AD0-E911 Adobe Workfront Project Manager Certified Professional Questions and Answers
Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.
What may have caused the planned start date of Task 2 to remain the same?
Which group of project elements can be used to monitor an active project’s progress?
A project manager wants to see all of the assignees for each task in a project.
Which field should the manager reference to view all task assignees?
A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.
How should the project manager keep these team members apprised of updates?
Which project elements can be used to measure a project’s adherence to its original schedule?
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?
A team wants to combine structured project planning with the flexibility to manage tasks in sprints.
Which Workfront methodology allows for this hybrid approach?
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads " Project cannot be marked Complete if there are open issues and tasks that are not complete. " How can the Project Owner determine which tasks are incomplete?
A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.
What impact does this have on the project progress status?
A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.
Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?
A user wants to know if a task is pending approval.
Which task field would the user review?
A user wants to add users to a proof based on who requested the project and the additional approvers listed in the request.
Which Workflow should the user choose?
A marketing team wants to manage their projects using a traditional, sequential approach where each phase must be completed before the next begins.
Which project management methodology in Workfront supports this approach?
Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?
A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.
What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?
The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?
A contract requires custom billing rates.
Where can a project manager update this on the project?
A copywriter wants to see his incomplete tasks for projects to which he is assigned.
Which steps should the project manager take to create a custom Workfront report with this information?
A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?