Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

Note! Oracle has retired the 1z0-244 Exam Contact us through Live Chat or email us for more information.

1z0-244 Oracle EBS R12: Advanced Supply Chain Planning Questions and Answers

Questions 4

Identify the three correct statements about the setups required to enable pegging within an ASCP plan.

Options:

A.

In plan options, if you use the Enable Pegging check box to enable pegging, the Planned Items field determines the Items for which pegging will be calculated.

B.

To enable Priority Pegging, select the Peg Supplies by Demand Priority check box In the plan options.

C.

Set the MSO: Firm Supply Allocation Window (Forward days) System Profile to the number of days to push any supply order forward to complete a Work Order, even if there is some excess. This ensures that the supply is not pegged to a Safety Stock.

D.

Set the MSO: Firm Supply Allocation Window (Backward days) System Profile to the number of

days to search backward from the Demand Date. The allocation of firm supplies is based on demand priorities within the Firm Supply Allocation window.

E.

To enable pegging for an Item, you must set the Pegging Item Attribute to any value except

-None."

F.

Setting the MSC: Use FIFO Pegging profile option to "Yes" pegs high-priority demands first to on- hand and firm supplies, and then continues with other existing and nonfirm supplies.

Buy Now
Questions 5

Exhibit.

You define a Supply Chain plan of type "Manufacturing Plan." In the Plan Options Main tab, you select Planned Items as "Demand schedule items and all sales orders" and select the Include Critical Components check box.

The Exhibit shows Bills of Material for Items A and B. It also shows the settings for the Include Sales Order check box on the Plan Options Organizations tabbed page.

Item A has Demand Schedules and Sales Orders for Organizations Ml and M2. Item B has only Sales Orders for Organizations Ml and M2.

Which three statements are correct in the above plan scenario?

Options:

A.

The critical components of Items A and B (Al, A3, and B3) along with the sandwiched Items A2 and B2 are planned in both Organizations. The noncritical components (A4, B1, and B4) are Ignored.

B.

All components of Items A and B are planned in both Organizations.

C.

The critical components of Items A and B (Al, A3, and B3) are planned. The sandwiched Items

(A2 and B2) and the noncritical components (A4, B1, and B4) are Ignored.

D.

Item A with Demand Schedules in Organizations Ml and M2 is planned.

E.

Sales Order demands of Items A and B for Organization Ml are planned and for Organization M2

are ignored.

Buy Now
Questions 6

For Make Items, the time required to make the Item If you have all of the Buy Items In Inventory and have to make all Subassemblies and the Item Itself Is called______.

Options:

A.

Processing Lead Time

B.

Cumulative Total Lead Time

C.

Cumulative Manufacturing Lead Time

D.

Postprocessing Lead Time

E.

Fixed Lead Time

F.

Lead Time Lot Size

G.

Variable Lead Time

Buy Now
Questions 7

Identify the statement that Is NOT correct.

Options:

A.

Oracle Warehouse Management uses Resource Warehouses to store Machine resources/Capital equipment needed in the Shop floor.

B.

Oracle ASCP recognizes Resource Warehouses as production facilities that require capacity planning.

C.

To use the capacity planning function of ASCP, each OPM production plant must own one resource warehouse.

D.

Complex routings are part of Oracle Process Manufacturing (OPM).

Buy Now
Questions 8

Identify the four correct features that Optimized plans automatically choose (on the basis of minimizing plan objective cost).

Options:

A.

Non-standard Work Orders

B.

Alternate Routings

C.

Substitute Components

D.

Purchase Requisitions

E.

Items

F.

Lead times

G.

Alternate Resources

Buy Now
Questions 9

Select two correct statements about standard operations.

Options:

A.

If you assign the operation code of standard operation in a routing, the standard operation information Is copied into the operation that you are currently defining.

B.

When defining resource setup Information, there Is no option of specifying the standard operations used during changeovers.

C.

You cannot modify the standard operation information after adding the information into your new operation.

D.

Standard operations are commonly used operations that you can define as a template for use in defining future routing operations.

E.

Standard operations are used only in a flow manufacturing environment.

Buy Now
Questions 10

Your client is using Global Forecasts. The client's Planning Manager states that Sales Order consumption is not working correctly. Identify two possible causes.

Options:

A.

In the Plan Options, on the Main tabbed page, "Do Not Spread Forecast" Is selected.

B.

In the Plan Options, "Schedule by" is set to "Promise Ship Date," but the Global Forecast uses Arrival Date for the Date Dimension.

C.

In the Plan Options, on the Organization Tabbed page, the Ship to Consumption level Is set to "Customer Zone," but the Customer's Site on the Sales Orders is not assigned to a Zone with Zone Usage set to "Forecast Analysis" in Order Management.

D.

The Item attribute Forecast Control for the Items is set to "None."

E.

In the Plan Options, on the Main tabbed page. Backward Days is set to "7," but the manufacturing calendar used for this plan has five-day work weeks.

Buy Now
Questions 11

Identify five Material Constraints.

Options:

A.

Effectivity Dates of Components In Bills of Material

B.

Effectivity Dates of Operations in Routings

C.

Resource efficiency and utilization

D.

Order modifiers

E.

Change of Shift timings

F.

Tolerance fences

G.

Substitute components

Buy Now
Questions 12

Identify four exception messages that are most likely to appear In an unconstrained plan.

Options:

A.

Order with Insufficient lead time

B.

Planned Order uses alternate DIM of Material/Routing

C.

Resource overloaded

D.

Items with a shortage

E.

Orders with compression days

F.

Order lead time constraint

G.

Supplier Capacity overloaded

Buy Now
Questions 13

The planning engine provides the detailed bills of material (BOM) and Routing information associated with an Item from the Planner workbench.

You right-click and item in the Navigator and select BOM/Routing. The shortcut menu displays some options to further navigate to specific information.

Which two option are NOT displayed?

Options:

A.

Components

B.

Where used

C.

Routing Operations

D.

BOM Item type

E.

Process Affectivity

F.

Substitutes

G.

Co-Products

Buy Now
Exam Code: 1z0-244
Exam Name: Oracle EBS R12: Advanced Supply Chain Planning
Last Update: Apr 14, 2023
Questions: 89