Questions 4

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels ' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Buy Now
Questions 5

The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-

rounds of the new bedroom and en-suite bathroom facilities throughout the project.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because the early and frequent demonstration of product features to the Business Sponsor increases the visibility of the project and keeps the business engaged.

B.

Yes, because the project ' s budget holder is the only person who can approve project products.

C.

No, because products should be handed over at the end of the project, during Post-Project.

D.

No, because the Daily Stand-up meetings should have allowed the key representatives to review and discuss the evolving solution.

Buy Now
Questions 6

Which 2 individuals would be suitable for the role of Workshop Facilitator?

Options:

A.

Team Leader

B.

IT Operations Manager

C.

Marketing Director

D.

Software Developer

E.

Project Manager

Buy Now
Questions 7

During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent

any Planning Authority issues.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because all stakeholders should attend the Daily Stand-up meetings.

B.

Yes, because each team member will have an opportunity to highlight any Planning Authority issues that may otherwise hinder their progress.

C.

No, because NOT all members of the Solution Development Team will attend the Daily Stand-up.

D.

No, because only members of the Solution Development Team should be permitted to attend Daily Stand-up meetings.

Buy Now
Questions 8

During Timebox B, the ' Hoy for Hoy Hall ' Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re-

engage this group and explore discrepancies in understanding.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because Facilitated Workshops provide a forum for each member of the team to present a short progress report.

B.

Yes, because discussing requirements in the presence of other stakeholders increases the whole group ' s awareness.

C.

No, because the Project Manager should have escalated this disagreement as an issue before any action was taken.

D.

No, because the local Action Group should have attended the Daily Stand-up meetings.

Buy Now
Questions 9

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to ' install a heat reclamation system ' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because only Must Have requirements should be fully understood.

B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.

C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.

D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.

Buy Now
Questions 10

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

AgilePM-Practitioner Question 10

Options:

Buy Now
Questions 11

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Delivery Plan?

Options:

A.

The Project Manager should include any known constraints associated with planning permission.

B.

The Project Manager should NOT need to identify any risks this early in the project.

C.

The approach to the project should be based on the Project Approach Questionnaire responses.

D.

The Earth Excavations ' Head Gardener should be excluded from discussions related to deliverables since contracts are NOT yet signed.

E.

The Architecture Angels ' Marketing Director should be involved in the development of the Delivery Plan.

Buy Now
Questions 12

Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the

project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements explain why the Architecture Angels ' Finance Director would be an appropriate Business Sponsor?

Options:

A.

Is able to delegate most of the required involvement to the Chief Accountant.

B.

Has been friends with the Architecture Angels ' Chief Executive since school.

C.

Is the project budget holder.

D.

Is concerned about preventing the costs of refurbishment from escalating and affecting the operations of the company.

E.

Will not distract the Solution Development Team, as is usually too busy to be involved.

Buy Now
Questions 13

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

At the beginning of Solution Development Timebox A, the Timebox is being

planned in detail. Although Foundations was conducted at a high level, the

Prioritised Requirements List was baselined. Now the Solution Development

Team is setting detailed acceptance criteria against each requirement.

Is this an appropriate approach to setting detailed acceptance criteria?

Options:

A.

Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.

B.

Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.

C.

No, because the Solution Development Team should NOT be involved in setting acceptance criteria.

D.

No, because acceptance criteria should be set in detail against each requirement during Foundations.

Buy Now
Questions 14

There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as

it evolves.

Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2

can be used once, more than once or not at all.

Column 1

1) In order to get an objective

view, the financial transaction

function is to be tested by

someone from Finance who

has had no involvement in its

development.

2) Before the developer works on

the printing function for the

policy documents, the Sales

Manager will review a prototype

of the online application form

for the new coffee shop

insurance product with the

solution tester.

3) Security test scripts have been

provided by the company ' s

bank. These scripts will be used

to test the link from the

company ' s website to the

banking system, which is to be

developed specifically to achieve these tests

4.

The addition of the new coffee

shop insurance product may

threaten the stability of the

existing website. As a primary

route to market this is

unacceptable. The website ' s

capacity to run additional pages

is to be verified before any

other tests are performed.

5.

The Must Have and Should

Have requirements are to be

tested before the Could Have

requirements.

Column 2

    Collaborative Testing

    Repeatable Testing

    Independent Testing

    Prioritised Testing

    Test-Driven Development

AgilePM-Practitioner Question 14

Options:

Buy Now
Questions 15

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

AgilePM-Practitioner Question 15

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)

Options:

A.

Conduct a full analysis of Spa treatments to create a fixed guest service specification.

B.

Host a stakeholder workshop to prioritize integrating the Spa into the resort experience.

C.

Develop high-level estimates of effort and cost for Spa facilities and IT systems.

D.

Prepare a risk report on aligning Spa services with guest experience.

E.

Define work items in enough detail for Developers to start design work on treatments.

Buy Now
Questions 16

(To keep Business Sponsor, Sarah, informed, Hira has set up a real-time dashboard displaying project progress, risks, and actions from planning events.

Will this meet Sarah ' s needs?)

Options:

A.

Yes, because she will have access to progress updates, removing all meeting dependency.

B.

Yes, because she can rely solely on the dashboard for all her updates.

C.

No, because dashboards lack the context and detail required for strategic decision-making.

D.

No, because she will need Hira to compile and present the data in a physical report for sharing.

Buy Now
Questions 17

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 17

(Which of the following actions is appropriate when defining prioritizable Product Backlog items for the ' Hydrotherapy in Mineral-Rich Spring Pools ' Product Goal?)

Options:

A.

Break the Product Goal into smaller Backlog items, each justified by the value it contributes to the hydrotherapy experience described.

B.

Create a Backlog item for every infrastructure need to ensure nothing is missed from the range of features to be prioritized.

C.

Use MoSCoW to prioritize Product Backlog items based on technical feasibility and cost of delivery each feature described.

D.

Defer the prioritization of Product Backlog items until Sprint Planning so that the Delivery Teams can decide what is achievable at that time.

Buy Now
Questions 18

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

AgilePM-Practitioner Question 18

(When defining and estimating work for Project Increment 4, the Delivery Teams must account for uncertainty in integrating the Eco-spa into the guest experience.

Which 2 of the following approaches align with AgilePM principles for managing uncertainty in estimation?)

Options:

A.

Use broad estimation ranges for high-uncertainty work and refine estimates as more information becomes available.

B.

Avoid committing to estimates for uncertain work until all unknowns are resolved.

C.

Identify key assumptions behind estimates and revisit them regularly as the project evolves.

D.

Ensure all estimates are fixed early to maintain control over scope and budget.

E.

Exclude uncertain work from estimation until development is underway and clearer details emerge.

Buy Now
Questions 19

During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,

controlled and evidenced.

Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

AgilePM-Practitioner Question 19

(On receiving the meeting invitation, Hira responded suggesting that Brinda Vyas should also be invited to the meeting. Based on AgilePM guidance, which of the following does NOT present an appropriate justification for Brinda Vyas ' attendance?)

Options:

A.

Brinda Vyas is responsible for ensuring that the solution aligns with the strategic direction of the business and provides the expected value. Her input will help shape decisions related to capital investment.

B.

Brinda Vyas is accountable for the financial and regulatory governance aspects of the project and must personally oversee compliance-related discussions to ensure standards for these are met.

C.

Brinda Vyas plays a key role in confirming that the regulatory and quality expectations being discussed are aligned with the business need and will not undermine the viability of the project.

D.

The understanding of regulatory compliance needs for the Eco-spa gained by attending the meeting will help Brinda Vyas keep business stakeholders aligned with the business solution as it emerges.

Buy Now
Questions 20

Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.

Some members from Marketing and IT, based in India, join via video conferencing.

Issues raised:

. Dependency management challenges

· Concerns about AgilePM principle ' Demonstrate Control '

To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the

issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 20

(Stakeholders have shared concerns about tracking progress. Sarah Lark finds reports inadequate, and Lee Tan dislikes attending meetings.

Which 2 of the following actions would help the Delivery Teams to address these concerns?)

Options:

A.

Share a " walk-around " video at the end of each Sprint to give Sarah Lark a visual update.

B.

Encourage Lee Tan to check in informally with the Delivery Teams when convenient for him.

C.

Schedule new monthly meetings to share updates with both Sarah Lark and Lee Tan together.

D.

Provide Sarah Lark with a detailed written report weekly instead of each Sprint.

E.

Require Lee Tan to attend Sprint Reviews to see completed work firsthand.

Buy Now
Questions 21

(Which 2 statements describe appropriate team behaviour for effective risk management?)

Options:

A.

Team members should adopt a collaborative mindset, sharing responsibility for identifying and mitigating risks.

B.

Hira should have sole responsibility for managing all risks with clear accountability.

C.

Developers should resolve all risks collaboratively and promptly without escalation.

D.

Sukra Aroon should handle all technical risks independently to ensure the solution is fit for purpose.

E.

Risk management should be proactive and part of daily activities, not a separate process.

Buy Now
Questions 22

During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,

controlled and evidenced.

Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

AgilePM-Practitioner Question 22

(During the meeting, Mira Bachar asked Sukra Aroon which AgilePM project artifacts should use to provide an auditable record of compliance requirements throughout Project Increment 4.

Based on AgilePM guidance, which of the following is an appropriate response?)

Options:

A.

Use the Management Approach Definition, as it describes how governance and compliance responsibilities are structured within the project.

B.

Use the Project Review Report, as it provides a retrospective assessment of how the project was managed, including compliance considerations.

C.

Use the Sprint Review Records, as these document what was delivered in each Sprint and whether it was compliant with regulatory requirements.

D.

Use the Solution Architecture Definition, as it captures technical decisions related to compliance and regulatory requirements.

Buy Now
Questions 23

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

AgilePM-Practitioner Question 23

(Having provided some sample estimates for Hira to review, a number of stakeholders have challenged their accuracy—some suggesting that the work has been significantly over-estimated, while others believe it has been significantly under-estimated.

What should the Developers do?)

Options:

A.

Explain that early estimates are inherently uncertain and that they will be refined progressively as more details emerge throughout the project.

B.

Defend their estimates as accurate, assuring stakeholders that the numbers provided are fixed and reliable for planning purposes.

C.

Adjust estimates to align with stakeholder expectations, increasing or decreasing them based on their concerns to gain buy-in.

D.

Document key assumptions behind the estimates to provide transparency of rationale and support further refinement as more information becomes available.

Buy Now
Questions 24

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Feasibility Assessment?

Options:

A.

The new Project Manager should NOT be involved in finalising the

Feasibility Assessment.

B.

The Architecture Angels ' Finance Director should approve the final

Business Case as part of the Feasibility Assessment.

C.

The Earth Excavations ' Head Gardener should contribute to the outline

solutions considered for the gardens.

D.

The different options should be presented to the ' Hoy for Hoy Hall ' Action

Group for their feedback before the chosen outline solution is finalised.

E.

The Timber Tigers ' Site Manager should be the sole approver of the

finalised Feasibility Assessment before development commences.

Buy Now
Questions 25

(Brinda Vyas has been absent for two weeks, leaving Mira Bachar and the Delivery Teams to make decisions. Recent strategic adjustments haven ' t been communicated to the Delivery Teams causing frustration and risk of rework.

Which 2 statements describe how this risk should be handled within the AgilePM framework?)

Options:

A.

Continue increment work based on the backlog, assuming adjustments can be made when Brinda Vyas returns.

B.

Mira Bachar and the Delivery Teams should document assumptions behind decisions and continue progress without validation.

C.

Hira should engage other business stakeholders to assume Brinda Vyas ' responsibilities to ensure the Delivery Teams receives strategic guidance.

D.

Hira should escalate to Sarah Lark, the Business Sponsor, to replace Brinda Vyas with another qualified Business Visionary.

E.

The Delivery Teams should focus on backlog items with clear business direction and pause tasks that require Brinda Vyas ' input until guidance is available.

Buy Now
Questions 26

Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.

Some members from Marketing and IT, based in India, join via video conferencing.

Issues raised:

. Dependency management challenges

· Concerns about AgilePM principle ' Demonstrate Control '

To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the

issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 26

(Another of the EPR Eco-spa ' s commissioned in India experienced major quality issues, causing a three-week shutdown. Stakeholders are now worried about similar problems in Project Increment 4.

Which 2 of the following actions would appropriately reassure stakeholders that the same quality issues will not arise in this project?)

Options:

A.

Engage stakeholders in Sprint Reviews and encourage detailed quality discussions on delivered increments.

B.

Define and make visible quality criteria for Backlog items, and ensure the Delivery Teams collectively confirm compliance before declaring ' Done ' .

C.

Explain to stakeholders that AgilePM prevents quality issues through iterative development, incremental delivery, and continuous improvement.

D.

Appoint an independent Quality Manager to approve completed work before it is released.

E.

Review the India project ' s issues with stakeholders and demonstrate how Project Increment 4 addresses them differently.

Buy Now
Questions 27

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 27

(Which one of the following statements does NOT align with AgilePM ' s MoSCoW prioritization?)

Options:

A.

' Must Have ' requirements are essential to success, without them the solution is unworkable, unsafe, illegal, or pointless.

B.

' Should Have ' requirements are important and must be delivered for the project be deemed successful.

C.

' Could Have ' requirements are valuable and desirable from a business perspective but will only be delivered if time and resources allow.

D.

' Won ' t Have this time ' requirements are explicitly out of scope of the current Solution Increment but should be reconsidered for inclusion later.

Buy Now
Questions 28

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 28

(It is appropriate that the Delivery Team Leaders attend this Project Sprint Planning Event?)

Options:

A.

Yes, because AgilePM mandates joint decision-making between leadership and Delivery Teams.

B.

Yes, because Team Leaders provide real-time insights on progress, risks, and dependencies.

C.

No, because Team Leaders should focus on development work, not planning meetings.

D.

No, because planning should be handled by project leaders, with Team Leaders informed later.

Buy Now
Questions 29

As Project Increment 4 progresses, the project team must choose the MOST effective communication methods for internal and external stakeholders. The Power/Interest Grid, created in the Foundations phase, is updated as needed when stakeholder influence or interest changes.

AgilePM-Practitioner Question 29

For each scenario in Column 1, select the MOST effective communication method from Column 2 to ensure successful

outcomes and minimize risk of failure. Each selection in Column 2 can either be used once only or not at all.

AgilePM-Practitioner Question 29

Options:

Buy Now
Questions 30

Answer the following question about the agile change practices that are being

used by the Change Manager.

Column 1 lists statements made by the change team. For each statement in

Column 1, select from Column 2 the relevant agile change practice being

used.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1

      A new company logo, which

maintains features of the

existing UniCo logo, but also

represents expertise in

innovative solutions and mobile

applications, is needed as a

high priority for the rebranding

of UniCo.

      Next time we work with the

Sales Team we will need to

schedule the fast-track training

of the Sales staff more carefully

as taking a member of staff

away from the sales work

caused operational issues.

3. Gaining access rights to make

amendments to UniCo ' s new

finance system is currently

causing issues and holding up

the updates to enable the

system to work with the new

processes.

    The company procedures for

delivering large-scale computer

systems will need to be revised

to reflect the new processes for

mobile applications, taking an

estimated 60 days of effort.

AgilePM-Practitioner Question 30

AgilePM-Practitioner Question 30

Options:

Buy Now
Questions 31

Which information could be recorded on an ‘empathy map’ for the marketing staff?

Options:

A.

The Promotions Team Leader has noted that staff have raised concerns about how the change may reduce their sales during the seasonal promotions.

B.

The Marketing Manager has identified potential stakeholders, drawn symbolic figures of each of them and positioned them on a visual diagram.

C.

The Marketing analyst staff have made a list of potential stakeholders and plan to share this with everyone else at the next sales meeting.

D.

During a meeting of Brand Team Leaders, each participant created a list of stakeholders and then compared these lists in small groups.

Buy Now
Questions 32

Which stakeholder should be placed within the ' primary ' segment?

Options:

A.

Industry-related professional associations, whose strong opinions and judgments about industry trends reach wide audiences.

B.

The Utilities company, who selected UniCo to provide services but will dictate their specific requirements and operational terms.

C.

The Operations Director, who will consult with others to understand their requirements and decide on the approach.

D.

The UniCo investors, who have provided the finance to support the innovation and improvement needed to recover profitability.

Buy Now
Questions 33

Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?

Options:

A.

Rebranding gives the company a modern look that has been missing historically.

B.

Comprehensive training is required to broaden skills, that are recognized as best practice.

C.

Increased effort will be needed initially to learn the new supporting business processes.

D.

This gives an opportunity for all staff to be involved and engaged in shaping the change.

Buy Now
Questions 34

The Sales Manager is excited by the challenge to lead a pilot to upskill the sales team in the new capabilities. They will particularly enjoy coaching and spending time with team members.

Which preference does this behavior BEST display?

Options:

A.

Extravert.

B.

Introvert.

C.

Thinking.

D.

Feeling.

Buy Now
Questions 35

The Change Manager has read Goleman ' s articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that

leadership style can improve organizational culture and performance as measured by staff surveys.

Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the

organization.

Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each

recommendation in Column 1, select from Column 2 the ' dimension ' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be

used once, more than once or not at all.

AgilePM-Practitioner Question 35

AgilePM-Practitioner Question 35

Options:

Buy Now
Questions 36

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Are the measures and source data to be monitored by the Human Resources and Facilities Manager likely to have any of the limitations of data analytics?

Options:

A.

No, because reporting on staff data should only be carried out by Human Resources.

B.

No, because internal processes are likely to ensure a good data quality.

C.

Yes, because the volume of the source data is likely to be unmanageable.

D.

Yes, because the source data is unlikely to provide ‘real-time’ accuracy.

Buy Now
Questions 37

Answer the following questions about applying the principles for building

engagement to the Change Programme, defined by Hodges.

Which 2 actions demonstrate inclusivity?

Options:

A.

Consider providing everyone at the next staff event with pens and notebooks with the UniCo logo and an image representing this change programme.

B.

Define in early key messages how the inclusion of Selco links to the strategic repositioning of UniCo in the marketplace.

C.

Encourage the team from Selco to continue to use their old logo as a way of maintaining some familiar symbolism they can identify with.

D.

Provide opportunities for staff who had volunteered to act as mentors during the Change Programme to meet to resolve resistance issues.

E.

Invite those staff who are asking questions about the Change Programme proposals to suggest what might work for them.

Buy Now
Questions 38

The Legal Specialist has reviewed the plans for the rebranding work and has assessed how this will affect current and future contracts. They are now pressing the Change Manager to establish the deadlines and to schedule when their input will be most needed.

Which preference does this behavior BEST display?

Options:

A.

Thinking.

B.

Feeling.

C.

Judging.

D.

Perceiving.

Buy Now
Questions 39

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?

Options:

A.

Is good at quietly implementing directions without challenging decisions at every step.

B.

Is well-positioned to bring together other line leaders facing similar change situations.

C.

Has a strong network due to supporting all staff at all levels organization-wide.

D.

Has direct line authority over the staff who will be changing internal IT systems.

E.

Wants to gain experience in change management to improve future implementations of IT systems.

Buy Now
Questions 40

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Within Sales, which 2 people would be the BEST candidates to use as change agents, based on the descriptions given?

Options:

A.

The Sales Director, who is keen to sell mobile applications to clients and manages the department.

B.

One of the existing long-standing members of the Sales staff, who is good at getting things done across the organization.

C.

One of the existing members of the Sales staff, who is resistant to the change but is diligent and responsible in all tasks.

D.

One of the new members of the Sales staff, who has previous experience selling mobile applications.

E.

The Sales Administrator, who ensures that the sales processes run smoothly and works with all levels of Sales staff.

Buy Now
Questions 41

Which statement should be recorded under the High-level timing considerations heading?

Options:

A.

The traditional market has changed over the last year and UniCo can no longer rest on its previous success.

B.

UniCo lost significant market share in the last six months and faces ongoing increased competition in the next year.

C.

UniCo’s new finance system was delivered in the last quarter and training in the new system is almost complete.

D.

Completing the large contract with a Utilities company over the next nine months is a vital step to achieving the end vision.

Buy Now
Questions 42

Which tool is likely to be the MOST useful in a co-design workshop for summarizing staff or customer reactions to a situation?

Options:

A.

Project plan.

B.

Empathy map.

C.

McKinsey 7s Model.

D.

Establish and discuss basic principles for interaction at the start of the workshop.

Buy Now
Questions 43

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.

Some of the employees of UniCo are unhappy that they have been given no choice in losing additional leisure space to accommodate the transferred Selco employees. The Change Manager has arranged for affected members to meet with the Selco employees at a social lunch.

Is this an appropriate approach to reward the brain in the need for ' autonomy, ' and why?

Options:

A.

No, because ' autonomy ' is best rewarded by establishing clear change expectations.

B.

No, because encouraging social interactions rewards the brain’s need for ' relatedness. '

C.

Yes, because ' autonomy ' is best rewarded by listening and supporting affected staff.

D.

Yes, because inviting colleagues to interact will make staff feel less powerless.

Buy Now
Questions 44

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?

Options:

A.

Refuse to discuss any detailed requirements in the early phases.

B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.

C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.

D.

Capture the Marketing Director ' s requirements in detail but leave the

input of others until later in the project.

Buy Now
Questions 45

The Web Content Manager has provided the Web Developer with a mock up

of the ' Contact Us ' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads ' Delete ' instead of ' Cancel ' .

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Buy Now
Questions 46

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

' all members of the project understand and accept the DSDM approach ' .

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Buy Now
Questions 47

A difference of opinion on the outcome of an earlier project has created a

' them and us ' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

Options:

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.

Buy Now
Questions 48

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

Options:

A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Buy Now
Questions 49

Which 2 actions should the Team Leader take to implement the new Must

Have requirement?

Options:

A.

Consolidate and circulate an agenda for the workshop.

B.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

C.

Discuss the development interfaces and dependencies with the Solution

Development Team to ensure the associated Timebox is appropriate.

D.

Agree to de-scope Should Have and/or Could Have requirements to allow

for the new Must Have functionality.

E.

Source and hire a web developer with experience in developing online

financial transaction functionality.

Buy Now
Questions 50

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

Options:

A.

Create an email group for the Solution Development Team to collaborate

on ideas.

B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.

C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.

D.

No action required as these employees are located in the same office.

Buy Now
Questions 51

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

AgilePM-Practitioner Question 51

Options:

Buy Now
Questions 52

Xan Insurance Company is a friendly company with no separate private offices

for individual managers. Staff members prefer to wander around the office

space and have one-to-one chats rather than use email or have lots of

meetings.

What action should the Project Manager take when planning for effective

communication throughout the Web project?

Options:

A.

Identify those individuals with power and influence over the project and

what information they require.

B.

No action is required as the existing form of spontaneous informal

communication is suitable for all project level and Solution Development

Team members.

C.

As this is already common practice, assume all Solution Development

Team members have effective communication skills.

D.

Mandate the use of email so that all communications are recorded for

future reference.

Buy Now
Questions 53

Which 2 actions should the Business Visionary take to implement the new

Must Have requirement?

Options:

A.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Ensure the marketing and sales teams are working together to deliver the

most effective outcome.

E.

Consolidate and circulate an agenda for the workshop.

Buy Now
Questions 54

Which 2 actions should the Workshop Facilitator take to implement the new

Must Have requirement?

Options:

A.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

B.

Consolidate and circulate an agenda for the workshop.

C.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

D.

Assess the impact of the additional development costs on the original

Business Case.

E.

Encourage all parties to contribute, irrespective of their views.

Buy Now
Questions 55

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Apr 19, 2026
Questions: 184

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99