads.

What is the best approach to ensure project-specific BIM processes are effectively implemented from the outset?

Options:

A.

Facilitate a project-specific BIM kickoff session to align all contributors on workflows, deliverables, and data-handover protocols.

B.

Accept each firm’s standard BIM workflows and distribute them to the team to promote consistency across consultants.

C.

Focus on setting the Common Data Environment permissions first and allow teams to organize their workflows independently.

D.

Establish a baseline BIM Execution Plan, then adjust it incrementally based on coordination issues as they arise.

Buy Now
Questions 8

The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.

What fix needs to happen to resolve this misalignment?

Options:

A.

The BIM manager needs to go to a 3D view and move the model to align with the architectural geometry.

B.

The Lighting team needs to fix its shared coordinates to match those of the Architectural model and reissue the file.

C.

The BIM manager needs to acquire the shared coordinates of the CAD file.

D.

The Lighting team needs to add gridlines so the BIM manager can align its CAD file to the architectural gridlines.

Buy Now
Questions 9

Refer to the exhibit.

BIM_MGT_101 Question 9

A client has provided the design team with a title block family and a Shared Parameters file that must be used as part of their standards. Those provided parameters must be applied both in the Project Information area as well as the title block.

When the design team is in the project model and attempts to fill in information into the title block parameters, a question mark appears. What is the likely cause of this?

Options:

A.

The shared parameters were included in the title block family but were not loaded into the project file.

B.

The parameters were not included in the Shared Parameters file provided by the client.

C.

The Shared Parameters file was not added to the title block family and was using text instead of a label.

D.

The Sheet and Project Information fields were overwritten in the title block.

Buy Now
Questions 10

The BIM manager received a subcontractor’s 3D model containing specialty equipment to be integrated into the federated model. Upon review, they observe that:

    Many elements lack consistent object styles and category assignments.

    Some components are modelled with excessive detail, affecting performance.

    Embedded data does not follow the project’s naming conventions outlined in the BEP.

What is the most appropriate next step when evaluating this geometry and content?

Options:

A.

Instruct the subcontractor to simplify geometry and reduce file size, even if some metadata and classifications are lost.

B.

Approve the model as-is to avoid delaying coordination and document the issues for review at the next quality-control milestone.

C.

Review the model against content standards, document noncompliance, and request revisions aligned with agreed deliverable requirements.

D.

Import the model into the coordination environment and apply view filters to hide excessive detail and inconsistencies.

Buy Now
Questions 11

A federated model has been created for a multidisciplinary project, but clashes are being reported in areas where coordination should already be resolved. Upon investigation, the BIM manager finds that some models were exported with outdated links and local coordinates.

What is the most appropriate next step before proceeding with coordination analysis?

Options:

A.

Instruct teams to verify model references and coordinate systems before reassembly.

B.

Freeze the current model state and ask trades to work around the identified issues.

C.

Notify the client and exclude the faulty models from further coordination.

D.

Run an additional clash-detection pass with adjusted tolerance thresholds to reduce clash totals.

Buy Now
Questions 12

Refer to the exhibits.

BIM_MGT_101 Question 12

BIM_MGT_101 Question 12

BIM_MGT_101 Question 12

BIM_MGT_101 Question 12

A BIM manager is preparing a site model that includes three separate buildings. Which exhibit shows the correct way to assemble and position the individual building models on the site while maintaining proper coordinates and orientation?

BIM_MGT_101 Question 12

BIM_MGT_101 Question 12

BIM_MGT_101 Question 12

BIM_MGT_101 Question 12

Options:

A.

Exhibit 4

B.

Exhibit 3

C.

Exhibit 2

D.

Exhibit 1

Buy Now
Questions 13

A contractor has requested the Architectural Revit model for a design-bid-build project to help with their fabrication drawings. The contractor understands and agrees that construction documents will govern in case of discrepancies.

How should the BIM Manager proceed?

Options:

A.

Add the contractor to the Autodesk Forma project for model access given their understanding.

B.

Copy the model file and send it as soon as possible.

C.

Verify that the contractor has signed a digital content release form before sending the model.

D.

Export the sheets to DWG format and send those files.

Buy Now
Questions 14

The BIM manager is working in an Architectural model that uses the phases Existing and New Construction . They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.

Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?

Options:

A.

Apply a phase-filter override to the linked model using Visibility/Graphics settings.

B.

Open the linked model and manually change its phase names to match the host model.

C.

Map the linked model’s phases to the host model’s phases in the Revit Link properties.

D.

Override the linked view’s phase settings using view templates in the host model.

Buy Now
Questions 15

A government facility project requires unique data formatting and export requirements that comply with a global data-management initiative. A workflow utilizing a newly released add-on tool is developed to perform this task.

How should a BIM manager define training and ensure the appropriate staff receive it?

Options:

A.

Create training tutorials for the unique tasks and assign them to the members whose roles are responsible for the tasks.

B.

Develop a full training curriculum and assign all members of the project team, regardless of role.

C.

Assign the task to the team and provide training to any user whose Journal reveals a crash.

D.

Review each project model at milestone deliveries and assign the team training on items that fail the quality-control review.

Buy Now
Questions 16

Which of the following would typically be included in an AECO BIM data handover package at project closeout?

Options:

A.

Internal meeting notes from model coordination sessions.

B.

Federated design models used during clash detection.

C.

3D views used for clash detection during model coordination.

D.

Record models with the required asset data embedded.

Buy Now
Questions 17

A BIM manager is creating a firm-wide template for mobilization plans to outline the key steps, resources, and strategies required to set up and launch BIM operations at the beginning of projects.

Which two components should the template include to accomplish the goal? (Select two.)

Options:

A.

Common Data Environment.

B.

Contract template.

C.

Roles and responsibilities.

D.

Specifications.

E.

Project milestone dates.

Buy Now
Exam Code: BIM_MGT_101
Exam Name: Autodesk Certified Professional in BIM Management for Building Design
Last Update: Jul 17, 2026
Questions: 57

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99