An external web developer is to be contracted to create the new coffee bar
insurance area on the existing web site. The chosen web developer will only
agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.
Which 2 actions should the Business Visionary take to implement the new
Must Have requirement?
Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the
agreement of the team.
Which Agile principle MOST influences this course of action?
Which 2 statements explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary?
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the
responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-
ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside
the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs
are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to
all interested parties.
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully
meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture
Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's
specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,
until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
Maintainability is a required attribute of the initial delivered solution
Deliver first, re-engineer later
Short-term, tactical solution
The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in
the gardens could be enjoyed.
Which Agile principle MOST influences this course of action?
Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
'all members of the project understand and accept the DSDM approach'.
What action should the Project Manager take?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.
Which information is MOST likely to be relevant for the change agents when being inducted into the change programme for the Operational delivery processes workstream?
The Applications Manager agreed to the acquisition by UniCo because they knew that growing Selco needed more investment than they could raise and that they personally didn’t have the skill set to move from technical leader to business leader.
Which preference does this behavior BEST display?
Answer the following question about Schein's concept of survival and learning
anxieties.
Column 1 is a list of messages about the change given to Sales staff. For each
message in Column 1, select from Column 2 the appropriate element of
Schein's concept of survival and learning anxieties. Each selection from
Column 2 can be used once, more than once or not at all.
Which tool is likely to be the MOST useful in a co-design workshop for summarizing staff or customer reactions to a situation?
Two Sales staff members appear to have lost energy for the change process and did not attend recent change meetings. When questioned, they said they were so overwhelmed by the number of changes in systems, materials, technical knowledge, and processes that they couldn’t deal with any more.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance from staff?
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions.
Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.
The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director's leadership team in the UniCo building. At the last Operations' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.
Is this an appropriate approach to reward the brain in the need for 'status', and
why?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 Sales Team Leaders (TL) are likely to be the line leaders MOST engaged in implementing change, based on the actions that have occurred to date?
Answer the following question about the agile change practices that are being
used by the Change Manager.
Column 1 lists statements made by the change team. For each statement in
Column 1, select from Column 2 the relevant agile change practice being
used.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1
A new company logo, which
maintains features of the
existing UniCo logo, but also
represents expertise in
innovative solutions and mobile
applications, is needed as a
high priority for the rebranding
of UniCo.
Next time we work with the
Sales Team we will need to
schedule the fast-track training
of the Sales staff more carefully
as taking a member of staff
away from the sales work
caused operational issues.
3. Gaining access rights to make
amendments to UniCo's new
finance system is currently
causing issues and holding up
the updates to enable the
system to work with the new
processes.
The company procedures for
delivering large-scale computer
systems will need to be revised
to reflect the new processes for
mobile applications, taking an
estimated 60 days of effort.
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions. Answer the following questions about the use of David Rock’s SCARF framework to increase the motivation for change.
One aim of the relocation is to develop a less hierarchical culture. The relocation team hear that staff believe managers are still getting special treatment in the allocation of desks. To mitigate this concern, they have planned for groups to move separately over a few weeks and have communicated details with each group independently.
Is this an appropriate approach to reward the brain in the need for ‘fairness,’ and why?