Given this information regarding a Task:
Planned Start Date: May 14
Actual Start Date: May 14
Planned Completion Date: May 20
Projected Completion Date: May 22
Percent Complete: 50%
Duration: 5 Days
Planned Hours: 8 Hours
Status: In ProgressIf today's date were May 19, what would be the Task's progress status?
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?
A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?
The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.
Which task settings should be configured to meet these requirements?
A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.
What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.
What may have caused the planned start date of Task 2 to remain the same?
A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.
What impact does this have on the project progress status?
A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.
What action should the task owner take?
A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?
An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?
A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?