Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

AD0-E911 Adobe Workfront Project Manager Certified Professional Questions and Answers

Questions 4

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

Options:

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

Buy Now
Questions 5

How is the primary assignee of a task determined?

Options:

A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

Buy Now
Questions 6

Which group of project elements can be used to monitor an active project’s progress?

Options:

A.

Gantt chart, project Condition, and Metrics

B.

Risks, planned hours, and resource utilization

C.

Project status, Updates, and Sharing

Buy Now
Questions 7

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

Options:

A.

Assigned To

B.

Assignments

C.

Assigned

Buy Now
Questions 8

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

Options:

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Buy Now
Questions 9

Which project elements can be used to measure a project’s adherence to its original schedule?

Options:

A.

Number of tasks, actual completion dates, and project status

B.

Project baselines, planned completion dates, and actual completion dates

C.

Workload balancer data, planned completion dates, and expenses

Buy Now
Questions 10

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

Options:

A.

Actual Completion Date

B.

Progress Status

C.

Status

Buy Now
Questions 11

An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?

Options:

A.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. From the Reporting Settings dropdown, add a prompt for Portfolio Name.

B.

Visit the Reports area and create a new Project report. Group the results by Portfolio Name. Add a column for Actual Cost and summarize this column by SUM.

C.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. Group the results by Portfolio Name.

Buy Now
Questions 12

A team wants to combine structured project planning with the flexibility to manage tasks in sprints.

Which Workfront methodology allows for this hybrid approach?

Options:

A.

Scrum

B.

Waterfall

C.

Kanban

Buy Now
Questions 13

All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads " Project cannot be marked Complete if there are open issues and tasks that are not complete. " How can the Project Owner determine which tasks are incomplete?

Options:

A.

There are incomplete approval workflows on one or more tasks. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

B.

There are incomplete issue predecessors that need to be resolved. The Project Owner can navigate to the project issues section in the left navigation pane to see the incomplete items.

C.

The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

Buy Now
Questions 14

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

Options:

A.

The next team member cannot start his task.

B.

No impact as the task is not overdue.

C.

The project shows an At Risk automatic condition.

Buy Now
Questions 15

A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.

Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?

Options:

A.

Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.

B.

Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.

C.

Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.

Buy Now
Questions 16

Which date type on tasks can a project manager manually modify?

Options:

A.

Planned

B.

Estimated

C.

Projected

Buy Now
Questions 17

A user wants to know if a task is pending approval.

Which task field would the user review?

Options:

A.

Status

B.

Critical Path

C.

Priority

Buy Now
Questions 18

A user wants to add users to a proof based on who requested the project and the additional approvers listed in the request.

Which Workflow should the user choose?

Options:

A.

Automated

B.

Basic

C.

Manual

Buy Now
Questions 19

A marketing team wants to manage their projects using a traditional, sequential approach where each phase must be completed before the next begins.

Which project management methodology in Workfront supports this approach?

Options:

A.

Scrum

B.

Kanban

C.

Waterfall

Buy Now
Questions 20

Which two options are available with Workfront reports? (Choose two.)

Options:

A.

A chart report that references a multi-select custom field

B.

Planned date-based calendar reports

C.

Filters with a custom grouping

D.

An object name with more than 500 characters

Buy Now
Questions 21

Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?

Options:

A.

USER.NAME

B.

USER.ID

C.

USER.roleID

Buy Now
Questions 22

A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

Options:

A.

Load the project template once the team has bandwidth to start on the project.

B.

Create projects but leave the roles in place without assigning users.

C.

Create a custom status for Backlog to use prior to using the Planning status.

Buy Now
Questions 23

The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.

Which task settings need to be configured to meet these requirements?

Options:

A.

The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.

B.

The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and Duration set to 2 weeks.

C.

The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.

Buy Now
Questions 24

A contract requires custom billing rates.

Where can a project manager update this on the project?

Options:

A.

Project Details > Billing Information

B.

Project Settings > Access Levels

C.

Project Finances > Override Project-Level Billing Rates

Buy Now
Questions 25

A copywriter wants to see his incomplete tasks for projects to which he is assigned.

Which steps should the project manager take to create a custom Workfront report with this information?

Options:

A.

Visit the Reports page, create a new Project report, add filters for Project Status > Equal > Current and Project Owner ID > Equal > [User Name]

B.

Visit the Reports page, create a new Task report, and add the filter Task > Assigned To Role ID > Equal > Copywriter and Task Status > Not Equal > Complete

C.

Visit the Reports page, create a new Task report, add filters for Task Status > Not Equal > Complete and Assignment Users Name > Equal > [User Name]

Buy Now
Questions 26

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

Options:

A.

Utilization section

B.

Hours tab

C.

Finance section

Buy Now
Questions 27

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

Options:

A.

Status

B.

Condition

C.

Progress Status

Buy Now
Questions 28

Which two statements are true about Groups and Teams? (Choose two.)

Options:

A.

A Team can be assigned to a task, but a Group cannot be assigned to a task.

B.

Objects can be shared with either a Group or a Team.

C.

A Group can be assigned to a task, but a Team cannot be assigned to a task.

D.

Work requests can be routed to either a Group or a Team.

Buy Now
Exam Code: AD0-E911
Exam Name: Adobe Workfront Project Manager Certified Professional
Last Update: May 13, 2026
Questions: 95

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99